Professional Documents
Culture Documents
MS-009
Rev.A
Ref.Letter No :
1 / 5
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
Contents
1. Introduction ................................................................................................................................................3
2. Responsibilities for activity Describe within this Method Statement ......................................3
3. Stability Analysis of Cut slope...............................................................................................................3
4. A Sample of Slope for Stability Analysis............................................................................................4
5. Conclusion ...................................................................................................................................................5
6. Annexure ......................................................................................................................................................5
2 / 5
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
1. Introduction
The nature of the excavation work being undertaken will affect the selection of an
excavation method and a safe system of work. Careful consideration would be given to
health and safety issues when planning the work where the excavation involves
anything other than shallow trenching and small quantities of material.
Ground collapse is one of the primary risks to be controlled in excavation work.
Ground collapse can occur quickly and without warning, giving a worker virtually no
time to escape, especially if the collapse is extensive.
Where a worker enters the canal and there is a risk of working, Control measures would
be implemented regardless of the depth of the canal.
When planning the work and selecting appropriate excavation methods and control
measures, it is important to consider: the type and strength of the material to be
excavated and the slope stability of cut slopes.
The ground conditions will have a significant impact on the selection of an excavation
method and the control measures implemented. Therefore, slope stability analysis need
to be done for the deep excavation segments.
Construction manager, section manager, section engineer and other relevant personnel
within whose scope of works shall be responsible for referred construction activities in
related to construction of deep excavation works. This work activity shall be carried out
according to the employer’s requirement and drawings, method stipulated in this
statement unless otherwise changed by the Engineer.
As per the design engineer’s advice (the meeting held on RE office on 2016/02/14) the
slope stability analyses would be carried out if the excavation depth exceed the 4m. If
we found any segment which need to be excavated more than 4m as per actual site
survey data, the slope stability analyses would be submitted separately in advance to
the engineer’s review.
3 / 5
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
Anyhow, the geological data are not available from Ch.13+490 to 22+300m, because
geological investigation has not been carried out for that area.
Geological investigation including 21 boreholes and laboratory test were carried out
for the canal trace at design stage from Ch.7+340 to Ch.13+490m. But, there is no
descriptions of geotechnical parameters in the Geological report. So, a comprehensive
study for constructions is necessary for the detailed slope stability analysis accordingly.
Anyhow, additional geological investigation would not be conducted unless otherwise
Engineer’s advice, because of no provision within project BOQ.
Therefore, typical geotechnical parameters are used for the predicted soil and rock
layers for slop stability analysis for a designed cut slope section.
Deepest cut section of the trace, Ch. 18+800m, is selected for slope stability analysis.
The cross section at the specific chainage is as below. (See Annexure 1 for further
details)
4 / 5
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
Cohesion: 25kPa
Phi’ :330
Cohesion: 45kPa
Phi’ :450
5. Conclusion
According to the Geoslope analysis the critical slip surface has a Factor of Safety
(FOS) of 1.715 which can be considered as safe.
6. Annexure
5 / 5
SLOPE/W Analysis
Report generated using GeoStudio 2012. Copyright © 1991-2015 GEO-SLOPE International Ltd.
File Information
File Version: 8.15
Revision Number: 12
Date: 3/19/2019
Time: 2:59:34 PM
Tool Version: 8.15.1.11236
Project Settings
Length(L) Units: Meters
Time(t) Units: Seconds
Force(F) Units: Kilo Newton
Pressure(p) Units: kPa
Strength Units: kPa
Unit Weight of Water: 9.807 kN/m³
View: 2D
Element Thickness: 1
Analysis Settings
SLOPE/W Analysis
Kind: SLOPE/W
Method: Spencer
Settings
PWP Conditions Source: Piezometric Line
Apply Phreatic Correction: No
Use Staged Rapid Drawdown: No
Slip Surface
Direction of movement: Left to Right
Use Passive Mode: No
Slip Surface Option: Grid and Radius
Critical slip surfaces saved: 1
Resisting Side Maximum Convex Angle: 1 °
Driving Side Maximum Convex Angle: 5 °
Optimize Critical Slip Surface Location: No
Tension Crack
Tension Crack Option: (none)
F of S Distribution
F of S Calculation Option: Constant
Advanced
Number of Slices: 30
F of S Tolerance: 0.001
Minimum Slip Surface Depth: 0.1 m
Search Method: Root Finder
Tolerable difference between starting and converged F of S: 3
Maximum iterations to calculate converged lambda: 20
Max Absolute Lambda: 2
Materials
Silty Sand (upper soil layer)
Model: Mohr-Coulomb
Unit Weight: 18 kN/m³
Cohesion': 25 kPa
Phi': 33 °
Phi-B: 0 °
Pore Water Pressure
Piezometric Line: 1
Piezometric Lines
Piezometric Line 1
Coordinates
X (m) Y (m)
Points
X (m) Y (m)
Regions
Material Points Area (m²)
Rubble Work - m²
CL
1 1
0.5 0.5
1.5193 1.5193
0.5 0.5
5 5
1 1
c b
a a
C A B
DATUM = 200m (masl)
201.512
DESIGN
LEVEL
0.00
DESIGN
OFFSET
215.690
EXISTING
LEVEL
0.00
EXISTING
OFFSET
NOTE
1. ALL DIMENSIONS ARE IN METERS. 2. THE DEFINITION OF a,b AND c SHALL BE AS FOLLOWS.
a = TOP LEVEL OF BOTTOM SLAB
b = TOP LEVEL OF RHS SLAB TOP
c = TOP LEVEL OF LHS SLAB TOP