TO ALL BIDDERS:
Item
1. Updated reference documents
Please note the provided reference documents are for Contractor’s validation.
3.5.1.2. The pumps shall be suitable and achieve the best energy efficiency for all
operating and flow conditions. Pump efficiency should be at least 86%.
The entire process shall be proven prior to practical completion being given.
A complete list of all standard settings and adjustments necessary to variable plant shall be
provided by the Contractor.
4.3.1.1 Piping - ISO7005-1/2, minimum of PN16 or higher depending on pressure, Pipe type-
Steel pipe, Inside Coating-406 microns epoxy lining (pumping). Outside coating-coal
tar enamel coating (buried) per AWWA 203 & rubber alkyd paint coating(exposed)
Item
per AWWA 218 and coating with PE sheets. Analyze for transient condition
(surge): Bentley Water Hammer Surge Analysis and AWWA piping design.
4.3.1.7 Gate Valve - for drain and blow off valve, Drain/blow off valve on all low points of piping.
Should be of flange type.
4.3.1.8 Check valves should be single disk and non-slam type with air cushion or lever arm with
counter weight or approved equivalent.
4.3.1.9 Double acting Air release valve shall have at pump discharge and header pipe and all
high points of piping with isolation valve. Single-acting air release valve shall be
installed for pump suction.
4.3.1.10 Pressure gauge shall have at pump suction, discharge and header pipe with
isolation valve and manual drain.
4.3.1.11 Surge anticipation valves shall have 1-duty and 1-standby, with isolation valve, sized for
5 m/s discharge maximum velocity of pumping system
4.3.1.12 Wye strainers must be readily maintainable while still installed along the pipeline.
• Design the drainage and flood management system of the facility using
computer modelling software or design templates that incorporates the
latest applicable codes and standards.
• Carry out checks for conformance of work per design and specification.
The CONTRACTOR shall carry out slope stability analysis for critically identified slopes.
The CONTRACTOR is responsible for the design and construction of the approved
slope protection as needed.
The CONTRACTOR shall make all the necessary excavations for foundations to grades
indicated on Drawings. The CONTRACTOR shall also conduct all excavation, grading,
rehabilitation, slope protection, and other site development works that are needed
beyond the perimeter fence up to the property line. The CONTRACTOR shall carry out
least excavation for site development.
4.6.5.2 Electronic copies of all drawings and documents shall also be provided on USB flash
disks. The electronic copy shall be MS word for all text; AutoCAD latest edition for
drawings, and Adobe Acrobat PDF for the entire document inclusive of all appendices
and sections.
4.8.4 Contractor shall conform to the scale of the following contents of as-built drawings.
a. Vicinity map (1:10,000 scale)
b. Key plan (1:5,000)
c. Plan (1:500)
d. Plan and profile – horizontal (1:500) and vertical (1:100)
e. Details – Plans and Tie-ins (1:100) and Sectional details (1:20)
4.8.5 The Plan shall contain and reflect the following information:
a. Pipes: include location, length, size and thickness
b. Fittings: include location and size
c. Appurtenances: location and size
d. Cross-under/ Cross-over: location
e. Interconnection/ Looping: location
f. Property limits: include household locations
4.12.1.2 CONTRACTOR shall refer to MANILA WATER Factory Acceptance Test (FAT) Guide and
will submit a list of equipment that will require factory acceptance test (FAT) to
MANILA WATER for approval. CONTRACTOR shall arrange the approved FAT for
designated MANILA WATER representatives specified in the FAT Guide. All costs and
arrangements for FAT activity/ies shall be by the CONTRACTOR. As a general rule, all
equipment that has not gone through accreditation by MANILA WATER shall be
subject to FAT.
4.12.1.3 CONTRACTOR shall prepare and submit all documents detailed in the FAT Guide and
shall take note of all the responsibilities specified therein.
The total duration of the design, construction and commissioning shall be 400 calendar days
(inclusive of 2 months commissioning and trial operation). Defects Liability period shall be
twelve (12) months after the successful Trial Operation Period.
Item
16 Update on section 3.6 (Electrical, Instrumentation and Control)
3.6.1.7 Medium-voltage motor efficiency shall be at least 93% at the specified operating
point;
3.6.1.8 Pump operation shall be linked to Boso-boso reservoir, and dependent
downstream facility/ies;
3.6.1.9 One hundred percent (100%) backup-up power prime rated diesel genset shall be
provided for pumping station;
3.6.1.10 Prepare detailed design, drawings, specifications for review and approval by the
Client.
4.4.12 Others
4.4.12.2 MCC Room shall be placed with high consideration of safety of site
personnel, e.g. distant from pumps in case of leakages or bursting of pipes.
4.13.1Drainage
f. Contractor shall ensure that site drainage system shall be connected to a municipal
drainage line.
4.3.1.11 Surge anticipation valves shall have 1-duty and 1-standby, with isolation valve,
sized for 5 m/s discharge maximum velocity of pumping system. The contractor
shall design and include the stub-out (with isolation valve and blind flange) for
the future SAV’s for the additional 220MLD of this Pumping Station.
22 Update on section 3.6 (Electrical, Instrumentation and Control)
Truly yours,
LOVELY ORTACIO
Procurement Manager
Supply Chain Management