CITY GOVERNMENT OF ADDIS ABABA

ADDIS ABABA HOUSING DEVELOPMENT


PROJECT OFFICE

GOTTERA SITE CONSTRUCTION OF MAIN&PEDESTRIAN

ACCESS ROAD PROJECT

WORK PROGRAM & METHODOLOGY

Submitted by:

CRBC ADDIS ENGINEERING PLC


P.O.Box 2509
Gottera site construction of main &pedestrian access road project
Tel. 0025-114-3919 71
Fax 00251-114-39 19 72
Addis Ababa, Ethiopia March, 2009

2
Gottera site construction of main &pedestrian access road project

INDEX

1.0 General Information of the Project


2.0 Mobilization of Material, Equipments & Personnel,
3.0 Organization and Staffing
4.0 Main Construction Plan and Detail Activities
4.1 Reinstatement of Alignment before Commencement of Works
4.2 Roadbed Construction
4.3 Pipe and outlet culvert Construction
4.4 Sub - Base and Base Construction
4.5 Bituminous Concrete Construction
5.0 Quality Control
6.0 Traffic & Safety measures

Appendices
a. Organization Chart
b. Proposed Overall Program

3
Gottera site construction of main &pedestrian access road project

Main &pedestrian access road project for Gottera site

Construction Methodology & Work Program


1.0 General Information of the Project

The project locate at around gottera interchange area. The project Contract
amount is ETB 22,895,191.64 including VAT & 10% contingency.

The work consist construction of 2.475 km of asphalt road including earth works, sub-
base, base, drainage and sidewalks. The following major construction activities will be
carried out:

 Earth Works, cut / fill & material (21,267m3)

 Sub-base pacing (3,550 m3)

 Base course placing (2,580 m3)

 Asphalt concrete wearing course (15,500 m2)

 Drainage Pipe installation ( 2,780 m)

 Concrete curb (10,500m)

 road signs & traffic marking (2.5 km)

2.0 Mobilization of Material, Equipments & Personnel,

1. Equipment:

As the project is located in the vicinity of the contractor’s existing camp sites, quarry

sites, crusher plants, asphalt plant and etc…, mobilization of resource can be easily

made from the central office following the scheduled commencement date of individual

activities whenever necessary. All equipment shall be kept in a good working condition

and carefully serviced before use in the central garage at Kality. The contractor will also

use its central laboratory at Kality and some instrument for routine site inspection

purposes shall be arranged on site for common use of the Engineer and the contractor.

2. Personnel

The key project management staffs including the project manager would be assigned

4
Gottera site construction of main &pedestrian access road project
within the mobilization period. All other site staff and manpower associated with the

central and common use plant and equipment are still on duty. All remaining technical

staff and skilled workers to be assigned for the project specifically shall be increased

gradually on the basis of the construction plan and actual progress.

3.0 Organization and Staffing

Appropriate and well organized site structure shall be organized under the project

manager’s office. The following sections will be organized and carry out their duty under

close supervision of the project manager: Engineering Section, Construction Section,

Personnel and Accounting Section, Material Procurement Section and General Services.

The construction section shall be further subdivided in to different crews as follows: Earth

works Crew, Pavement Crew, minor and major drainage Crews. The detail organization

chart is as shown in Appendix A.

4.0 Main Construction Plan and Detail Activities

4.1 Reinstatement of Alignment before Commencement of Works

1. Before the commencement of the major works, The Contractor will assure

the surveying works with sufficient details. This work consists of traverse,

centerline, level points, check-up the cross section of the roadbed, increase

the number of level points, make sure the level points, structures and

adjacent constructional sections, detecting any error in time, and report

them to engineer or the employer. The precision of surveying shall meet the

relevant specifications.

2. Check the traverse along the centerline and proceed with the stake out

survey works in accordance with design drawings. Check and correct the

surveying equipment. If the construction area exceeds the one that the

existing traverse points surround, the points need shifting, and assure good

visibility between traverse points.

3. Fix main controlling stakes. Pay attention to the center of the structures

such as culverts and check whether the centerlines of the adjacent sections

properly close while reinstating the centerline. Report the problems to the

engineer or the employer at once when certain errors occur.

5
Gottera site construction of main &pedestrian access road project
4. The hole work will be divided into three part according to the site condition.

The first part (road-2,8,9,10),the second part(road-11,3,4,7),the third

part(road-1,5,6) will be constructed in pipelining.

4.2 Roadbed Construction

These works shall be carried out under close supervision of the Engineer.
Detail stake out survey of level points shall be set jointly with the Engineer
before commencing the major construction. Complete data of all level points
shall be submitted to the engineer for approval.
a. Clearing and grubbing

This work will proceed following the setting out works. The clearance of the surfacing

shall be carried out using appropriate machinery. The depth of clearing shall be

determined as directed by the Engineer and in accordance of the width design.

Unsuitable materials shall be disposed off to a designated spoil area. When executing

the clearing works, the gravel materials which could be used afterwards, would be

stockpiled in a separate place as will be designated by the engineer.

Demolition of the existing structures shall be carried out upon the approval of the

engineer. The area shall also be properly backfilled and the recycled materials after the

demolition should be piled at a spot directed by the engineer, and kept in good condition.

The spoiled materials should be transported to a spoil area as directed by the engineer .

b. Roadbed excavation

All the road way excavation shall be carried out using bulldozer and excavators. The

excavated material shall be loaded and dumped to the designated places.

The earth fill roadbed shall be leveled by bulldozers at first, fine leveled by the graders

and rolled by the vibratory rollers. Rock filling shall be leveled by high-power bull dozers,

rolled by heavy vibration rollers.

c. Roadbed embankment

I. The degree of compaction and the minimum strength of the fill materials must

comply with the requirements of the specifications.

II. Since the thickness of this project is very thin, the fill shall be completed by one

layer. When the slope of the fill embankment is bigger than 1:5, make the original

ground into a step with a width of 2m and tamp it with smaller size machinery.

6
Gottera site construction of main &pedestrian access road project
III. According to the fill thickness and the width of the roadbed, calculate the required fill

quantity on every cross section, and level it with graders. Sampling will be taken to

measure the moisture and compare it with the optimum moisture content.

IV. After each layer is placed, Carry out compaction test following the interval as

specified in the standards and continue the second layer following the test results.

4.3 Pipe and outlet culvert Construction

4,3.1 Setting out of the surveying

a. A centralized surveying crew shall carry out the longitudinal and

transverse survey and locate the structures. The construction

surveying team shall also carry out the detail setting out and control of

works during construction.

b. Confirm the original level of the existing ground surface, in comparison

with the level at the foundation, take into account the geological and

terrain condition, a slope is determined and it will in general be

decided according to site condition.

4.3.2 Excavation works

a. Excavators are used in excavating the foundation pit. The excavation

shall be done up to 50 cm beyond the foundation width for

convenience and working space if it need the formwork setup,.

Unsuitable material shall be transported to a designated location.

b. The abutment and wing wall shall be constructed following the levels

and setting out data as specified in the design drawings.

c. Foundation treatment is employed if the capacity can not meet the

requirements of the foundation design. The treatment method shall be

approved by the engineer.

4.3.3 Concrete inlet and outlet works

a. Metallic adjustable scaffolding and form works shall be used for the

concrete slab construction.

b. Concrete shall be mixed from the central mixing plant and transported

to the site with truck mixers.

7
Gottera site construction of main &pedestrian access road project
4.4 Sub - Base and Base Construction

Sub base and base production shall be carried out and monitored by the central office for

different projects. The Engineer will have unrestricted access to check and control the

quality and methods of production.

4.4.1 Constructional method of sub-base

1. Prepare the materials for sub-base and make sure the grading and the quality

comply with the specification.

2. Setting out the surface along the centerline at intervals of 20m, outside the

edges using side stakes and clearly mark the levels on the side stakes.

3. Determine the requirement of loose volume on each section taking in to

consideration the shrinkage factor.

4. Check the moisture content and spray it again if the moisture is not sufficient.

5. Dump the sub-base material at uniform interval on the finished sub-grade and

spread to the required thickness and make sure that the surface is even and

smooth before compaction.

6. Check the road crown and traverse slope and continue compaction

7. During the rolling process keep the surface wet, and examine the degree of

compaction, until it reaches 95% which is specified in the specification. No

traffic will be allowed on the roadbed before the completion of the wearing

courses.

4.4.2 Construction method of base

1. Check up the grading & moisture content of the crushed stones, to see if they

are in accordance with the requirements.

2. Carry out leveling surveying following the data indicated in the design.

3. Determine the ratio between the layer thickness before and after compaction.

4. Dump and spread the material, right after unloaded from trucks.

5. Compact the material to the required density and check grade elevation.

4.5 Bituminous Concrete Construction

4.5.1 Surface finish and Prime Coat


1. The supervisor is required to give approval on the surface finish before
proceeding with the spray of the penetration asphalt. Some water should be
spread and wait to dry so as to facilitate easy penetration.

8
Gottera site construction of main &pedestrian access road project
2. The limits of spray area have to be clearly marked.
3. The surface must be cleaned against any pollutant foreign matter.
4. The penetration asphalt should be 50-90% bitumen and has to be applied
according to the Specification.
5. Spraying of bitumen should not be allowed during time of strong wind and
rain.

4.5.2 Bitumen concrete road surface


(I) Preparation for construction
a. Crushed stone of desired sizes should be stocked separately and protected
against wetting.
b. Mix Proportioning design should send supervisor for approval.
c. Clean the crushed rock base with broom and spray the penetration asphalt.
d. All instrument and equipment should be checked before 3 days of start working of
paving the test section which will eventually be part of the permanent work.

(ii) Mixing of bitumen mixed material


a. Every aggregate material should be stock piled and has to be mixed following
the appropriate mix design.
b. Heating of bitumen should be controlled to be within the specified range of
temperature from 150—1700C. Aggregate is from 160—1800C. Mixed material
should be from 140—1650C, if temperature is too high when come out from
plant, it should be discarded. Mixed material reached to site should not be lower
than 120—1500C. Above temperature should be considered according to actual
local condition.
c. Mixed material from plant should be uniform.

(iii) Transportation of mixed material


a. Arrange transportation trucks according to the production quantity.
b. Keep the Inside of the trucks clean and waterproof.
c. Mixed material inside the vehicle, if it is lower than regulated temperature or
watered by rain, should not be used.

(iv) Paving of Asphalt mix


a. The paving machine should be checked to ensure good quality surface finish.
Stopping the machine or change speed should be avoided during paving.
b. Check quality of mix during construction and take suitable adjustment. Check
thickness and altitude so as to tell machine operator.
c. Use manpower on places not reachable by machine.

(v) Rolling of mixed material


a. Make use of road roller, which weigh no less than 15 tons.
b. Initial rolling: Roll 1 or 2 times with roller machine, immediately following the
paving machine, the temperature should not be less than 110 0C. Secondary
rolling: 4—6 times, the temperature is controlled in 80—100 0C. Final rolling: 1—2
times, the temperature should not be lower than 80 0C. Make use of small rollers

9
Gottera site construction of main &pedestrian access road project
to compact I if the area is not accessible for big rollers.
c. Rolling should be done uniformly from lower side to higher side and conform to
the specification requirement.
d. The rollers should be equipped with water Sprinkler so as to avoid sticking of
asphalt on the roller surface.

(vi) Inspection and Testing


a. According to construction technical requirement, all kinds of tests have to be
carried out carefully.
b. Check pavement thickness, level, width and elevation during construction.
c. All tests results for materials should be reported to supervisor for approval.

The detail methodology and activity flow chart is as indicated hereunder

Construction Flow Charts for Major Activities

10
Gottera site construction of main &pedestrian access road project

CHART 1 Construction Sequences for sub grade construction

Re-establish control points

Setting -out

Detour road Detour road Clearing & grabbing


maintenance construction

Approval by Test for Fill Cut


the Engineer Borrowed
materials

Replaced by No
suitable Road bed Material Transport to
materials Treatment Treatment the waste

Yes Yes

Yes Rolling the fill Filling utilized


material layer by locally
layer

Sub-grade tests

Getting engineer’s
approval

CHART 2 Construction Sequences for Sub base construction

11
Gottera site construction of main &pedestrian access road project

Sub-grade approved by Engineer


Test Borrow
Material or crushed
stone sub base
material
Survey and layout

Approval by the
Engineer Dump and spread sub-base
material on sub-grade

Water to
Level to the grades and lines optimum
moisture
content

Compact to required density


Getting engineer’s
Approval

Chart3 Construction Sequences for Base course construction

Sub-base approved by Engineer


Crushed stone sub-base
material
12
Survey and layout
Getting engineer’s
Dump and spread base
Compact Approval
to required density
Material on sub-base
Gottera site construction of main &pedestrian access road project

Approval by
Engineer

Water to
Level to the grades and lines optimum
moisture
content

13
Gottera site construction of main &pedestrian access road project

Chart 4 Construction sequences of asphalt Pavement

Maintain and check


mixing plant Prepare base surface

Adjust design Survey and layout


formula

Prime Coat
Trail mixing

Prepare trial section


Maintain paver

Pave asphalt concrete material

Approval by Engineer
Compaction

Approval by Engineer
Design Binder &
wearing course
mixing formula
Curing

Open to Traffic

14
Gottera site construction of main &pedestrian access road project

Chart 5 Construction sequences of drainage Works

inspect existing drainage


Survey and layout

Remove inlet and outlet


structure Excavate the trench

Deepen and widen the trench Fill gravel Material Check


level and compact

Install pipe/ bar placing & Cast in precast yard


cast concrete

Inlet and outlet structure

Backfill and compact in layer

The quality for the concrete mixing shall be controlled by experienced technicians in accordance
with the Specification. The casting and vibrating of the concrete shall be in accordance with the
Specification.

15
Gottera site construction of main &pedestrian access road project

Chart 6 Concrete mixing

Washing the sand and aggregate

Cement Aggregate Sand

Balancing Balancing Balancing

Adding water Mixing Additive material

Transporting

Casting Taking samples

Curing

Dismantling the formwork Testing

5.0 Quality Control

16
Gottera site construction of main &pedestrian access road project
5.1 Strengthen Construction Management
a. The quality management group shall be led by project manager. It consists of the
survey crew, laboratory technicians, construction supervisors and they will jointly
be responsible to carry out internal supervision and quality assurance works.
b. Experienced and well versed Construction personnel shall be assigned.

5.2 Step of control


a. The project management group will always focus on keeping Quality of work as
their core value. All site Forman we will be instructed to carry out his task strictly
following the specification requirement, rules, and all quality control systems.
b. Construction must strictly conform to design plan, construction technical
specification.
c. Material sampling and testing shall be taken jointly with the Engineer.
d. Temporary bench marks shall be established at every 500m for controlling the
road construction.
e. Quality certificates shall be delivered from manufacturers for major materials like
bitumen and reinforcement steel in addition to routine tests to be carried out on
site.

6.0 Traffic Management & Safety measures


6.1 Team Set up
A full time traffic and safety Officer having a team on different sites will be assigned to
guarantee safety of workers and road users during construction.
6.2 Safety details
As the traffic safety works is not heavy except the contractor’s truck, The details steps
are as follow:
a. Build the capacity of the traffic safety team with all necessary resource like
movable signs, flags and etc….
b. Arrange periodic meetings with the safety officer and his team to discuss and
solve safety problems on site.
c. Construction vehicles must run in limited speed to avoid traffic accident.
d. The equipment and power line must be installed following the user manuals and
safe installation rules with appropriate earthling wire. Defective electrical
equipment must not be used without repair.

6.3 Work arrangement during night

The contractor will also arrange night works of some activities such as excavation to
waste, dumping of aggregates and other activities all as per the Engineer’s approval.
Adequate number of reflector signs will be provided on sections where construction is
going on.