Method of Statement of
PC Footing
TABLE OF CONTENT:
INDEX
NO. Content
Scope of work
Reference
Prior to activity
Procedure of execution
Quality control
- Scope of work :
- References :
Contract documents
Structural and architectural drawings issued for construction
Egyptian code of practice.
-Materails :
Equipments :
Concrete pump
Concrete vibrators
Water tankers
leveling
Total station
- Prior to activities:
A-Surveyors :
Responsible for :
- Checking the limits of excavation
- Checking the levels and to locate the secondary surveying points of the
footing & building axes.
C- Site engineer:
Responsible for:
- Ensuring that project is managed in a safe manner and meets the
requirements of the documentation.
- Ensuring that subcontractors and suppliers achieve on-site required
standards.
-Ensuring the performance measurable is delivered.
- shall refer to QC engineer and HSE officer for advice and guidance if
required.
- shall ensure that operatives comply with the relevant method of statement
, toolbox talks and general site briefing .
D- QC engineer:
Responsible for:
- Carrying out phased inspection as required
- ensuring that completed work are offered for inspection/approval to
TEBR within specific dates.
- ensuring that all required tests are performed and are in compliance with
appropriate specification.
- ensuring that materials are inspected when delivered to insure they
comply with various specification.
- prepare reports for submission to IECS project manager and where
required.
- controlling all non-conforming products or workmanship and
implementing the required prevention action.
- ensuring the corrective action and prevention actions are taken when
required.
- Procedure of execution:
-Setting out the secondary surveying points and footing corners and axes
using total station from the base points ( , )
- Curing concrete must be take place after casting for one day (day and
night) using the approved mixture (master kure) which mixing by water to
make curing emulsion under supervision of QC engineer.
- IECS shall prepare concrete cubes to be submitted to the site lab. and
all Curing and testing procedures for cubes and reports to be handled by
the lab’s personnel under supervision of TEBR.
nd
stage at level ( ) for typical pc footing:
nd
Repeat the previous steps of execution for stage.
rd
stage at level ( ) for stripe footing for R.W.:
nd
Repeat the previous steps of execution for stage.
- Quality Control :
For pc footing:
- All safety rules for all site personnel shall be applicable in accordance of
the approved HSE plan (i.e. wearing helmets and vests… etc.)
- At all time IECS shall monitor the work so as far as reasonably practical
the storage of rubbish, waste materials and debris at work face . all waste
materials shall be removed from the workplace to suitable areas.
-END-