Professional Documents
Culture Documents
in Large Spans
Antonio Albuquerque Póvoas, President, AP-BCS-Portugal, LDA., Lisbon, Portugal. Contact: antonio.povoas@sapo.pt
DOI: 10.2749/101686612X13363869853374
Abstract
The use of movable scaffolding systems
(MSSs) was initially developed for
bridge spans between 36 m and 50 m,
and in very few projects for a maxi-
mum of 60 m. Projects of 70, 80 and 90
m spans were usually executed by form
travelers. The high speed train (HST)
viaducts brought heavier concrete gird-
ers owing to the live loads required for
such superstructures. To perform the
construction of such heavy viaducts,
as for example the AVE-LLobregat
Viaduct in Barcelona, with unit loads of
400 KN/n and spans of 50 m, stronger
MSS were needed. The study of such
bridge construction equipments and
the projects that followed, going up to
60 m span, also for HST, demanded a
step forward in the conception of the
MSS from its structural system to the Fig. 1: Vasco da Gama South viaduct, Lisbon
mechanical equipments required for
its main operations, such as the open-
ing of the formworks and the move- spans between 36 and 50 m, and in The article is directed at both bridge
ment of the MSS from pier to pier. very few projects for a maximum of design engineers and site construction
As a conclusion of the studies made for 60 m between piers. engineers.
long spans with bridge design engineers All projects for 70, 80 and 90 m were
and after the construction of very heavy usually performed by form travellers. Evolution of Movable
60 m span viaducts and road viaducts for
70 m spans, today it can be stated that it is The high-speed train (HST) viaducts Scaffolding Systems
possible to use MSS for spans of 80 and brought very heavy concrete girders as
90 m with the machines developed so far. a result of the live loads required for MSS Evolution in Portugal
As another consequence of those stud- such superstructures. To perform the
The design and supply of MSS in
ies it can be concluded that for such high construction of such heavy viaducts,
Portugal, specially designed to carry
spans it is very important to develop a as for example the AVE–Llobregat
the rebar cages and access the front
joint design of the MSS and the bridge Viaduct in Barcelona, with concrete
pier, started in 1994 with equipments
because the optimal cost solution weight loads of 400 kN/m and spans
designed especially for motorway
can be quite different from the initial of 50 m, stronger MSS were needed.
bridges in Portugal, being the first two
idea of the bridge design engineers. The study of such bridge construction
supplied for the A4 motorway (Porto-
The cast in situ method with MSS being equipments and the projects that fol-
Amarante), followed by another four
the most economical for concrete via- lowed, with 60 m span, also for HST,
used for Vasco da Gama Bridge con-
duct construction, the use of MSS can made a step forward in the concep-
struction, in Lisbon (Fig. 1).
be more popular and achieve higher tion of the MSS from its structural
performances if the bridge engineers’ system to the mechanical equipments The motorway viaducts in Portugal are
community provides factual informa- required for its main operations, such mostly designed using π sections up to
tion on how far and how often the tech- as the opening of the formworks and 45 m span between piers and Vasco da
nique can be used. the movement of the MSS from pier to Gama Bridge had 88 spans of 45 m,
pier. cast in situ girders that weighted about
Kewords: movable scaffolding systems; 250 kN/m, requiring 46 m between the
bridge; construction equipment; live The evolution of bridge construc-
tion equ ipments continues and now MSS supports due to the spans after
loads; long span bridges. the expansion joints. The nose of the
some companies are able to produce
MSS was 48 m long passing over the
Introduction MSS capable of casting in situ spans
front pier.
of 72 m or even larger, with girder
Movable scaffolding systems (MSS) weights up to 300 kN/m in one single The equipments were designed with a
were initially developed for bridge stage. load capacity of 300 kN/m (concrete
2% 2%
0,333
0,20
2,00
0,20
1 2 3 4 5 6 7 8 9 1011 1213
0,15
1,10
0,27 0,66 0,73 0,73 0,73 0,73 0,73 0,73 0,66 0,27
Polystyrene ∅ 1350
Center of the span cross section
Scale 1:100
6,00
0,27 0,66 0,73 0,73 0,73 0,73 0,73 0,73 0,66 0,27
0,40
1,30
1 2 3 4 5 6 7 8 9 1011 1213
Cross section of
6,00 × 1,30
0,45
0,20
1,80
Section A-A
A A Scale 1:100
Natural
A Ground
1 4 7 10 13
2 3 5 6 8 9 11 12
0,27 0,66 0,73 0,73 0,73 0,73 0,73 0,73 0,66 0,27
4200
4200
2700
BMVE 1,70
1+500
1+400
1+300
1+200
1+100
1+000
0+900
0+800
0+700
5
PMVE (~5.80)
10
PMVE (~5.80)
1+5
Pedr
ad o Na
0+7
00
00
do e
1+4
ngan
0+800
00
o E-1
1+300
Pd
12,30
0+900
E-2 P-1
1+200
P-14
1+000
2,55 Tc 8,19
Pd
1+100
P-13 P-2 11,35
2,67 Mb T 16,2
P-12
P-3 c
P-4 11,61 15.5
16,60 3
P-11
5,50 P-10 P-5
3,1 P-9 P-6 Tc
6 P-8 P-7
Mb 16,96
7,4 1,5
CA
9 3,5 6 Pd
NA
4 17,12
1,8
LP
3,876
3,8 22.,656
5 8
1481 RIN
Pun CIP 17,27
ta do
enga
AL
Ase 2,2 no
rrad
oiro 3,3 6
5
E-1 E-2
P.K. 0+689.029
16,08 P.K. 1+410,029
5
R1200,00
x=50
2
3
E–1
8295
5
10 P.K.
0+68
4
9,02
,000
9
P.K. P–1 Y=47
0+73
0,02 4149
Pedraplen 9 0
0,00 2 9
E–41
1,25 H/1,00 V 0,02
Pedra do Navio P–2 1+
P.K.
Enseada do Engano P–100,029
Junta de P.K. 0+
800,02
NOT dilatacion 9 36
A P P.K. 1+
P.K. 0+ –3 P–9 0,029
870,029 29
P–4 P.K. 1+
P–8
00
Junta
P.K. 0+940,02
9 P–5 P–6 P–7 P.K. 1+2
20,029
0+7
de Dilatacion
P.K. 1+010,029
P.K. 1+080,029 P.K. 1+150,029
al
cip
1+400
rin
5
0
lP
10
0+80
na
Ca
1+300
Er
0+900
Tc
1+200
pd
1+000
1+100
Er
Punta do Engano
which allowed the rear support of the on the span pier and a rear support considering the location of the rear
MSS to be placed 16 m ahead of the over the cantilever, 63 m behind. support of the MSS at 63, 58,5 and
rear pier in all spans. 54 m from the front pier (Fig. 12).
The MSS was then designed 148 m
long, for 63 m or less between concret- These calculations were done consid-
Design Requirements for the MSS ing supports. This design configuration ering the reduction of the MSS length
of the MSS allowed it to reach 70 m and self weight, and the corresponding
The initial design of the MSS was done
span between piers (Figs. 9, 10 and 11). reactions.
considering that the construction joint
would be at 1/5th of the span, with Meanwhile, some of the calculations After a global cost analysis for pre-
14 m cantilever ahead of the pier, and had been made using 1/4th of the span stressing + concrete + MSS final cost,
the MSS should have a front support construction joints, instead of 1/5th, the client finally decided to use 1/5th of
Pavement = 0,08 m
3,12% 3,10%
0,4
0
0,40
2,65
3,20
5,00
4,00
4,50
5,50
5,80
1,50
2 Piles ∅ 1,80 m
4,20
148 000
63 000 71 000
Fig. 9: MSS 148 m long with 63 m between concreting supports (units: mm)
139 000
Fig. 10: MSS 139 m long with 54 m between supports (units: mm)
the span joints, and a 9 m shorter MSS its impact on the final bridge cost Movable Scaffolding Systems
with 54 m between supports, which play a vital role, which is worth giv- for 80–90 m Span
became the cheapest global solution. ing it much more relevance during the
design stage of the bridge. Another important conclusion that
was demonstrated was that the tech-
Relevance of the Construction Joint The increase in weight of the MSS nology and equipments needed to
Location steel girder was about 70 t by lowering build large spans of 70, 80 or 90 m in
its span and total length 9 m, which one stage, using span-by-span–cast
The global cost studies made for this corresponded to about 300,000 USD.
Viaduct brought very important con- in situ method, already exists.
clusions concerning the interaction The increase in active steel as a result
of this solution for the whole bridge Considering the same MSS previously
between the concrete design and designed for Viaducto do Engano,
the building construction equipment was about half that amount. It meant
that about 150,000 USD were saved with the rear concreting support 63
design for large span viaducts.
by shortening the span of the MSS m behind the pier, it was possible to
One important conclusion is that the although spending a bit more on pre- cast 60 m between concreting sup-
location of the construction joint and stressing the cables. ports plus a cantilever 20 m ahead,
Conclusions
On the basis of the studies made on
long span bridges for very heavy 60 m
span viaducts and 70 m span road via-
80,000 60,000 20,000
ducts, it can now be stated that it is
Concreting possible to use MSS for spans of 80 m
and 90 m with the mechanical develop-
Fig. 13: Concreting 80 m span with the same MSS of Engano Viaduct (units: m) ment achieved so far.
It can be concluded from those stud-
making an 80 m concrete girder sponding pre-stressing cables and con- ies that for such long spans it is very
(Fig. 13). struction joints, and the construction important to arrive at a joint design
rhythm is normally 4–5 m per week, for the MSS and the bridge because
in two directions per pier and pair of the optimal global cost can be a differ-
Comparing MSS and Form travellers. It means that 80 m spans, for ent solution than the initial idea of the
Travellers: Pre-stressing example, can be built in 8 weeks with a bridge design engineers.
pair of form travellers.
Requirements during the The “cast in situ” method with MSS
Construction Stage In that 70 m span viaduct, an average being one of the most economical for
cycle of 10 days per span was achieved, concrete viaduct construction, the use
When building large spans with meaning that even if the 80 m span of MSS can be more popular and can
form travellers, the concrete girder is would require 2 weeks, the construc- achieve even higher performances if
designed with multiple segments and tion with MSS could take 25% of the bridge engineers’ community pro-
variable inertia increasing from the the time needed by the pair of form vides factual information on how far
piers to the span centre. travellers. and how often the technique can be
This construction method requires The concrete girder is also designed for used.
joints every 4 or 5 m, with the corre- carrying the dead load of the travellers