TABLE OF CONTENTS
1. General ........................................................................................................................................................................................................................... 3
2. Scope of work ................................................................................................................................................................................................................. 3
3. Location .......................................................................................................................................................................................................................... 3
3.1 STR & ATR Area ............................................................................................................................................................................................................ 3
3.2 PTR Area ....................................................................................................................................................................................................................... 4
4. Resources ........................................................................................................................................................................................................................ 5
5. Time Programme ............................................................................................................................................................................................................ 5
6. Method of Work ............................................................................................................................................................................................................. 6
6.1 Flow Chart of Work ................................................................................................................................................................................................. 6
6.2 Sequence of Work ................................................................................................................................................................................................... 7
6.2.1 Work Cycle of Exposed Column at STR & ATR Area ........................................................................................................................................ 7
6.2.2 Work Cycle of Exposed Column at PTR Area .................................................................................................................................................. 8
6.2.3 Preparation work ............................................................................................................................................................................................ 9
6.2.4 Rebar assembling and exposed concrete column casting ............................................................................................................................... 9
7. Inspection and Test Plan ............................................................................................................................................................................................... 10
8. Safety Plan .................................................................................................................................................................................................................... 10
9. JSA (Risks and Mitigation) ............................................................................................................................................................................................. 11
2
1. General
This document is describing general part of the method for column structure. This document includes the scope of work, location,
resources, work method, safety plan. The specific part of the method such as traffic management plan, environmental plan, the
specific schedule, resources will be submitted separately.
2. Scope of work
The scopes of work are stated as follows:
Preparation work
Install rebar
Casting work
3. Location
3
3.2 PTR Area
4
4. Resources
This activity will be conducted using some equipment, materials and labor as stated in below table:
No Description Quantity
Equipment
1 Cutting Wheel 1 Unit
2 Concrete Pump 1 Unit
3 Vibrate 1 Set
4 Formwork 2 Set
Material
1 Rebar As Designed
2 Concrete As Designed
3 Plywood and timber As Designed
4 Rebar Wire As Needed
5 Concrete Decking As Needed
Labour
1 Supervisor 1 Person
5. Time Programme
The detailed schedule for structure work at equipment building is shown as time schedule
5
6. Method of Work
START
SHOP DRAWING
MARKING AND
SURVEY
REBAR FABRICATION
REBAR INSTALLATION
According to SNI 2847-2019 and
EN 1992.1.1 Part 4 , Steel Rebar
on BJTS 50 Mpa cannot be welded
FORMWORK
INSTALLATION REPAIR
REINFORCEMENT
NO
CHECK
REINFORCEMENT
ACCORDING TO SHOP
DRAWING YES
CONCRETE CASTING
FINISH
6
6.2 Sequence of Work
1
1 2
Stage 1
5
2
Stage 2 3
16
4
Stage 3
Stage 4 3
15
5
Stage 5
6
Stage 6
6 4
Stage 7 7
14
13
7
9
11
10
7
6.2.2 Work Cycle of Exposed Column at PTR Area
1
1
Stage 1 2
Stage 2 2
5
8
6.2.3 Preparation work
We have to check the approved drawing & bar bending schedule before cutting the Rebar.
Workers must wear safety shoes, safety helmets, reflector vests, & gloves prior to rebar fabrication
Reinforcement assembly consists of fabrication, such as cutting, joining and installation work. This work shall be
carried out in accordance with the drawings, standards and related specifications. The rebar material will be sent to
the fabrication yard to carry out the fabrication work. The material being stocked and manufactured must be
protected with plastic sheeting and wooden logs to avoid rust and bearing supports in the lying area.
After fabrication, fabricated rebar will be installed, decking with the specified distance according to the construction
drawings.
First, the rebar assembly for the column sections will be installed on the overlap between the rebars using manual
shifting. Reinforcement must be installed with proper reinforcing wire. After that QC & Supervisor must check the
After the rebar checklist, we start the concrete work casting. Concrete casting work will be carried out using a concrete
pump or manually. Prior to equipment placement, site conditions should be checked by the concrete pump operator
Ready mix concrete will be transferred to a cast tub and then using a manual bucket and then poured into the column.
The workability of fresh concrete will be checked with a slump flow test on site prior to commencement of casting.
Concrete must be poured continuously with a monolithic process until the peak elevation is determined. Column
concrete must be cast in conditions without the addition of water using concrete K 350, slum 49 – 55, screening with
beige color.
Each m3 of concrete requires 60 kg of the beige dye. then it takes 2-3 days to open the concrete formwork.
9
7. Inspection and Test Plan
8. Safety Plan
Safety is an important thing that shall be enforced during column work activity. The relevant safety procedure will be
Personnel Standard Safety Tools, i.e. safety helmet, reflector vest, and safety shoes.
These safety tools shall be appropriate with the safety standards. Guna Mulya Cahaya will keep all of the personnel to always use
Safety for maintaining existing traffic, i.e. rubber cone, plastic safety barrier, red flag, traffic signboard, and other related safety
material. A safety office and flagman will be provided during activity to concern on safety matter and control existing traffic.
Safety on the equipment when operated; the around area of equipment shall be made sure of safe conditions. Guna Mulya Cahaya
will check the condition of equipment which shall be safe before use. The working radius of crane and maximum lifting load
Safety on the material; Safe location will be provided for the stock area of the material before used. During unloading the material,
a safety officer will make sterilization to the area from unimportant persons and others. Unloading of material will be guided by
special personnel and supported by workers. During loading and unloading, it shall be made sure that no one stands on the bottom
of the material when lifted up. It will prevent accident during this activity.
Safety Facilities; Guna Mulya Cahaya will provide safety facilities in the working area. The safety facilities will be including First aid,
10
9. JSA (Risks and Mitigation)
11
Risk Hazard
No. Work Sequence Potential Risk Determined Control
Categories Consequences
Iron tip sticking out Low Bleed, Injury Iron tip closed
Wear complete
body harness and
Fall accidentally Low slips, trips
notice board for
1 Install Rebar access
Install the electrical
Got electric shock High Die installation
correctly
slips, trips, fall &
Iron collapsed Medium Install steger
other injuries
slips, trips, fall & Structure must be
Scaffold Collapse Medium
other injuries strengthened
Adequate
Broken Formwork Low slips, trips
formwork frame
2 Install Formwork
Falling materials Wear complete
High Injury, Die
and components. body harness
12