Professional Documents
Culture Documents
SUBJECT : Wiring, Cable Pulling & Installation of Wiring Accessories PROJECT No. : M1492
Discipline :
Architectural Structural M.E.P Interiors External Other (state) ...........
DOCUMENT DESIGNATION:
NO. OF
NO. DESCRIPTION / TITLE DOCUMENT NO. REVISION
COPIES
1 Wiring, Cable Pulling & Installation of Wiring Accessories M1492-MCL-MSS-024 00 1
DOCUMENT STATUS :
A – Approved (Work may proceed)
B – Approved with Comments (Work may proceed subject to incorporation of comments indicated)
C – Revise and Resubmit (Work may not proceed need to resubmit)
ENGINEER’S REPRESENTATIVE:
NAME: LORENZO
…………………………....... ELECTRICAL
INDICK DESIGNATION: ENGINEER
………………………....... 14-05-2020
SIGNATURE: ………………………… DATE: ………………………….
Corrections or comments made via submittals during this review do not relieve the contractor from compliance with the requirements of
the Contract Documents.
SUBJECT : Wiring, Cable Pulling & Installation of Wiring Accessories PROJECT No. : M1492
Originator Subcontractor:
QMS012 (UAE) 09/15 Rev A Page 1 of 1 Method Statement Comments Sheet Form
RAMS EVALUATION SHEET
Al Karamah Private School
Project name Project No M1492
– Phase 2
Wiring, Cable Pulling & Genfocus
Activity Installation of Wiring Subcontractor Electromechanical
Accessories Contracting EST.
Anticipated start date 15-05-2020 Issue/Revision number M1492-MCL-MSS-024
Status Comment
These RAMS are deemed to cover the requirements of MCL as per the MCL RAMS Pro-Forma (SAF 072) and are
A
suitable for purpose
B All MCL comments need to be incorporated into the RAMS before they can be accepted.
Reviewed
Status A achieved
The RAMS documentation submitted by the subcontractor should include the following
RISK ASSESSMENTS Yes ■ No PERSONAL PROTECTIVE EQUIPMENT Yes ■ No
COSHH (MSDS) Yes■ No EMERGENCY ARRANGEMENTS Yes ■ No
Yes ■
FULL DESCRIPTION OF METHODOLOGY AND MATERIALS, WASTE REMOVAL
SEQUENCE OF WORK
No
HOUSEKEEPING AND STORAGE Yes ■ No
commencement of works.
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Contents
Section A Register of Revisions
Section B Scope of Works to be undertaken
Section C Location of the Project
Section D Location of the Works to be Undertaken with the Project
Section E Site Access/Egress and Access to the Work Zone
Section F Emergency Contacts Details and Procedures
Section G McLaren Site Specific HSE Safety Induction
Section H Welfare facilities
Section I Personal Protective Equipment
Section J Plant/Equipment and tools to be Used
Section K Materials To be used
Section L Inspection and Test Regime
Section M Communication/Toolbox Talks/Training Requirements
Section N Works Permits
Section O Environmental and Waste Management
Section P Programme for the Works
Section Q Housekeeping and Storage
Section R Working at Height
Section S Occupational Health
Section T Sequence of Works/Activities
Appendices
Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets (to be provided by Subcontractor)
Appendix D Risk Assessments (to be provided by Subcontractor)
Appendix E Technical Information (to be provided by the Subcontractor)
Appendix F Inspection and Test Plans
Appendix G Third Party competency/certifications
Rev. No Date Reason for Amendment Amended By Signature Has this amendment been
(Name) briefed to the operatives
involved and have the
operatives signed the register?
This method statement has been prepared in conjunction with the following documents;
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
The Project premise is located at Al Rowdah, W14-01, Abu Dhabi as marked below.
Existing Services
As per current information, there are underground electrical cables for existing lighting poles within
the plot. Service identification checks using CAT scanner and trenches will be hand excavated in
various locations as per existing services drawing to locate any services running into, or close to the
plot.
A permit to dig must be obtained from McLaren prior to any excavations commencing.
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
site plan.pdf
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
In case of an Emergency/fire Alarm, all operatives, Staff and Visitors are required to report to the Assembly
Point, which is indicated on the site logistics drawing, as indicated by the symbol below. Where the registers will
be checked to ensure that no one is un-accounted. No one will be allowed to leave the assembly point until the
Emergency Response Controller confirms that it is safe to do so.
Assembly Point
Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available within the
First Aid Room and in the Main Office Reception.
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
On completion of the HSE induction, those involved in this activity will be briefed on the contents of the RAMS
by their respective Site Engineer or Supervisor. They will then be required to sign a RAMS Briefing Register
(SAF019 UAE) confirming that they have been briefed and that they fully understand the RAMS and what is
expected from them during the execution of the works.
Any operative who will be operating any plant or equipment will be required to produce a copy of their
competency certificate/card carried out by an OSHAD approved third party training provider to enable McLaren
to issue them with the Plant Operators Authorisation (SAF023 UAE).
Please ensure that any specific precautions for PPE as identified within MSDS/COSHH assessment or any
specific requirements by supplier/manufacturer are to be complied and adhered to.
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
1. Cable Roller
2. Hand Tools & Power Tools
3. Mobile Scaffolding
4. Ladder
5. Hydraulic Jack
6. Spindle Bar
7. Mobile Crane/Hiab
*Note: All relevant competency certificates to be submitted to HSE Officer/Eng./Advisor prior to start of any
activity.
All inspections and tests must be conducted in accordance with the work procedure approved with the Hold
and Inspection points signed off on the approved inspection and Test Plan and Check sheets.
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
During the Preparation of this RAMS the following training for the staff and operatives has been identified;
Item Description of Training Has the Training been If not, when will be
completed? (Yes/No) completed (Date)
1 Work at Height Yes
2 Using Abrasive wheel Yes
3 Manual Handling Yes
4 Banksman Yes
5 Lifting Operation Yes
6 Banksman Training Yes
*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.
Item Description of the Work Permit Permit Issued By Tick only applicable
1 Permit to Enter Confined Space McLaren
2 Permit for Lifting Operations. McLaren
3 Permit to Dig McLaren
4 Permit to work Hot cutting or Welding McLaren
5 Permit to Work in Ceiling Void McLaren
6 Permit for Roof Access McLaren
7 Permit to Work with Ladders, steps/scaffold McLaren
8 Permit to Work at Height McLaren
9 Permit to Work – Electrical above 110V McLaren
10 Permit to Work with COSHH Items McLaren
11 Permit to Work at External Face of The Building McLaren
12 Permit for Removal of Existing Fall Protections McLaren
13 Permit for Pressure Testing McLaren
14 Other Permit
Any other permits if required to be added
1. Metal Waste
2. Plastic Waste
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
3. General Waste
4. Concrete Waste
5. Food Waste
6. Hazardous Waste
7. Wood Waste
8. Cardboard Waste
Due to the nature of the works and the current site conditions, airborne dust will be minimal, however where
necessary and on unpaved roads, water shall be sprayed so as to minimize air pollution.
Where any plant is used, drip trays shall be placed underneath to catch any spilled oils or fuels. Oils and fuels
will be managed in accordance with the MSDS and the site Waste Management Plan.
Section P- Programme for the Works.
6 months
Combustible materials will be carefully managed and monitored in order to reduce the risk of fire.
Ite Description Preventative Measures, (see also within the Risk Assessments)
m
1 Back pain/sprain due to All Operatives will be briefed on correct lifting techniques and avoid
improper Manual handling heavy lifting altogether
2 Hand/Arm Vibration Any tools used that are prone to cause HAVS must be used in accordance
with manufactures guidelines and specification for avoidance of HAVS
3 Construction dust Area will be watered to minimise dust if required and housekeeping to
be carried out as and when required.
4 Noise Any work area producing over 85dBA will be required to provide ear
protection for any person in the areas with warning signs in place for the
areas (noise assessment to be carried out)
5 Sun Operatives will be required to wear long sleeve and pants to avoid direct
sunlight UV rays and drink plenty of water to avoid dehydration
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Relevant earth cables also to be pulled along with the main cables and shall be run adjacent to the
6.
main cables throughout the length. (Sizes as mentioned in approved shop drawings).
Care shall be taken at bending locations that minimum bending radius for cables shall be maintained
7.
as per the manufacturer recommendations.
8. A slack of 800mm shall be kept at the distribution board side for the purpose of termination.
9. Cables shall be secured to the containment system by using cable ties at regular intervals.
10. Cables shall be caped and sealed at both ends after pulling until glanding and termination is done.
Glanding and termination shall be carried out with approved materials – glands, lugs, cable ties (for
11.
dressing of cables inside DBs) and proper crimping tools.
Cables shall be identified at both ends mentioning size, type and where it is fed, using appropriate
12.
labels as per the specifications at 50mm below the gland.
Cable drum shall be positioned so that the pull from the drum to trench shall be as straight as
13.
possible.
14. Cable rollers shall always be used to guide the cable to the trench.
When pulling a cable to the duct the drum shall be placed such that the cable enters the duct in a
15.
smooth curve.
16. Check that the jacks and spindle are adequate for the size and weight of the cable drum.
Battens or other drum protections shall be removed carefully to ensure that any nails or tools do not
17.
damage the cables.
Make sure that there are no nails protruding from the drum flanges as these may result in injury
18.
while moving or handling the drum.
19. Ensure correct disposal of any excess materials.
20. Trench bottom shall be as level as possible and shall be free of stones.
Edges of the trench shall be free of stones, tools and other objects which may fall into the trench and
21.
damage cables.
22. Minimum depth of trench shall be as per approved drawings.
For cables to be pulled through ducts, ducts shall be cleaned before installation to be free from other
23.
objects.
24. Ducts diameter, thickness shall be as per approved shop drawings.
A shallow pit shall be dug at the entry point of duct to ensure that stones, etc are not dragged inside
25.
at the time of pulling the cables.
At all times during pulling, a member of team shall be stationed at the drum to control its rotation
26.
and to check the stability of the drum and jacks.
Cable laying shall be started in the direction recommended by the manufacturer and as indicated on
27.
drums.
28. The site supervision team will ensure that undue stress on pull is not applied to cables while laying.
29. Earth conductors shall be laid along with respective main cables.
30. Cables shall be caped and sealed at both ends after pulling until glanding and termination is done.
Glanding and termination shall be carried out with approved materials – glands, lugs, cable ties (for
31.
dressing of cables inside DBs) and proper crimping tools.
Cables shall be identified at both ends mentioning size, type and where it is fed, using appropriate
32.
labels as per the specifications at 50mm below the gland.
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
APPENDIX A
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
APPENDIX B
CRISIS PLAN
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
CRISIS PLAN
Upon an incident, being discovered the first member of McLaren’s staff or the site operative
1.
discovering the incident shall inform the Project Manager and HSE department by Project
Emergency no- 056 898 7960
Both the Safety Officer and the first Aider are to attend the scene with their mobile. The project
2.
Manager or site receptionist waits in office ready to telephone relevant emergency services.
Both the Safety Officer and the first Aider are to assess the situation and put in place the relevant
3.
systems to end/deal with the emergency.
Both the Safety Officer and the first Aider are to ensure all trades are gathered at the assembly
4.
point and liase with supervisor to account for all operatives - no person should leave site.
Either the Safety Officer or the first Aider phones the project Manager or site receptionist and
5.
informs him/her of which emergency services are required.
Both the Safety Officer and the first Aider keep trades informed of the situation and releases trades
9.
to return to work or leave site only when emergency services or The Project Manager instruct that
it is safe to do so, and all names of witnesses are recorded.
The Project Manager or Construction Manager are to arrange for photographs of the scene to be
10.
taken, and if necessary, the area to be cordoned.
A full investigation of the Incident is to be carried out, with a written report being submitted the
11.
SHEQ Director, as soon as practicably possible after the incident, including all witness statements,
photos of the scene, induction and method statement records, recommendation to prevent a re-
occurrence and what action has been taken since the incident taking place.
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
APPENDIX C
(Attach if any)
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
APPENDIX- D
RISK ASSESSMENT
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
1
1. Delivery/ collection drivers shall be subject to
McLaren induction/Training with regards to
traffic management.
Plant and 2. Ensure exclusion zone is set up around the
Traffic preparation work area and all plant
movement movement and checked by supervisor
3. Always use the pedestrian access provided
Run over by 4. Traffic light batons shall be provided for
Delivering,
vehicles/plants banks man at night
unloading and 5. All plant to have a fully trained and certified
storing of Hit by reversing
banks man present all times.
Cable/wire Drums equipment
Operatives 6. No plant to reverse without banks man. Site Eng.
materials using Overhead Staff/visitors
1 7. Ensure access route are sufficient and safe to Supervisor,
pickup and obstructions 3 4 12 Med 1 4 4 Low
use. Foreman,
unloading by Crane break
manual 8. Do not take rest in or under vehicles
down
handling/using 9. Proper barricade and safety signboard
Over turning of
Mobile Crane/Hiab provided on open excavation
Crane
for heavy load 10. All vehicles/Crane/Hiab must be fitted with
Collision with reverse alarm / Flashing light.
other vehicles 11. The work place and all access to be well
Personal injury illuminated.
12. Enforce Speed limit
13. Ensure all vehicles entering the site is
properly maintained and reported if found
any defect
14. Ensure materials are secured/tied in pallet
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
that.
10. The ladder securely fixed to prevent
slipping outwards or sideways or securely
footed at all times.
11. Person must hold the ladder while another
operative working on it
12. Materials should not be placed above the
thread of ladders/step ladders
13. Do not carry any materials in one hand
while climbing or getting down from ladder
14. Ensure the area under the ladder is
barricaded especially if it is being used in a
public area.
15. Ensure the ladder is electrical insulated
podium type if working in live services
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
replacement.
13. Instruct workers to keep their hands warm
and dry, and to not grip a vibrating tool too
tightly.
14. Hot work permit should have obtained if
using heat gun.
15. Fire extinguisher/Fire blanket must be in
place
16. Fire watcher must monitor the hot work area
and he will not move until there is any smoke
or heat.
17. Ensure proper earth leakage protection is
provided.
18. power tools must be 110V to be ensured.
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
Safety
Activity: Wiring, Cable Pulling and Installing of Wiring Accessories Prabir
Officer
2
3
4
5 Approved By: Name Vishnu Mohan Position __PM_______ Signature _____ ____ ___________
1. Executing Steps:
1.1. Planning
a) Construction and HSE team must ensure that hazard identification is complete.
b) Construction and HSE team must prioritize the hazard issues, which are of significant in nature. (It means that
risks have well established legal requirements, potentially high risks).
c) Construction and HSE team to prepare the risk assessment plan for the priorities identified hazards for these
potential high risks.
APPENDIX-E
TECHNICAL INFORMATION
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
APPENDIX-F
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date:
Construction Compliance
Prepared By: Anandu Ashokan Checked and Approved by: Vishnu Mohan Completion approved by:
(I have read the specification and relevant drawings) (Project Manager or nominee) (Project Manager or nominee)
APPENDIX-G
Title: Wiring, Cable Pulling & Installation of Wiring Accessories Ref. No: M1492 MCL-MSS-024
Project: Al Karama Private School, Abu Dhabi, UAE Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: