TERP-01(NCB)
MS – 09 – WC
1 General

This work shall consist of furnishing materials, mixing at central mixing plant and spreading
Asphalt concrete wearing course on binder course pavement.
2 Reference

Volume 4, Section VI Technical Specification, Part 1 Standard Specification, Chapter 500;


Sub Clause 502,506
Volume 6; Section IX: Contract Drawings
Construction Drawings

3 Resources

3.1 Material

No. Material Specification Remarks


Supplied from
1 Penetration Grade bitumen Clause 1702.1 Tech. Spec. approved
(60-70) supplier
Supplied from
2 Coarse aggregate Clause 1701.3 Tech. Spec. approved stock
pile
3 Fine aggregate Clause 1701.3 Tech. Spec. Supplied from
approved stock
pile

3.2 Equipments/ Machinery

No. Equipment/Machinery Q’ty Remarks


1 Asphalt plant (100Ton/Hour) 1 For producing Asphalt
concrete
2 3 Pin static Roller (8Ton) 1 Break down rolling
3 Crew cab 2 To transport labor crew.
4 Dump Truck (16 Ton)* 8 To Transport Asphalt concrete
5 Asphalt Paver (5.5m) 1 For laying Asphalt concrete
6 Hand Sprayer 1 For Applying the Tack coat
7 Water tanker 1 For fill the water to the rollers
8 Farm Tractor 1 For Transporting of the
compressor
9 Pneumatic Tired Roller(12 Ton) 2 Intermediate compaction
10 Air compressor 1 Cleaning of surface
11 Asphalt cutter 1 To cut the longitudinal and
transverse joints

* No of trucks can be varied


3of 7

TERP-01(NCB)
MS – 09 - WC
3.3 Manpower

No. Job Title Q’ty Remarks


1 Surveyor 1 For Setting out and leveling
2 Surveyor Helpers 5 To help Surveyor
3 Forman 1 Organizing And labor
controlling
4 Operators 6 Asphalt plant, 3 Pin static
roller, Asphalt paver, PTR , &
compressor, Asphalt cutter
5 Drivers 11 Dump trucks. crew cabs
&farm tractor
6 labor 8 Finishing works, Preparing
Edge and compaction, Joint
cutting, Asphalt finishing&
Unloading & Clearing
7 Flagmen 3 Traffic controlling

4. Flow Chart
Step 1 – Setting out

Step 2 – Surface Preparation

Step 3 – Tack coat

Step 4 – Laying Asphalt mixture

Step 5 – Compaction

4of 7
TERP-01(NCB)
MS – 09 - WC

5. Application of Wearing course.

Step 1 –Setting out


The setting out shall be done accordance with the specific requirements of the contact
and shall be set out with the lines and levels in according to the Construction
drawings and final design levels of the Wearing course.

Step 2–Surface Preparation


The selected section of one side of road shall be closed for traffic and diverted to the
other side. The two flagmen with two walky-talky shall be designated to either side to
control the traffic. The surface of the binder course which is going to apply wearing
course shall be washed thoroughly, swept to remove all dust and extraneous material.
The surface shall be dried using the air compressor before applying tack coat.
When the wearing course is completed one half of the road, the longitudinal joint
edge should be vertically cut to line carefully by using asphalt cutter, clean and apply
thin coat of tack coat on the surface before laying the next half.

Step 3 – Applying Tack coat


Tack coat shall be applied on binder course road prior to laying the Asphalt concrete
mixture to enhance the bond between the two layers. CRS 01 Shall be used for the
Tack coat and applied at a rate of 0.3 liter/m 2 by means of a Hand sprayer. Field tray
test shall be carried out to check the application rate of Tack coat as one test per day.
The tack coat shall be allowed to cure about 20 min before applying the Wearing
course.

Step 4 - Laying Asphalt mixture


The material shall be furnished to the Central Mixing plant, mixed and transported to
the site using dumped trucks. The Mix shall be delivered to the paver at the site a
minimum temperature of 135 0C. The Mix shall be laid immediately after
transporting, by means of approved mechanical pavers. A laboratory representative
shall be appointed at the site for monitor the mix temperature. Hot mix samples shall
be collected from the mixture before laying for the test of Wearing content, aggregate
grading and other properties of the mix as one sample per day or more as per
Engineer’s instruction.

Step 5 Compaction
Immediately after the Mix has been spread as struck off, the surface shall be checked
and any irregularities are adjusted. Rolling shall commence as soon as the material
will support the roller with undue displacement or cracking. First in the break down
rolling stage, paved stretch including all joints and edges shall be compacted with 8
ton Steel wheeled tandem roller at a speed of 3 km/h, 2 no of passes. And then the
intermediate rolling shall be done by means of Pneumatic tired roller at a speed of 5
km/h, 12 no of passes. Breakdown and intermediate rolling shall be carried out at a
temperature not less than 135 0C and 115 0C respectively.

5of 7
TERP-01(NCB)
MS – 09 – WC

The final rolling shall be completed before the temperature of the mix falls below
900C. Finally the surface irregularities shall be checked using standard straight edge
Traffic shall not be allowed over newly laid surfaces at least for 12 hours after laying
or until the temperature of the newly laid surfacing has achieved the ambient
temperature.
The core samples shall be made as per couple for 500 m 2 for the density test of
compacted layer using core cutter before allowing to traffic and the holes shall be
filled with similar hot mix and compacted appropriately. The density of all samples
taken shall not be less than 98% of Marshall density at the point appropriate to the
locations.

6. Supervision

Position Responsibilities
Site Engineer Perform the Wearing course construction work on the
basis of method statement & specification.
Quality Control Currying out all kind of inspection in accordance with
Inspector (QCI) Quality Procedure and Method Statement
Technical Officer All setting out works in accordance with Method
Statement
Forman Assist to Site Engineer

7. Inspection

According to the attached Inspection and Test Plan “H” point, “W” point inspection
and tests shall be notified to QC Inspector. QC Inspector shall inspect site works as
schedule and report the Check List to Quality Assurance Engineer (QAE).
The Inspection and Test Plan for relevant working area shall be available on site for
the Resident Engineer to see. Upon completion of the Inspection and Test Plan, the
ITP shall be maintained at the MAGA- CDIG Project Office and submit to the RE
with the progress claim.

8. Traffic Control

Two flagmen shall be assigned with two walky-talky on either side of the working
area to facilitate the traffic in one way.

9. Safety Provision

Warning signs shall be displayed in advance as well as in working area. Working area
shall be barricaded with barricading tapes with painted barrels or by placing traffic
cones. Traffic warden jackets are to be provided to all flagmen. The safety
arrangements of the road are as shown in the attached drawing. When a road section is
closed at night, blinker lights shall be provided at both ends.

10. Attached Forms


10.1 Inspection and Test Plan
10.2 Check List