TERP-01(NCB)
MS – 09 – WC
1 General
This work shall consist of furnishing materials, mixing at central mixing plant and spreading
Asphalt concrete wearing course on binder course pavement.
2 Reference
3 Resources
3.1 Material
TERP-01(NCB)
MS – 09 - WC
3.3 Manpower
4. Flow Chart
Step 1 – Setting out
Step 5 – Compaction
4of 7
TERP-01(NCB)
MS – 09 - WC
Step 5 Compaction
Immediately after the Mix has been spread as struck off, the surface shall be checked
and any irregularities are adjusted. Rolling shall commence as soon as the material
will support the roller with undue displacement or cracking. First in the break down
rolling stage, paved stretch including all joints and edges shall be compacted with 8
ton Steel wheeled tandem roller at a speed of 3 km/h, 2 no of passes. And then the
intermediate rolling shall be done by means of Pneumatic tired roller at a speed of 5
km/h, 12 no of passes. Breakdown and intermediate rolling shall be carried out at a
temperature not less than 135 0C and 115 0C respectively.
5of 7
TERP-01(NCB)
MS – 09 – WC
The final rolling shall be completed before the temperature of the mix falls below
900C. Finally the surface irregularities shall be checked using standard straight edge
Traffic shall not be allowed over newly laid surfaces at least for 12 hours after laying
or until the temperature of the newly laid surfacing has achieved the ambient
temperature.
The core samples shall be made as per couple for 500 m 2 for the density test of
compacted layer using core cutter before allowing to traffic and the holes shall be
filled with similar hot mix and compacted appropriately. The density of all samples
taken shall not be less than 98% of Marshall density at the point appropriate to the
locations.
6. Supervision
Position Responsibilities
Site Engineer Perform the Wearing course construction work on the
basis of method statement & specification.
Quality Control Currying out all kind of inspection in accordance with
Inspector (QCI) Quality Procedure and Method Statement
Technical Officer All setting out works in accordance with Method
Statement
Forman Assist to Site Engineer
7. Inspection
According to the attached Inspection and Test Plan “H” point, “W” point inspection
and tests shall be notified to QC Inspector. QC Inspector shall inspect site works as
schedule and report the Check List to Quality Assurance Engineer (QAE).
The Inspection and Test Plan for relevant working area shall be available on site for
the Resident Engineer to see. Upon completion of the Inspection and Test Plan, the
ITP shall be maintained at the MAGA- CDIG Project Office and submit to the RE
with the progress claim.
8. Traffic Control
Two flagmen shall be assigned with two walky-talky on either side of the working
area to facilitate the traffic in one way.
9. Safety Provision
Warning signs shall be displayed in advance as well as in working area. Working area
shall be barricaded with barricading tapes with painted barrels or by placing traffic
cones. Traffic warden jackets are to be provided to all flagmen. The safety
arrangements of the road are as shown in the attached drawing. When a road section is
closed at night, blinker lights shall be provided at both ends.