You are on page 1of 6

Movable Scaffolding Systems

Michael Däbritz, Dipl. Ing. ewe, RöRo Traggerüstsysteme, Branch of ThyssenKrupp Bauservice GmbH, Zwenkau, Germany.
Contact: michael.daebritz@thyssenkrupp.com
DOI: 10.2749/101686611X13131377725442

Abstract where the final positioning for the next


casting step will be carried out after
Movable scaffolding systems (MSSs) were developed after the introduction of closing the formwork.
pre-stressing technology for concrete bridges to raise efficiency of bridge con-
struction using mechanization in some steps of the construction cycle. These
systems help to build multiple span in situ bridges with a variable degree of Range of Application
independence from the ground works regarding their dismantling and resetting MSSs rank among the heaviest bridge
in successive spans. construction techniques. This bridge
The working principle of this full-span construction method is based on the idea construction method can be applied
of moving formwork and its supporting structure from under the previously cast efficiently when the site faces topo-
bridge span to the next pier and aims at minimizing labour and lifting equipment graphic or man-made restraints or a
costs in all stages between casting one span and the following one. Whilst on one combination of different factors:
hand this raises safety on site, the more complex technology on the other hand
requires an experienced crew to handle the equipment. – Deep valleys, canyons
– Difficult access on the ground
MSSs can be applied for variable cross sections, bearing systems, curvature – Crossing waters
radii, span lengths and regardless of almost all topographic restraints imagin- – Inappropriate ground conditions
able. Individually shaped bridges can be fabricated. With MSSs, the construction – Within existing infrastructure
site is not stationary. Finalization works at the bridge, such as the installation of – More than eight spans
drainage, electrification and edge beams can be started even before the MSS – Variable curvature radius
completes the superstructure. – Preferably constant span length
The equipment requires a comparatively large quantity of material and time to – Variable cross-sectional height
be erected before it can start operating. Therefore with this construction method, – Longitudinal inclination up to 5%
economic advantage can mainly be gained with multiple span bridges. – Variable transversal inclination
– Span length 30 to 80 m without
As for every construction technology, contractors can achieve competitive cycle intermediate supports
times and lower costs on the construction by considering the technological – Low clearance over or under the
requirements of these systems regarding their supports and load conduction dur- bridge
ing the design phase of the piers and girders of the bridges. – Different bridge bearing systems
Keywords: movable scaffolding systems; span-by-span; bridge construction; con- Each of the above mentioned points
crete; bridge construction equipment. apply to majority of existing projects;
as always, there are exceptions for
Introduction: Description of Andernach, Germany), first in the any rule. Even if only one condition
Construction Method construction of viaducts, later also for is fulfilled, the use of MSS is already
building high-speed railway bridges justified.
Movable scaffolding systems (MSSs) (see Fig. 1).
are used for span-by-span construction Components and Kinematics
In the construction of multiple span
of cast in situ concrete bridges. The
bridges, MSSs show significant economic
bridge superstructure is fabricated on MSSs consist of five main compo-
advantages compared with stationary
a falsework construction that can be nents that should be chosen accord-
scaffolding systems. Once assembled,
moved in all three dimensions in order ing to the requirements resulting from
the MSSs can be shifted from one cast-
to achieve the best adaptation to geo- bridge design, regional characteristics
ing step to the next span by hydraulic
metric requirements and to minimize and economic considerations: form-
or mechanic means. Depending on the
lifting equipment for relocation works work (yellow), formwork supporting
support system of the applied MSS,
during the construction stage. structure (blue), main-girders (red),
ground works can be avoided or are
moving devices and supports (green)
The construction technology is being limited to relocation of pier supports.
(see Fig. 2).
used since 1959 (Kettiger Hangbrücke,
When MSSs are applied for pre-
In general, MSSs can be distinguished
stressed continuous beam bridges, typ-
from the position of the main-girders
ically one bridge span and a cantilever
Peer-reviewed by international ex- related to the superstructure:
perts and accepted for publication
will be produced. After pre-stressing,
by SEI Editorial Board the MSS will be lowered down, form- Underslung (see Fig. 2) and along-
work will be opened at a constructive side systems provide full clearance for
Paper received: March 07, 2011 joint, will be shifted transversally and material feeding from above. This is the
Paper accepted: July 27, 2011 be launched forward to the next span lightest and most common type of MSS.

Structural Engineering International 4/2011 Scientific Paper 413


ments of the concrete surface, cross
section, curvature radius, number of
applications and formwork supporting
system.
While steel formwork is used mostly
in applications with equal geometry,
wooden formwork gives more room
for adaptations to variations of above
mentioned requirements and to react
easily to “unforeseen” geometrical
imperfections, especially at connec-
tions to existing structures.
A good interaction between a form-
work and its supporting structure
helps in saving material for bracings
between beams, reduces weight and
improves stiffness of the construction.
The formwork is fixed on a formwork
supporting structure, which is a grid
of transversal beams that conducts
vertical loads to the main-girders
Fig. 1: Underslung movable scaffolding system with self-launching brackets on semi-inte- over a centering construction. These
gral railway bridge, Scherkondetalbrücke, Germany3 transversal beams have joints that
enable transversal movement of the
MSS when opened, in order to allow
passing of the pier when launching the
next span. The execution of the joints
influences the deformation of the MSS
in the casting stage and the cycle times
in the launching stage.
Pre-cambering and variations of trans-
versal inclination can be carried out
with spindles or hydraulic jacks under
the transversal beams or, at regular
span lengths with equal concrete loads
Fig. 2: MSS types: Underslung, alongside and overhead and constant inclination, either with
shimming plates or by adapting the
formwork construction.
With alongside systems, more vertical clean connection to the previous con-
clearance under the bridge can also be struction stage and efficient handling. Main-girders of the MSS are equipped
realized. On underslung systems, form- The choice of a suitable formwork with front and rear launching noses.
work construction can be adapted to system is mainly affected by require- The MSS is artificially elongated to
changes of cross-section or span length
of the bridge without interfering with
other MSS construction parts.
Overhead systems (see Fig. 3) need
the smallest space under the bridge
when the formwork is closed. Feed-
ing of materials (reinforcement, etc.)
cannot be executed with tower cranes
because the formwork supporting the
construction obstructs deliveries from
above. Housings can be installed with-
out much effort in cold regions, and
dismantling operations can be much
easier once a bridge is finished. These
heavy systems offer a comparably
larger area for wind forces, and their
centre of gravity and position of load
introduction points are on a higher
level than other systems2.
The formwork construction produces
a smooth concrete surface, and enables Fig. 3: Overhead system in Chasan, Korea (photocourtesy: J. Nitschke, NRS)

414 Scientific Paper Structural Engineering International 4/2011


over double the maximum span length
of the bridge in order to prevent it
from overturning in the launching
stage before reaching the next pier.
Launching noses are very light and not
intended to take any concrete loads.
There are two kinds of main-girders:
truss girders and box girders. Box gird-
ers offer more flexibility in positioning
the load introduction points and more
torsional rigidity; they are normally
heavier than truss girders and provide
a larger area for wind forces; with truss
girders, alongside systems can be real-
ized easily without cutting holes in any
walls. Load introduction points for
cantilever suspension, formwork sup-
porting structure and pier supports
should be located at the truss nodes.
Overhead systems mainly consist of
one or two main-girders, while under-
slung and alongside systems for single
box-girder bridges usually work with
two. Double-tee-beams are often fab-
ricated with three main-girders when
applying underslung or alongside
systems. Fig. 5: Alongside MSS on brackets; German railway project Saale-Elster-Talbrücke
Main-girders must be designed for two
primal load cases: casting and launch-
ing. Both load cases are totally differ- the next span, transversal movement vertical loads must be indicated to the
ent but have to be considered carefully. of the MSS will be there. Most of these pier designer. The supports normally
The launching stage often represents actions are taken over by the moving require holes in the slab to allow the
the decisive design case. To reduce the devices located between main-girders support legs to come out when disas-
weight of the main-girders, they can be and pier supports. sembling them, what must be studied
reinforced by means of pre-stressing due to the high concentration of rein-
(see Fig. 4). As the MSS faces various Vertical positioning is carried out with forcement. Both types of pier sup-
load and deformation scenarios dur- hydraulic jacks, and transversal move- ports for overhead systems can either
ing operation, the pre-stressing system ment through double-acting hydraulic be transported by an on-board crane
has to be constructed and adapted cylinders or electric engines. There are or relocated by independent lifting
sensitively. different types of launching devices. Self- devices.
locking systems are always preferred.
The operation of MSSs requires move- For underslung and alongside systems,
ments in all directions: The MSS must Overhead systems are supported there are mainly four types of pier sup-
be lowered down to strip the formwork on steel portals placed over the pier ports: pier towers, longitudinal beams
and the vertical position must be set head or on towers around the piers. in pier box-outs, grids suspended to the
up for the next casting step. To allow These supports require anchor bolts, pier table and pier brackets (see Fig. 5).
passing of the piers when launching whose position and horizontal and
Pier towers are a simple solution for
piers of small heights. Vertical loads
are introduced in the foundations, and
horizontal loads mainly close to the
top of the pier.
Longitudinal beams in pier box-outs
help in substituting towers at higher
piers. On top of the piers, hydraulic
jacks or transversal beams of the pier
support will be located. The box-out
causes weakening of the pier walls and
therefore installation of the longitudinal
beams should be carried out carefully.
With a grid being suspended to the top
of the pier, box-outs can be avoided.
Fig. 4: Main-girders reinforced with pre-stressing units at Rio Sousa Bridge, Portugal This type of construction requires
(photocourtesy: P. Pacheco, BERD) space between the superstructure and

Structural Engineering International 4/2011 Scientific Paper 415


top of the pier and a strong pier head. loads into piers and their foundations. Performance and Productivity
Dismantling operations are difficult Longitudinal loads due to launching
because the crane hook has to reach of an MSS vary between 3 and 10% Owing to the quantity and size of mate-
between the suspension beam and the because of different sliding or roller sys- rial being required for MSSs, logistics
superstructure. tems; additionally, longitudinal inclina- may sometimes be difficult and expen-
tions have to be considered. Especially, sive. Main-girders with dimensions of
Pier brackets (see Fig. 5) are commonly 4 × 2,5 × 21 m3 for large bridges that
the initial effort to start the movement
applied in higher piers. They introduce can only be transported as a unit are
has to be taken into account. This load
high transversal pressure forces in the available in the market. But smaller
will be introduced not only on the piers
pier walls. Vertical loads from the MSS systems are also available for smaller
which already bear the weight of the
can either be transferred to the pier spans or even modular systems. Many
superstructure but also on the next
with friction collars that avoid almost parts of MSSs, such as main-girders
span which is not yet completed. Strong
any holes in the pier walls and shear or brackets, are bulky or have a great
deformations in high and slim piers can
pins in pier box-outs or directly into the length. Among other points, this fact
cause damages during launching. This
foundations with additional supporting justifies the use of MSS technology
appearance can be reduced by cou-
legs under the brackets. only in long bridges with multiple
pling piers with tensile strands. Bridge
In general, three sets of pier supports supports should be relaxed from this applications or with long construction
should be provided. When two of them horizontal stress after launching. time or if there is no cheaper technol-
are in use, the third one will be disman- ogy available.
tled and relocated for the production Especially, MSSs with box girders and
overhead systems can introduce high Assembling and dismantling on site
of the next span. is the most time-consuming opera-
transversal loads into the piers as a
On-board brackets grant complete result of wind forces. tion with MSS. With a higher degree
independence from ground works for of pre-fabrication of delivered parts,
relocating pier supports. This com- Cantilever supports introduce high transport costs and handling costs
plex system works with only two sets vertical loads into bridge cantilevers. on site may increase but time can be
of brackets. But as it does not allow a Often holes are needed in the super- saved. If assembling procedures can
relocation of supports during the fab- structure to guide suspension bars be clarified with the bridge designer
rication of the superstructure, disman- from the supports. in advance, cost of temporary foun-
tling and resetting of the pier supports dations and lifting equipment can be
Pier towers stand on the pier foun-
must be carried out during the launch- reduced, i.e. when assembling can take
dations where they introduce high
ing operation. Some underslung MSSs place behind abutments and the MSS
vertical loads, which should be taken
perform the relocation of brackets can be launched through them.
into account in the dimensioning of
during the execution of the reinforce- reinforcement and measurement of If that is not possible, end spans can
ment. Additional suspension construc- foundations. either be produced with stationary
tions on the bridge are needed to keep shoring systems, or the MSS can be
the MSS in safe position while launch- The casting sequence of a span has a
installed completely in the second
ing brackets. great influence on the deformation of
span. End spans can also be fabricated
the MSS. On a MSS that is supported
Cantilever support constructions allow with shortened main-girders; launch-
on a front pier and a cantilever suspen-
a good connection between new con- ing noses can be installed subsequently
sion casting should be started at the
crete and the previously fabricated during the first launching operation.
front pier and continued forward and
span. On pre-stressed continuous backward simultaneously. At the end, The first launching also serves as a load
beam bridges, the tendon couplings the connection to the existing struc- test for the MSS. Loads and deforma-
are mostly located at the zero-point of ture should be completed. In this man- tions at fixed points, being given in
bending moments of the finished super- ner, proper loading and deformation handling instructions, are recorded,
structure. The location of the cantile- of MSS and bridge can be achieved. deviations are transferred to the MSS
ver support is shortly behind the joint. designer who immediately evaluates
In the casting stage, the rear end of the If concrete is poured at the cantile- consequences for further launching
MSS is suspended on that point while ver joint to the existing structure first steps. The MSS’s self-weight on the
the rear pier support is inactive. This and carried on forward, the MSS will pier supports’ hydraulic jacks is con-
suspension point requires additional become deformed once the concrete at sidered the base for all examinations.
pre-tensioning of the cantilever over the cantilever joint hardens, which can Simulation of the pouring stage with
the pier and is not always preferred lead to cracks. If the concrete is filled a load test of the MSS is possible but,
by the bridge designer. It reduces the after the mid-span, the middle section in most cases, not decisive: the initial
casting span for the MSS but increases of main-girders will bend down strongly, casting steps will often be fabricated
the design moment over the pier when and the front parts of main-girders will with an incomplete MSS; so it is not
the MSS is very heavy. Bridges can also bend upwards. The weight of concrete possible to simulate the development
be built without cantilever supports; at the front cantilever will not elimi- of inner friction due to hardening of
this has to be considered in the pre- nate the deformation in the mid-span concrete with water-bags and in many
stressing layout and while determining and the cantilever will be higher than cases, the pouring stage does not rep-
the length of the main-girders. expected. Apart from a bad shape of resent the determining design case for
the bridge, this incorrect pouring pro- the MSS.
Permanent Work Interfaces cedure can even lead to failure of the
MSS’s main-girders or support con- Relocating the pier supports will nor-
When using MSS, pier supports conduct structions, and the existing bridge can- mally be carried out during the pro-
not only vertical but also horizontal tilever will be temporarily overloaded. duction of the superstructure. Figure 6

416 Scientific Paper Structural Engineering International 4/2011


Any changes being made at the MSS
during one project, such as the instal-
lation of concrete spreaders, should be
transmitted to and approved by the
designer of the system.
MSS works are usually carried out
over the ground. Three main critical
phases can be identified in the use of
standard MSSs: works on incomplete
MSSs during assembling and disman-
tling, relocation works of pier supports
and the launching stage.
Two risk analyses should be provided:
one for the assembling and disman-
tling operations and one regarding the
Fig. 6: Overhead system in pouring and launching stage; scheme from Dae-Duck-Bridge use of MSSs.
in Korea
With the rising degree of pre-assem-
bling, the risk of accidents during
shows the two stages of an overhead Experienced operation crews help in assembling phases over the ground
MSS in cross-sectional view. Launching making cycle times, especially assem- will be reduced.
stages are critical stages for the sched- bling, dismantling and relocating The MSS should be kept clean; unfore-
ule. Whenever span length, cross- works, reliable and easy to schedule. seen loads due to mixing up the MSS
sectional shape of the superstructure With inexperienced crews, assembling in a storage yard can have fatal con-
or transversal inclination varies, needs more time and the initial cycles sequences. General issues such as
modifications have to be carried out. of fabrication must be acknowledged avoiding launching operations at night
Reinforcement installation has to only as training cycles. or provision of integrated working
wait until these works are finished. platform concepts (see Fig. 7) should
Additional features such as adaptable be considered. Interrupting launch-
cantilever suspensions and exchange-
Risks and Safety
ing operations, for example during a
able formwork constructions help in A remarkable advantage in terms of strong wind, must be avoided because
saving time during these critical phases. labour safety is the reduction of relo- MSSs will be separated as completely
At MSSs without intermediate sup- cation works compared with stationary independent parts for the launching
ports, fabricating span-by-span on shoring systems. which will reduce the stability of the
three sets of pier supports, launching In most cases, fabrication of MSS parts is whole system.
of the MSS requires about 10 to 15% taken over by the supplier who assures a Approval of the assembled MSS and
of the whole cycle time. complete and traceable quality control. approval before casting of each span
While 40 to 50 m single-cell box-
girder spans with ordinary pier sup-
ports can be produced in two casting
steps within 10 working days (one
shift, 10 working hours per day with
minimized staff), cycle times with on-
board brackets on the same bridge
may need 2 to 4 days longer because
relocating the pier supports cannot
be carried out independently from
the launching procedure (both exam-
ples from German railway bridge
construction).
The fastest way to cast box girders is
to cast them in one stage. It requires
sophisticated and expensive inner
formwork, similar to tunnel formwork.
Owing to higher bending moments
resulting from casting the full cross sec-
tion at once, the MSS construction will
be stronger and mostly heavier. With
that type of MSS, pre-fabrication of
reinforcement, higher manpower and
longer working times, cycle times can
be shortened to 1 week (as in Viaducto Fig. 7: Integrated platform concept at Füllbach-Talbrücke in Germany (photocourtesy: Mr.
de Rio Portos, Portugal). Bader, Strukturas)

Structural Engineering International 4/2011 Scientific Paper 417


should be a done as matter of course. down, the MSS’s deformation will relax, trough cannot be taken into account
Site-internal approvals for the founda- but in the launching stage deformations for static calculations, the whole mov-
tion levels and relocated pier supports, will again change. Proper communica- able scaffolding system must have
and checklists for launching stages tion between bridge designer and MSS stronger dimensions, which will lead to
help in eliminating mistakes during designer and feedback from the site higher loadings of the concrete struc-
routine operations. help in creating reliable forecasts for ture during the pouring and launching
the necessary pre-cambering and for stages.
Safe handling of the MSS depends
providing sufficient clearance between
on the operators as they are the most
formwork and superstructure when
important influence. Careful train-
launching.
Conclusion
ing and education are basic require-
ments in operators but cannot replace MSSs make the construction site linear MSSs are economically useful to cast
experience. and movable. Material supply can be long bridges in place and are suitable
optimized with access from the rear to build bridges in areas with hin-
abutment. When using underslung or dered access. Well designed MSSs and
Recommendations alongside systems, a crane-on-rails on good communication between bridge
or next to the bridge deck helps in designer and formwork supplier cre-
Bridge design offers a high potential to saving time and eases material supply. ate more flexibility in use than incre-
increase efficiency during operations If a tower crane cannot be installed, mental launching systems, especially
of the MSS. Equal bridge span lengths cycle times can be shortened with pre- in more complex bridges in countries
avoid adaptations of the MSS and save fabricated reinforcement baskets that with high labour costs. With the pos-
time. Communication between bridge can be transported to in place i.e. by sibility to create individual shapes of
and MSS designers in the early phases straddle carriers. In areas with dif- superstructures and lower costs for the
of a project optimizes assembling and ficult access, it may be useful to raise application of the bridges with medium
dismantling procedures and eases the degree of mechanization, that is, length and in urban areas, this con-
operations with simple measures such by using MSSs that can unload trucks, struction method also has advantages
as repositioning the cantilever sus- feed themselves of materials and rein- in comparison to pre-cast technology.
pensions in order to have equal span stall their own supports.
lengths.
Bridge completion works for drainage, References
A good coordination between form- edge beams and lighting can start even
work and its support construction before the MSS has reached the final [1] Marx S, Krontal L, Bätz S, Vehlow A. Die
on the MSS help in saving material span, thereby production time for the Scherkondetalbrücke, die erste semi-integrale
and weight, i.e. regarding distances whole bridge can be optimized. Talbrücke der DB AG auf der Neubaustrecke
between the grid of transversal beams Erfurt—Leipzig/Halle VDE 8.2. Beton
and exchangeability of formwork Tower cranes that follow underslung Stahlbetonbau 2010; 105 (Heft 3); S134–S141.
elements. or alongside systems on the bridge DOI: 10.1002/best.201090021.
help in saving time and money spent [2] Mertinaschk A. Köröshegy Viadukt—
When the MSSs is lowered down, the on lifting equipment. Vorschubgerüsttechnik mit vielfältigen
superstructure experiences different Möglichkeiten, VDI Jahrbuch 2009. Bautechnik,
kinds of deformation: bending of the Remarkably high savings in the time VDI Verlag GmbH Düsseldorf: Germany, 2008.
MSS during the casting stages, deforma- can be achieved by casting box gird-
[3] Marx S, Schlaich J. Fresh wind for German rail-
tion of the previously fabricated cantile- ers not in two steps but in one. In such way bridges. In: The 11th Annual International fib
ver, creeping and shrinking of concrete, cases it must be considered that the Symposium, Concrete: 21st Century Superhero?
pre-stressing and settlements of foun- MSS faces a much higher bending load. Building a Sustainable Future, London, June
dations and supports. When lowering As the partial bearing capacity of the 22–24, 2009, Book of Abstracts and CD-Rom.

418 Scientific Paper Structural Engineering International 4/2011

You might also like