You are on page 1of 10

Computers and Structures 84 (2006) 2141–2150

www.elsevier.com/locate/compstruc

Determination of design moments in bridges constructed with


a movable scaffolding system (MSS)
Hyo-Gyoung Kwak *, Je-Kuk Son
Department of Civil and Environmental Engineering, Korea Advanced Institute of Science and Technology,
373-1 Guseong-dong, Yuseong-gu, Daejon 305-701, Republic of Korea

Received 27 July 2005; accepted 8 August 2006


Available online 7 November 2006

Abstract

This paper introduces simple but effective equations to calculate the dead load and tendon moments in concrete box-girder bridges
constructed with a movable scaffolding system (MSS). Through time-dependent analyses of concrete box-girder bridges considering the
construction sequence and creep deformation of concrete, structural responses related to the member forces are reviewed. On the basis of
the compatibility condition and equilibrium equation at every construction stage, basic equations that can describe the moment variation
with time in movable scaffolding construction are derived. These equations are then extended to take into account the moment variation
according to changes in the construction steps. By using the introduced relations, the design moment and its variation over time can
easily be obtained with only the elastic analysis results and without additional time-dependent analyses considering the construction
sequences. In addition, the design moments determined by the introduced equations are compared with the results from a rigorous
numerical analysis with the objective of establishing the relative efficiencies of the introduced equations.
 2006 Elsevier Ltd. All rights reserved.

Keywords: Movable scaffolding system; Concrete box-girder bridges; Construction sequence; Creep; Dead load moment; Tendon moment

1. Introduction of the internal moment redistribution that takes place over


the service life of a structure, on account of the time-depen-
In accordance with the increased demand for the con- dent deformations of concrete, stress relaxation of tendons
struction of bridges, numerous bridges with exceptional and changes in the structural system repeated during
aesthetics and style have been constructed. At the same construction. Hence, in order to preserve the safety and
time, the construction methods have also undergone refine- serviceability of the bridge, an analysis that considers the
ment. In particular, among these construction methods, the construction sequence must be performed. All of the
movable scaffolding system has recently been recognized as related bridge design codes [1,5] have also noted the need
one of the most efficient methods in constructing multi- to consider the internal moment redistribution due to the
span continuous bridges with an identical span length. This time-dependent deformations of materials when the struc-
method has great advantages over other types of construc- tural system is changed during construction.
tion, particularly in urban areas where temporary shoring Several studies have dealt with the general topics of
would disrupt traffic and services below [19]. However, design and analysis of bridges, while a few studies have
the design and analysis of bridges constructed with the been directed toward the analysis of the deflection and
movable scaffolding system (MSS) require a consideration internal moment redistribution in bridges constructed by
a movable scaffolding system [17,18]. Furthermore, devel-
opment of sophisticated computer programs for the analy-
*
Corresponding author. Tel.: +82 42 869 3621; fax: +82 42 869 3610. sis of bridges considering the time-dependent deformations
E-mail address: khg@kaist.ac.kr (H.-G. Kwak). in addition to the construction sequence has followed, and

0045-7949/$ - see front matter  2006 Elsevier Ltd. All rights reserved.
doi:10.1016/j.compstruc.2006.08.044
2142 H.-G. Kwak, J.-K. Son / Computers and Structures 84 (2006) 2141–2150

a number of these programs are popularly used in the system, wherein each span of the superstructure is tied to
design practice [7–10]. a previous span by a sequential post-tensioning of tendons.
Most analysis programs, however, have some limita- The same erection process is repeated until the structure is
tions in term of a wider use stemming from complexities completed; consequently, the internal moment is continu-
in practical applications, such as the preparation for a great ously changed according to the construction sequence
amount of input data, no standard for the I/O formats, and and the changing structural system during construction.
a misunderstanding of output results. Consequently, a sim- This signifies that the tendon force and the dead load dom-
ple formula for estimating the internal moment redistribu- inantly affect the internal moment variation, as these two
tion due to the time-dependent deformations of concrete force components accompany the secondary moments
and the stress relaxation of the appropriate tendon used caused by concrete creep deformation as the structural sys-
by the design engineer during the primary design of bridges tem changes. With consideration of the aforementioned
is needed. Trost and Wolff [18] introduced a simple formula factors, a five-span continuous bridge, shown in Fig. 1,
that can simulate the internal moment redistribution with a was selected as an example structure in order to review
superposition of the elastic moments occurring at each con- structural responses due to changes in the construction
struction step. A similar approach has been presented by sequences. This bridge has a total length of 150 m with
the prestressed concrete institute (PCI) and the post-ten- equal span lengths of 30 m, maintaining a prismatic box-
sioning institute (PTI) on the basis of the force equilibrium girder section along the span length. The assumed material
and the rotation compatibility at the connecting point [3]; and section properties are taken from an actual bridge;
however, these formulas do not adequately address the these are summarized in Table 1, and the tendon properties
changing structural system due to several adopted simplify- are presented in Table 2. The creep deformation of con-
ing assumptions. crete is considered on the basis of the ACI model with an
In this paper, simple but effective formulas that can cal- ultimate creep coefficient of /1 cr ¼ 2:35 [2].
culate the internal moment redistribution in concrete As shown in Fig. 1, the time interval between each con-
bridges after completion of construction by MSS are intro- struction step is assumed to be approximately 10 days.
duced. With previously developed computer programs [11– When a scaffold moves to the next span, the concentrated
15], many parametric studies for bridges erected by a load Pg caused by the self-weight of the scaffold acts at
movable scaffolding system are conducted, and correlation the end of the previous span (see Fig. 1(c), (e), (g) and
studies between the obtained numerical results and those (i)). In advance, an additional concentrated load Pc by the
by the introduced formulas are included to verify the appli- concrete pouring of the following span also acts at the same
cability of the introduced formulas. Finally, a reasonable point. These repeated applications of concentrated loads, as
guideline to determine the internal design moments, which shown in Fig. 1, continue until the end of the construction.
are essential in selecting a proper initial section, is If the self-weights of the scaffold and superstructure are
proposed. assumed to be wg = 13.7 ton/m and wD = 26.65 ton/m,
respectively, the concentrated loads of Pg and Pc can then
2. Construction sequence analysis be determined by the following equation derived on the
basis of the moment equilibrium to the pier in Fig. 2, where
2.1. Construction sequences the lengths of L = 30 m, l0 = 2.5 m, l1 = 27 m, l2 = 3 m,
l3 = 27.5 m, and l4 = 6 m are assumed in this paper by refer-
Every nonlinear analysis algorithm consists of four basic ring to an actual bridge project. The two concentrated loads
steps: a formulation of the current stiffness matrix, a solu- of Pg = 179.4 ton and Pc = 348.9 ton are finally calculated
tion of the equilibrium equations for the displacement in this example structure
increments, stress determination of all elements in the
P g ¼ wg ðl23  l24 Þ=ð2l3 Þ; P c ¼ wD ðl23  l24 Þ=ð2l3 Þ ð1Þ
model, and a convergence check. Several papers [11–15]
have presented an analytical model that predicts the time-
dependent behavior of bridge structures. Experimental ver- 2.2. Dead load moment variation
ification and correlation studies between analytical and
field testing results were conducted to verify the efficiency The dead load moments corresponding to each con-
of the proposed numerical model. The rigorous time depen- struction sequence at typical construction steps are shown
dent analyses in this paper are performed with the intro- in Fig. 3, where TS (total structure) in Fig. 3(c) indicates
duced analytical model. Details of the analytical model that all of the spans are constructed simultaneously at
can be found in the aforementioned papers [11–15]. In the reference time t = 0 day. As shown in Fig. 3(a), the
advance, all the material properties related to a tendon, dead load at the first span with a concentrated load Pg
from the definition of the stress–strain relation to the for- by the formwork for concreting of the second span (see
mulation of relaxation, can also be found elsewhere [11,12]. Fig. 1(c)) produces a constant moment distribution without
Movable scaffolding construction refers to a step-by- any change until the additional concentrated load Pc is
step construction of a bridge superstructure sequentially applied at t = 21 days (see Fig. 1(d)). No internal moment
from the first to the end span using a movable scaffolding redistribution by creep deformation of concrete in a span
H.-G. Kwak, J.-K. Son / Computers and Structures 84 (2006) 2141–2150 2143

(a) Scaffolding at the first span (t = 1day)

(b) Concrete pouring of the first span (t = 10days)

wD Pg

(c) Post-tensioning the tendon (t=20days) & Moving the scaffold to the second span (t=21days)

wD Pg + Pc

(d) Concrete pouring of the second span (t = 30days)

wD Pg

(e) Post-tensioning the tendon (t=40days) & Moving the scaffold to the third span (t = 41days)

wD Pg + Pc

(f) Concrete pouring of the third span (t = 50days)


wD Pg

(g) Post-tensioning the tendon (t=60days) & Moving the scaffold to the fourth span (t = 61days)

wD Pg + Pc

(h) Concrete pouring of the fourth span (t = 70days)


wD Pg

(i) Post-tensioning the tendon (t=80days) & Moving the scaffold to the fifth span (t = 81days)
w Pg + Pc
D

(j) Concrete pouring of the fifth span (t = 90days)


wD

(k) Post-tensioning the tendon (t=100days) & Completion of the superstructure (t = 101days)

Fig. 1. Construction Sequences in a Bridge Constructed by MSS.


2144 H.-G. Kwak, J.-K. Son / Computers and Structures 84 (2006) 2141–2150

Table 1 SPAN
Material and sectional properties used in application 1st 2nd 3rd 4th 5th
4000
Representative section properties Material properties 2680 21 DAYS
3000 2210 30 DAYS
45cm WD 26.65 ton/m
fc0 400 kg/cm2 2000

MOMENT (ton-m)
120.4cm
fsy 4000 kg/cm2
1000
ES 2.1 · 106 kg/cm2
35cm 229.6cm
62.5cm 0

420cm 560cm 420cm -1000

-2000 -658
Ac = 116350cm 2
-3000 -1710

-4000
0 30 60 90 120 150
Table 2 LENGTH (m)
Tendon properties used in application
Pi AP fpy SPAN
2 2
1st 2nd 3rd 4th 5th
1480 ton 106.4 cm 14765 kg/cm 4000
61 DAYS
2080 70 DAYS
3000
1540

MOMENT (ton-m)
2000 900 1100
P=Pg+Pc
1000
l2 l1 l2
0

-1000

-2000 -658
l0 l3 l4
-3000 -2100
-1710
L -2390
-4000
0 30 60 90 120 150
LENGTH (m)

SPAN
1st 2nd 3rd 4th 5th
Fig. 2. Determination of concentrated loads, Pg and Pc. 4000
101 DAYS
100 YEARS
3000 2010 TS

occurs from t = 21 days to t = 30 days, as the structural 2000 1110 1840


MOMENT (ton-m)

896
779
system maintains the statically determinate structure. 1000
The sequential applications of the dead load by the self-
0
weight of the following span with the concentrated loads of
Pg and Pc introduce repeated increases and decreases of the -1000
moment distribution along the span. A time dependent -2000
moment redistribution is also expected as the structural sys-
-3000 -2040 -1910
tem changes in the statically indeterminate structure. How- -2520 -2660
ever, the relatively short duration of 11 days and the -4000
0 30 60 90 120 150
subsequent application of a concentrated load Pc do not LENGTH (m)
allow the time-dependent moment redistribution to be sus-
Fig. 3. Dead load moment distributions: (a) after construction of the first
tained. From Fig. 3(c), representing the final moment distri- span, (b) after construction of the third span and (c) after completion of
butions after the completion of construction, it can be the bridge.
inferred that the dead load moment distribution is not
greatly affected by the time-dependent deformations of con- maximum moments experienced during construction at
crete but is instead influenced by the concentrated load Pg each point are presented in Fig. 4. These obtained results
and Pc. That is, the dead load design moment in a bridge clearly demonstrate that the dead load design moment
constructed by MSS can be determined on the basis of an can be determined by an elastic analysis if only the con-
elastic analysis considering only the construction sequence. struction sequence is taken into account.
Numerous parametric studies have been conducted with
changes in design parameters such as the construction time 2.3. Tendon moment variation
interval and the ultimate creep coefficient Cu, which affect
the time-dependent behavior of a structure, and a few typ- The same example structure is also reanalyzed with
ical moment envelope curves obtained by connecting the respect to the longitudinal tendons. Referring to drawings
H.-G. Kwak, J.-K. Son / Computers and Structures 84 (2006) 2141–2150 2145

SPAN the tendons for the first span at t = 21 days when the first
1st 2nd 3rd 4th 5th span works as an elastic body. As no additional post-ten-
4000
2680 Construction Interval t=20 days
Construction Interval t=50 days sioning is conducted at the second span up to t = 40 days,
3000 TS
1540
the moment variation from t = 21 days to t = 40 days, as
1870
MOMENT (ton-m)

2000 shown in Fig. 6(a), is caused by the stress relaxation of


1000 the tendons post-tensioned at the first span.
As shown in Fig. 6, the moment distribution at time t
0
represents a difference from that of the total structure
-1000 (TS in Fig. 6) due to the changes in the structural system
-2000 and the accompanying time-dependent effects of the con-
-3000
crete and the tendons at each construction step. In
-2520 -2520
-2660 advance, the positive moments at the interior supports do
-4000
0 30 60 90 120 150 not display a large variation while the negative moments
LENGTH (m) at the mid-spans show definite decreases with time. This
variation can be explained by the following: (1) The creep
SPAN
1st 2nd 3rd 4th 5th
moment distributions in Fig. 7(a) shows that the creep
4000
Cu=2.35
moments represent the positive moment distributions along
2680
3000
Cu=1.5
TS
the entire spans and change with time even after comple-
1540 1870 tion of the bridge. The creep moment has a maximum value
MOMENT (ton-m)

2000
at the first interior support, whose value converges to
1000 513t  m at the end of the time-dependent behavior; (2)
0 the tendon moments as shown in Fig. 6 displays positive
-1000
values at the interior supports and negative values at the
mid-spans due to the primary tendon profile shown in
-2000
Fig. 5. As the stress relaxation represents the reduction of
-3000
-2520 -2660 -2520
the tendon forces with time, the moment values resulting
-4000 from the stress relaxation have opposite signs to those
0 30 60 90 120 150
noted above, which signifies that the moment reduction
LENGTH (m)
occurs along the entire span. Fig. 7(b) shows the moment
SPAN reductions of the example structure according to the relax-
1st 2nd 3rd 4th 5th ation; (3) finally, the superposition of both moment com-
4000
2680 Rigorous Analysis ponents in Fig. 7(a) and (b) gives an increase of positive
Elastic Analysis
3000 TS moments at the mid-spans and an immaterial variation of
1610
2000
1870 negative moments at the interior supports, which results
MOMENT (ton-m)

in decreases of the tendon moments at the mid-spans.


1000
From the obtained results, it can be concluded that, unlike
0 the case of the dead load moment variation, the time-
-1000 dependent deformations of concrete and tendons as well
-2000
as the construction sequence must also be considered in
order to determine the tendon moment variation with time.
-3000
-2660 -2520
-2820
-4000 3. Determination of tendon moments
0 30 60 90 120 150
LENGTH (m)
3.1. A proposed relation for tendon moment
Fig. 4. Dead load moment envelopes for the example structure: (a)
moment envelopes according to the construction time intervals, (b)
moment envelopes according to the ultimate creep coefficients and (c) Construction of a multi-span continuous bridge com-
moment envelopes according to the analysis methods. mences at one end and proceeds continuously to the other
end. Therefore, changes in the structural system are
for a high-speed railway bridge project in Korea, the ten- repeated whenever a newly constructed span is tied to a
don profile shown in Fig. 5 is determined, and the stress preceding span. In advance, the sequential installation of
relaxation in a tendon with time is taken into consideration the longitudinal tendons following the construction of each
on the basis of an equation proposed by Magura et al. [16]. span cause the moment variations in the preceding spans,
As post-tensioning of the tendons must follow the con- as shown in Fig. 6. To precisely calculate the final time-
struction sequences described in Fig. 1, the time interval dependent moments in a bridge constructed by a MSS
for the continuity of tendons placed at each span is auto- (movable scaffolding system), Trost and Wolff [18]
matically determined. The example structure in Fig. 1 rep- proposed a relation
P on the basis of the combination of elas-
resents a time interval of t = 20 days after post-tensioning tic moments M S;i occurring after scaffolding at each
2146 H.-G. Kwak, J.-K. Son / Computers and Structures 84 (2006) 2141–2150

SPAN
1st 2nd 3rd
120.4

Y-axis (cm)
35.4 1st span 35.4 2nd span
-3.6 construction
construction
0

l =33m l =30m
-159.6 -159.6
-229.6
0 15 30 45 60 75
Length (m)

Fig. 5. Tendon profile of the example structure.

SPAN
1st 2nd 3rd 4th 5th
4000 SPAN
21 DAYS 1st 2nd 3rd 4th 5th
3000 40 DAYS 2000
1 YEAR
10 YEARS
MOMENT (ton-m)

2000 1500 100 YEARS


523
1000 513

MOMENT (ton-m)
1000 341 366
260
0 500

-1000 -52
0

-2000 -500

-3000 -1000
-2190
-2360
-4000 -1500
0 30 60 90 120 150
LENGTH (m) -2000
0 30 60 90 120 150
LENGTH (m)
SPAN
1st 2nd 3rd 4th 5th
4000 SPAN
61 DAYS 1st 2nd 3rd 4th 5th
3000 2000 1950
80 DAYS 2000
TS 1 YEAR
1620
1370 10 YEARS
MOMENT (ton-m)

2000 1500 100 YEARS


523
1000
MOMENT (ton-m)

1000 396 315


234
189
0 500

-1000 -52
0

-2000 -907 -500


-1200 -175 -156 -149
-1680 -322 -316
-1740 -1000 -380
-3000 -1830

-4000 -1500
0 30 60 90 120 150
LENGTH (m) -2000
0 30 60 90 120 150
LENGTH (m)
SPAN
1st 2nd 3rd 4th 5th Fig. 7. Time-dependent moment variation: (a) creep moment distribution
4000 101 DAYS
and (b) moment losses by relaxation.
1 YEAR
3000 2080 100 YEARS
1650
1470 TS
1390 1700
construction step (see Fig. 8), and the moment obtained by
MOMENT (ton-m)

2000

1000 assuming that the entire structure is constructed at the


same point in time (ME; corresponding to TS in Fig. 6)
0
X  X  /
t
-1000 MT ¼ M S;i þ M E  M S;i ð2Þ
-851
1 þ q/t
-2000 -964 -1270
-1330 -1180 -1270
-1650 -1820 where /t and q represent the creep factor and correspond-
-3000
ing relaxation factor, respectively.
-4000
0 30 60 90 120 150 This relation has been broadly used in practice owing to
LENGTH (m) its simplicity. It is particularly efficient for bridges con-
Fig. 6. Tendon moment distribution: (a) after construction of the first structed by ILM (Incremental Launching Method) or
span, (b) after construction of the third span and (c) after completion of MSS (Movable Scaffolding System), i.e., in span-by-span
the bridge. constructed bridges. Nevertheless, there are still limitations
H.-G. Kwak, J.-K. Son / Computers and Structures 84 (2006) 2141–2150 2147

3 tion of time (see Fig. 9(a)), the bending moment at the inte-
Construction 2
stages 1
rior support can be determined from the compatibility
condition for the rotation with time at point A in
Fig. 9(a). As the well-known derivation procedure can be
found elsewhere [6,17], more details are not given in this
paper; the moment variation at the interior support can
M S,1
be predicted by
/ðt; t0 Þ  /ðt1 ; t0 Þ
M A ðtÞ ¼ M A ð0Þ  ð3Þ
1 þ v/ðt; t1 Þ
M S,2
where MA(0) is the moment developed in the elastic
structure, indicating that all of the spans are constructed
simultaneously at the reference time t = 0 day; / is the
M S,3
creep factor; and v is the aging coefficient. In particu-
lar, this equation indicates that the moment MA(t), in-
duced as a consequence of creep, is proportional to the
ME moment MA(0) which would develop in an elastic
structure.
Given that the time-dependent behavior of a two-span
MT
continuous beam effectively describes the internal moment
M S, i variation in bridges constructed by a movable scaffolding
system, with the basic form of Eq. (2) suggested by Trost
Fig. 8. Combination of MS,i.
and Wolff [18] considering the construction sequence while
calculating the internal moments at an arbitrary time t, the
following relation is introduced in this paper:
related to direct applications of Eq. (2) to determine the X  X 
tendon moments, as this equation cannot take into account MT ¼ M S;i  RðtÞ þ M E  M S;i  RðtÞ  f ð/t Þ ð4Þ
the time-dependent moment redistributions according to
the construction sequence and the stress relaxation of where f(/t) = (/(t, t0)  /(t1, t0))/(1 + v/(t, t1)), and R(t) is
tendons. the stress relaxation in the tendon and can be determined
To solve this problem and to accurately simulate the by R(t) = fs/fsi = 1  log t/10 Æ (fsi/fy  0.55) introduced by
time-dependent tendon moment variation, an improved Magura et al. [16], where fsi/fy P 0.55; fs is the stress at
moment relation is proposed in this paper on the basis of time t, fsi is the initial stress immediately after stressing,
the relaxation phenomenon and construction simulation fy is the 0.1% offset yield stress, and t is the time in hours
for MSS. If two simple beams of equal age and of equal after stressing. In the case of low-relaxation tendons, a
span L, carrying a uniformly distributed load w, as time value of 45 is used instead of 10 in the denominator of
t = t0 day are connected at time t = t1 day and they behave the equation R(t). v is the concrete aging coefficient which
as a continuous beam of two spans in the subsequent dura- accounts for the effect of aging on the ultimate value of

A
L L

M A (0) : Moment in the Elastic Structure


M A (t) : Moment at time t
: Moment before Continuity

L L

Fig. 9. Moment variation according to the continuity: (a) continuity of two simple beams and (b) moment distribution with time.
2148 H.-G. Kwak, J.-K. Son / Computers and Structures 84 (2006) 2141–2150

creep for stress increments or decrements occurring gradu- SPAN


ally after the application of the original load. It was found 1st 2nd 3rd 4th 5th
4000
in previous studies [4,6] that an average value of v = 0.82 Rigorous Analysis
Trost & Wolff
3000 2000
can be used for most practical problems where the creep 1590 1480
(Eq.(4))

coefficient lies between 1.5 and 3.0. An approximate value 2000

MOMENT (ton-m)
of v = 0.82 is adopted in this paper. In advance, the addi- 1000
tional short-term loss caused by friction between the ten-
0
don and the duct during jacking can also be considered
by determining the initial prestressing force according to -1000

an equation adopted in the ACI code [2]; its contribution


P -2000 -1040 -1150
-1480 -1250
will be implemented while calculating ME and M S;i in -3000 -1710
Eq. (4).
-4000
Comparing this equation (Eq. (4)) with Eq. (2), the fol- 0 30 60 90 120 150
lowing differences can be found: (1) since the tendons LENGTH (m)
accompany the moment decrease due to the stress relaxa-
SPAN
tion, even in a structure without any change in the struc- 1st 2nd 3rd 4th 5th
tural system, as well as the moment variation according 4000
Rigorous Analysis
to changes in the structural system, all of the moment com- 3000 2020 Trost & Wolff
1760 (Eq.(4))
ponents described in Eq. (4) must include the stress relaxa- 1550
1410

MOMENT (ton-m)
2000
tion of the tendon. Based on this aspect, the combination P
of elastic moments by the longitudinal tendons ð M S;i Þ 1000
as well as the moment difference P caused by the changes in 0
the Pstructural system ðM E  PM S;i Þ need to be revised -1000
by M S;i  RðtÞ and ðM E  M S;i Þ  RðtÞ, respectively;
-2000 -960
and (2) the term /t/(1 + q/t) in Eq. (2) also needs to be -1080
-1410 -1380
-1700
revised by f(/t) = (/(t, t0)  /(t1, t0))/(1 + v/(t, t1)) to effec- -3000
tively simulate the moment variation in a bridge con- -4000
0 30 60 90 120 150
structed by MSS (see Eq. (3)).
LENGTH (m)

3.2. Application of the proposal relation SPAN


1st 2nd 3rd 4th 5th
4000
To verify the effectiveness of the introduced relation, the Rigorous Analysis
2020 Trost & Wolff
internal tendon moment variations in the example structure 3000 1760 (Eq.(4))
1480
after construction, which were obtained through rigorous 1340
MOMENT (ton-m)

2000
time-dependent analyses, are compared with those by the
1000
introduced relation. The effect of creep in the rigorous
0
numerical model was studied in accordance with the first-
order algorithm based on the expansion of a degenerate -1000
kernel of the compliance function [11–15], and the stress -2000 -906
-1030
-1340
relaxation was taken into account with the equation intro- -1700
-1370
-3000
duced by Magura et al. [16]. Fig. 10 representing the
obtained results at t = 1 year, t = 10 years, and t = 100 -4000
0 30 60 90 120 150
years after the completion of construction, shows that the LENGTH (m)
relation of Eq. (2) proposed by Trost and Wolff gives
Fig. 10. Tendon moment variations after construction (a) t = 1 year, (b)
slightly conservative positive and negative moments, t = 10 years and (c) t = 100 years.
although they are still acceptable in the preliminary design
stage. These differences appear to be caused by insufficient
consideration of the moment redistribution according to of the tendon. Conversely, the relation introduced in Eq.
the changes in the construction sequence of the MSS (4) very effectively simulates the internal moment variation
(movable scaffolding system) as well as by a rough imple- over time, regardless of the construction sequence, and
mentation of the stress relaxation of the tendons. In partic- gives slightly larger positive and negative moments than
ular, the relation proposed by Trost and Wolff (Eq. (2)) those obtained by the rigorous analysis along the spans.
shows an increase of the tendon moment from 2000 ton- Hence, the use of Eq. (4) in determining the internal tendon
m at 1 year to 2020 ton-m at 10 years at the first interior moments will lead to more reasonable preliminary designs
support. This result appears to have been caused by the of bridges constructed by a movable scaffolding system.
considering the creep deformation of the structure only Fig. 11 shows two tendon moment envelope curves
without an additional implementation for the relaxation obtained by a rigorous analysis considering the time-
H.-G. Kwak, J.-K. Son / Computers and Structures 84 (2006) 2141–2150 2149

SPAN Fig. 1 is taken as the example structure. All of the material


1st 2nd 3rd 4th 5th properties used in the numerical analyses are identical to
5000
Elastic Analysis
Rigorous Analysis
those given in Tables 1 and 2 in this paper. Fig. 12 repre-
4000
2360
1950 1880
(Eq.(4)) at 101days
senting the obtained results at t = 1 year, t = 10 years,
3000 1620
1700 and t = 100 years after the completion of construction,
MOMENT (ton-m)

2000
shows that the superposition of two moments effectively
1000
simulates the internal moment variation with time.
0
The moment envelope curve in Fig. 13, determined from
-1000
a rigorous analysis considering the construction sequence
-2000
-1500 -1770 and the time-dependent behaviors of materials, shows that
-3000 -1820
-2350
-1860 the proposed method, suggesting the determination of
-4000
-5000
0 30 60 90 120 150
SPAN
LENGTH (m) 1st 2nd 3rd 4th 5th
4000
TD Analysis
Fig. 11. Tendon moment envelope curves. Trost & Wolff
3000 Proposed Method

MOMENT (ton-m)
2000
529
dependent deformations of concrete in addition to the stress 1000
404

relaxation of tendons as well as the construction sequence


0
given in Fig. 1 and by an elastic analysis considering the
construction sequence only. From the obtained results, -1000
-407
-688
the following can be inferred: (1) the bridge experiences -2000 -925 -703
-996
the maximum negative tendon moment at the first mid-span -3000
after construction of the first span (see Fig. 6(a)), and this
-4000
moment value is determined as a boundary value for the 0 30 60 90 120 150
first mid-span. As the bridge maintains a statically determi- LENGTH (m)
(a) t = 1 year
nate state at this construction step, no moment variation
due to the time-dependent behaviors of concrete and ten- SPAN
1st 2nd 3rd 4th 5th
dons appears, and the same boundary values at both enve- 4000
TD Analysis
lope curves are produced; (2) the negative moments at each 3000
Trost & Wolff
Proposed Method
mid-span after the first span represent slightly reduced but
MOMENT (ton-m)

2000
uniform values in a bridge constructed by a MSS, as these 585 488
1000
values are always obtained at the last span post-tensioned
at each construction step; (3) the maximum positive 0

moments obtained at each interior support can also be -1000


-481
explained by the same reasoning; (4) when the results using -2000 -972 -724 -773
-1040
Eq. (4) and the rigorous analysis are compared, Eq. (4) pro-
-3000
posed in this paper gives a slightly smaller value at the last
-4000
mid-span for the negative moment and very similar bound- 0 30 60 90 120 150
ary values along the span for the positive moments; and (5) LENGTH (m)
the tendon moment envelope can be constructed with Eq. (b) t = 10 years
(4). The positive moment envelope curve is obtained by
SPAN
directly connecting the two boundary values at the first 1st 2nd 3rd 4th 5th
and last interior supports, and the negative moment develop 4000
TD Analysis
Trost & Wolff
curve can also be determined if the boundary value for the 3000 Proposed Method

first mid-span is taken from the elastic analysis and if the


MOMENT (ton-m)

2000
630 556
negative moment value at the last span, obtained by Eq. 1000
(4), is used as the boundary value for the other mid-spans.
0

-1000
4. Determination of design moments -550
-2000 -1040 -772 -858
-1100
To verify the effectiveness of the relation introduced in -3000
this paper, the internal moment variations by the dead load -4000
and prestressing tendons obtained through rigorous time- 0 30 60 90 120 150
LENGTH (m)
dependent analyses [7–9,11,15] are compared with those
(c) t = 100 years
obtained by the superposition of Eq. (4), and the elastic
dead load moment. The five-span continuous bridge in Fig. 12. Total moment variations after construction.
2150 H.-G. Kwak, J.-K. Son / Computers and Structures 84 (2006) 2141–2150

SPAN loads also show that the design moments by the proposed
1st 2nd 3rd 4th 5th method can effectively be used in determining an initial sec-
4000
Rigorous Analy sis tion assumed for the analysis of a bridge in the preliminary
3000 Proposed Method (100 YEARS)
design stage.
2000
MOMENT (ton-m)

634
438 558
1000
298 Acknowledgement
0
The authors would like to thank the Infra-Structures
-1000 Assessment Research Center (ISARC) funded by Korea
-2000 -1040
-858
-1210 -1230
Ministry of Construction and Transportation (MOCT)
-1230
for financial support.
-3000

-4000
0 30 60 90 120 150
References
LENGTH (m)

Fig. 13. Total moment envelope curve for example structure. [1] AASHTO. Standard specifications for highway bridges. 15th ed.
Washington, DC, 1992.
[2] ACI Committee 209. Prediction of creep, shrinkage and temperature
design moments by the superposition of Eq. (4) for the ten- effects in concrete structures. ACI 209R-92, American Concrete
Institute Detroit, 1997.
don moment and the elastic moment considering the con-
[3] Barker JM. Post-tensioned box girder manual. Post-Tensioning
struction sequence for the dead load moment, effectively Institute: USA, 1978.
represents the boundary values for the maximum and min- [4] Bazant ZP. Prediction of creep effects using age-adjusted effective
imum moments used as the reference values in determining modulus method. ACI J 1972;69:212–7.
the section dimensions in the preliminary design stage. [5] British Standards Institution. Part 4. Code of practice for the design
Therefore, the moment envelope curve can also be con- of concrete bridges. (BS 5400:Part 4:1984). Milton Keynes. United
Kingdom, 1984.
structed with the moment distribution by the proposed [6] Gilbert RI, Mickleborough NC. Design of prestressed concrete.
method through a similar procedure to that noted with London: E&FN Spon; 1990.
regard to the tendon moment envelope. The positive [7] Heinz P. RM-spaceframe Static analysis of SPACEFRAME, TDA-
moment envelope curve can be determined by directly con- technische Datenverarbeitung Ges.m.b.H., 1997.
[8] Kang YJ. Nonlinear geometric, material and time dependent analysis
necting the two boundary values at the first and last mid-
of reinforced and prestressed concrete frame. Report no. UC-SEEM
spans, and the negative moment at the first interior support 77-1, UNIV. of California, Berkeley, 1977.
can be used as the boundary values for all the interior sup- [9] Kasti FA. Nonlinear material and time dependent analysis of
ports, even though it varies by approximately 13% from the segmentally erected reinforced and prestressed concrete composite
value obtained through the rigorous analysis. This differ- 3D frame structures. Report no. UCB/SEMM 90-03, University of
California, Berkeley, 1990.
ence does not have a great influence, as the obtained enve-
[10] Ketchum MA. Redistribution of stresses in segmentally erected
lope serves as the starting value for the determination of prestressed concrete bridges. UCB/SESM – 86/07, Department of
the initial sections of a bridge. Civil Engineering, University of California, Berkeley, 1986.
[11] Kwak HG, Seo YJ. Numerical analysis of time-dependent behavior of
5. Conclusions pre-cast pre-stressed concrete girder bridges. Construct Build Mater
2002;16:49–63.
[12] Kwak HG, Seo YJ. Shrinkage cracking at interior supports of
A simple but effective relation that can simulate the continuous pre-cast pre-stressed concrete girder bridges. Construct
internal tendon moment variation due to the creep defor- Build Mater 2002;16:35–47.
mation of concrete, relaxation of tendons, and changes in [13] Kwak HG, Seo YJ, Jung CM. Effects of the slab casting sequences
the structural system during construction is proposed; as and the drying shrinkage of concrete slabs on the short-term and
long-term behavior of composite steel box girder bridges, Part I. Eng
well, a new method to determine the design moments is
Struct 2000;23:1453–66.
introduced in this paper. The design moments for a dead [14] Kwak HG, Seo YJ, Jung CM. Effects of the slab casting sequences
load at any construction step can be determined on the and the drying shrinkage of concrete slabs on the short-term and
basis of an elastic analysis considering the construction long-term behavior of composite steel box girder bridges, Part II. Eng
sequence only. The design moments after construction Struct 2000;23:1467–80.
can also be determined from the elastic moment for the [15] Kwak HG, Seo YJ. Long-term behavior of composite girder bridges.
Comput Struct 2000:583–99.
total structure without considering any effect. When the [16] Magura DD, Sozen MA, Siess CP. A study of stress relaxation in
longitudinal tendons, which may affect the internal prestressing reinforcement. J PCI 1964;9(2):13–57.
moment redistribution during construction, need to be con- [17] Neville AM, Dilger WH, Brooks JJ. Creep of plain and structural
sidered in calculating the internal moments and the corre- concrete. London: Construction Press; 1983.
[18] Trost H, Wolff HJ. Zur Wirklichkeitsnahen Ermittlung der Beansp-
sponding normal stresses at an arbitrary section, Eq. (4)
ruchungen in Abschnittswiese Hergestellten Spannbeton-Ragwerken.
can be suitable employed. Bauingenieur 1970;5.
In advance, the moment envelope curves for the dead [19] Xanthakos PP. Theory and design of bridges. New York: John
load, longitudinal tendons, and the superposition of both Wiley & Sons Inc.; 1994.

You might also like