Professional Documents
Culture Documents
GENERAL CONSTRUCTION
METHODOLOGY
FOR
ABUSAG BRIDGE PROJECT
A. INTRODUCTION
The objective of this narrative construction method is to guide and
familiarize the Contractor and the Owner regarding how civil works of the
project will be carried out. The foregoing procedure and methods are
formulated to attain the scheduled program of the project within the prescribed
contract time.
It is an over-all view of various aspects of construction activities
comprising of delivery of materials, deployment of equipment suited for the job
and combined expertise and cooperation of Contractor and the Owner.
However, this will be a continuous studying process to seek the highest
standard of workmanship and the introduction of better methods for the best
interest of the project.
B. PRELIMINARY WORKS
1. MOBILIZATION OF PLANT EQUIPMENT, MATERIALS and
PERSONNEL – upon receipt of Notice to Proceed (NTP) and construction
drawings, preparatory works for civil construction will start. Mobilization of
the equipment and management team for the job will be done at least two
(2) weeks prior preliminary site works especially the major works like
construction of detour road and bridge, bored piling and girder fabrication
works. All temporary works including the contractor’s camp facilities will be
installed including any proposed plant.
C. CONSTRUCTION IMPLEMENTATION
1. BRIDGE CONSTRUCTION REQUIREMENTS
4. EARTHWORKS
4.1. CLEARING OF SITE/ DEMOLITION, REMOVAL AND DISPOSAL
OF EXISTING BRIDGES ABUTMENTS, PIERS AND PCCP.
`
Step IV: REBAR FABRICATION AND INSTALLATION
Simultaneous to boring of piles, cage bars will be pre-fabricated nearby the
boring location. Rebar cages should be provided with stiffener ring space at 2m
each segment. Main bars should best if any welded to stiffener ring to ensure the
stiffness of cage. It will be transformed near borehole location for installation.
After the final depth of the borehole is reached and confirmed by the client,
rebar cages will be installed inside the borehole using service crane (Fig. E). Rebar
cages will be spliced during installation with certain number of main bars to be
welded to secure stability of splicing when lowered into the borehole. Take note that
the cage should hang up from the bottom of the borehole to provide a concrete
covering.
Step V: CONCRETE POURING
The pipes will be installed by segments using service crane (Fig. F). Concrete
will be poured into the borehole through tremie pipes (Fig. G). The pipeline will be
adjusted as the concrete fills into the borehole.
TEODORICO A. GUICO
Project Manager, FREY-FIL CORPORATION