Professional Documents
Culture Documents
JIMMA UNIVERSITY
RM 7628 /1
JIMMA UNIVERISTY 2021
1 Bridge Assignment
JIMMA UNIVERISTY 2021
superstructure is launched over temporary sliding bearings on the piers. To keep the
bending moment low in the superstructure during construction, a launching nose is
attached to the front of the bridge deck.
The main advantages for using this construction methodology, rather than other
traditional methods, are:
Minimal disturbance to environmentally sensitive areas
Smaller assembly zone required
Greater safety during construction which is mainly carried out at ground level
Economy of transportation and general reduction in construction elements
Higher quality finish and performance derived from easier working conditions
and repeatability of tasks
Ease of access to restricted or limited sites – such as over rivers, deep valleys,
road or train lines, in poor soil conditions or environmentally protected areas
Although its significant advantages make using this technique a highly attractive
option, certain aspects require a high level of expertise – both in terms of people
and equipment – offered by Members of the BBR Network. They have much
experience, acquired over many years, in the techniques of incremental launching
and a track record for successful delivery of launched structures all over the
world.
2 Bridge Assignment
JIMMA UNIVERISTY 2021
method uses a movable supporting beam, gantry, for the false work that reaches over
at least one span but usually over the length of two spans. With the supporting beam
in place, transverse beams along the gantry secure the formwork and working
platform and the building process can be carried out efficiently. With special roller
bearings and launching jacks the gantry can easily be moved forward along the bridge
as the construction proceeds. The travelling gantry system is most suited for spans of
30 to 60m.
IV. Precast span-by-span
The precast span-by-span bridge construction method offers a very high speed of
construction. It is most often used in conjunction with an erection truss under the
bridge segments or an overhead erection gantry to guide the precast elements into
position. The span-by-span construction technique consists of the following primary
steps:
Erecting the segments for the entire span onto a temporary erection girder spanning
between a pair of adjacent permanent piers
Installing and stressing longitudinal PT tendons enabling the segments to span
on their own
Advancing the erection girder into place to erect the adjacent span
Since there is only one cycle of stressing and grouting of tendons per span, the
method can be significantly faster than precast balanced cantilever
construction, which requires one such cycle per pair of segments.
The most common use of span-by-span construction is to build long viaducts with
spans of similar length. The method has been used most often for spans ranging
from 25m to 45m. As spans increase, there is a significant increase in the cost of
the erection girder. Erection girder can support the segment from below, or above
– under slung and overhead launching gantries.
Alternatively, full-span precast beams can be delivered from the precast beam
production to the erection front by the launching gantry. This method allows a fast
rate of erection.
3 Bridge Assignment
JIMMA UNIVERISTY 2021
4 Bridge Assignment
JIMMA UNIVERISTY 2021
Aesthetics
Economics and ease of Maintenance:- Bridge with the minimum number of spans,
fewest deck joints, and widest spacing of girders will be the most economical
3) What are the designe loads of bridge superstructure, abutments and piers?
Transient Loads
Live Loads
LL: Vehicular live load
PL: pedestrian live load
5 Bridge Assignment
JIMMA UNIVERISTY 2021
IM: vehicular dynamic load allowance
CE: vehicular centrifugal force
BR: vehicular braking force
CT: vehicular collision force
Wind Loads
WL: wind on live load
WS: wind load on structure
For abutments and piers design
Water Loads, WA
Static pressure
Buoyancy
Stream pressure
Wave load
Earth pressure due to live load surcharge, LS
SE: settlement
Loads on pier like:- Dead Loads, Live Loads, Vehicular Braking Force, Wind
Loads, Uniform Temperature Forces , Force of Stream Current , Buoyancy , Ice,
Centrifugal Force, Extreme Event Collision Loads and etc.
Abutments loads like:- The dead load forces, DC and DW, live load, Earth
surcharge, Earth pressure, Water load, Temperature and shrinkage, Vehicular
braking force from live load and etc.
4) Mention the factors that affect the load distribution in RCC girder bridges?
The stiffness of the slab and its span.
Spacing and stiffness of beams.
5) List the types of bridge structures and their uses.
a) T-Girder bridges: are generally economical for spans of 10-20m. These are usually
constructed on ground supported false work.
b) Composite Steel Plate Girder Bridges: spans of 25-50m and have been used for spans
well over 100m. They have low dead load, which may be of value when foundation
conditions are poor.
6 Bridge Assignment
JIMMA UNIVERISTY 2021
c) Composite Steel Box Girder Bridges: are used for spans of 20-150m. These bridges are
more economical in the upper span ranges where depth may be limited.
d) Culverts: are used for small spans through highway embankments with span length of
15m.
e) Slab Bridges: for small spans up to 12m. These bridges can be built on ground supported
false work or constructed of precast elements
f) A truss bridge: is a bridge whose load-bearing superstructure is composed of a truss.
This truss is a structure of connected elements forming triangular units.
g) Cantilever bridges are built using cantilevers—horizontal beams supported on only one
end. Most cantilever bridges use a pair of continuous spans that extend from opposite
sides of the supporting piers to meet at the center of the obstacle the bridge crosses.
h) Arch bridges: have abutments at each end. The weight of the bridge is thrust into the
abutments at either side.
i) Suspension bridges are suspended from cables. The earliest suspension bridges were
made of ropes or vines covered with pieces of bamboo. In modern bridges, the cables
hang from towers that are attached to caissons or cofferdams.
j) Cable-stayed bridges, like suspension bridges, are held up by cables. However, in a
cable-stayed bridge, less cable is required and the towers holding the cables are
proportionately higher
6) Compare cable stayed bridge and suspension bridges.
Cable-stayed bridges
In cable-stayed bridges, the cables are straight and extend from one tower and
connected to the deck directly at discrete points. Being, taut, they furnish
relatively inflexible support along the span at several points and provide a
bridge with relatively greater stiffness than that achievable in suspension
bridges.
A cable stayed bridge is dependent upon towers/pylons which are the load-
bearing element of the structure. Cables are connected from the pylons to the
deck below.
A Cable-stayed bridge is differ from their suspension bridge in a way they
don't require anchorages, nor do they need two towers.
7 Bridge Assignment
JIMMA UNIVERISTY 2021
In a cable stayed bridge, most all of the load is transferred from the road to the
towers directly through cables and balanced on each side of the towers. Except
for when affected by wind loads the towers are mostly in compression.
In cable-stayed bridges, the towers are the primary load-bearing structures that
transmit the bridge loads to the ground. A cantilever approach is often used to
support the bridge deck near the towers, but lengths further from them are
supported by cables running directly to the towers. That has the disadvantage,
unlike for the suspension bridge that the cables pull to the sides as opposed to
directly up, which requires the bridge deck to be stronger to resist the resulting
horizontal compression loads, but it has the advantage of not requiring firm
anchorages to resist the horizontal pull of the main cables of the suspension
bridge. By design, all static horizontal forces of the cable-stayed bridge are
balanced so that the supporting towers do not tend to tilt or slide and so must
only resist horizontal forces from the live loads.
Suspension bridge
In suspension bridge it has elements like major suspension cables and minor
suspension cables which hold the deck unlike cable stayed bridge.
In suspension bridges, the cables ride freely across the towers, transmitting the
load to the anchorages at either end. In cable-stayed bridges, the cables are
attached to the towers, which alone bear the load.
In a suspension bridge, a portion of the load is transferred to towers
(sometimes…primitive suspension bridges can lack towers) from the deck via
suspender cables tied to catenary cables.
In suspension bridges the main cables are curved and continuous between the
towers. The deck and other vertical loading are suspended from these cables at
relatively short intervals. Being relatively flexible, the main cable develops
funicular shape, which is a function of the magnitude and position of the
loading.
This type of bridge has cables suspended between towers, with vertical
suspender cables that transfer the live and dead loads of the deck below, upon
8 Bridge Assignment
JIMMA UNIVERISTY 2021
which traffic crosses. This arrangement allows the deck to be level or to arc
upward for additional clearance.
The suspension cables must be anchored at each end of the bridge, since any
load applied to the bridge is transformed into a tension in these main cables.
9 Bridge Assignment
JIMMA UNIVERISTY 2021
The relatively shallow depth of box girders is an advantage where headroom is limited
like in urban overpasses.
Monolithic construction of the superstructure and substructure offers structural as well as
aesthetic advantage. The pier caps for continuous box girders can be placed within the
box, facilitating rigid connection to the pier.
They provide space for utilities such as water and gas lines, power, telephone and cable
ducts, storm drains and sewers, which can be placed in the hollow cellular section.
The other advantages are, as mentioned previously, their torisional stiffness and
aesthetics.
Box girders offer better resistance to torsion, which is particularly of benefit if the bridge
deck is curved in plane. Additionally, larger girders can be constructed, because the
presence of two webs allows wider and hence stronger flanges to be used. This in turn
allows longer spans.
Box girders are more suitable for larger spans and wider decks. Economy and aesthetics
further lead to the evolution of cantilevers in top flanges and inclined webs in external
cells of box girder. The dimension of the cell could be controlled by pre-stressing.
9) Comment on the different kinds of abutments and piers?
Abutments
a. Spill-Through or Open
A spill-through or open abutment is mostly used where an additional span may be added to
the bridge in the future. It may also be used to satisfy unique construction problems. This
abutment type is situated on columns or stems that extend upward from the natural ground. It
is essentially a pier being used as an abutment.
It is very difficult to properly compact the embankment materials that must be placed around
the columns and under the abutment cap. Early settlement and erosion are problems
frequently encountered with spill-through or open abutments
b. Pile-Encased
Pile-encased abutments should only be used where documented cost data shows them to be
more economical than sill abutments due to site conditions. For local roads right-of-way
acquisition can be difficult, making the A5 a good option. Requiring crane access from only
one side of a stream may be another reason to use a single span bridge with A5 abutments, as
10 Bridge Assignment
JIMMA UNIVERISTY 2021
would savings in railing costs. Steeper topography may make A5 abutments a more
reasonable choice than sill
abutments. In general, however, using sill abutments with longer bridges under most
conditions has cost advantages over using the Type A5 abutments. Type A5 abutments may
require additional erosion control measures that increase construction cost.
c. Gravity Abutment: These are used for abutments of small height.
d. Cantilever Abutment: derive lateral resistance through embedment of the stem by cantilever
action
e. Counterfort Abutment: used for larger heights for which cantilever abutments will be
uneconomical
f. Stub Abutment: used at the top of an embankment or slope. Unless rock foundation exists at
the site, stub abutment is supported on piles.
g. Spill through Abutment: this utilizes two or more columns with a cap beam at the top.
h. Reinforced earth Abutment: It is being used in many parts of the world, and is preferred for
its low cost and aesthetics.
Pier Types
a. Multi-Column Piers
Multi-column piers, as shown in Standard for Multi-Columned Pier, are the most
commonly used pier type for grade separation structures.
b. Pile Bents
Pile bents are most commonly used for small to intermediate stream crossings and are
shown on the Standard for Pile Bent. Pile bents shall not be used to support structures
over roadways or railroads due to their susceptibility to severe damage should a vehicular
collision occur.
c. Pile Encased Piers
Pile encased piers are similar to pile bents except that a concrete encasement wall
surrounds the piles. They are most commonly used for small to intermediate stream
crossings where a pile bent pier is not feasible. Pile encased piers are detailed on
Standard for Pile Encased Pier.
d. Solid Single Shaft / Hammerheads
Solid single shaft piers are used for all types of crossings and are detailed on Standards
for Hammer head Pier. The choice between using a multicolumn pier and a solid single
shaft pier is based on economics and aesthetics. For high level bridges, a solid single
shaft pier is generally the most economical and attractive pier type available.
11 Bridge Assignment
JIMMA UNIVERISTY 2021
e. Solid Wall Pier: used at water crossings since they can be constructed to proportions
those are both slender and streamlined, which has a minimal resistance to flow.
f. Hammer Head Pier: These are used for high piers. These are predominantly used in
urban areas because they are attractive and occupy minimum space providing relatively
large clearance for underpass traffic.
g. Column Bent Pier: consists of a cap beam and supporting columns in the form of a
frame.
10) List the causes of scour nearby a piers and the methods to protect it.
The main causes of scour around the bridge piers are
natural scour and channel shifting on alluvial rivers
scour caused by changes to the river channel u/s or d/s
general scour caused by reduction in the channel width at bridge site
local scour at the base of piers, abutments and river training works due to turbulence
Riprap: Is carpet of loose stones, which protects the loose bed material for bed protection
and loose bank or embankment material from erosion by water current
Gabion and Reno mattresses: The standard gabion is a rectangular basket made of steel
wire mesh with sizes of 2m, 3m and 4m long by 1m wide by 0.5m or 1m high.
Filter Blankets: used to protect non – cohesive and fine bank materials that may be
washed away through the space between the voids in riprap or gabion lining.
Vegetation
aprons or revetments
groynes
11) What are the approaches for obtaining the depth scour at bridge piers.
The Area – Velocity Method: In this method the flow through the structure is assumed
to be equal to the unrestricted flow calculated on the basis of velocity measurement or
estimates made.
12 Bridge Assignment
JIMMA UNIVERISTY 2021
The Competent-Velocity Method: The competent velocity (Vc) is the largest velocity
that will not cause scour to the river bed. In this method a probable scour line is drawn
and area of flow increased (by As) until the resulting mean velocity of flow is reduced
to Vc.
12) Clarify the purpose of bridge bearings and issue that affect their selection.
Main functions
To transmit loads from the superstructure to the substructure, and
To accommodate relative movements between the superstructure and the
substructure.
A simply supported span requires fixed bearings at one and expansion joints at the other.
A continuous girder require fixed bearing at one and expansion bearing on all other
supports
A two span girder will have fixed bearing at the center support and expansion bearings at
the two abutments
13) Describe when to select a bridge or a culvert for a site of interest.
When the waterway opening is less than about 15m2, and particularly where the road crosses
the waterway on a relatively high embankment, a culvert will usually be cheaper than a
bridge
14) What do you think the positioning and alignment of the culverts.
it is fine to use culverts when:-
Where the waterway opening is less than about 15m2, and particularly where the
road crosses the waterway on a relatively high embankment, a culvert will usually
be cheaper than a bridge
For a span ranging up to 6m
For cross drainage work
Where a road crosses a valley, the lowest point requires a vent, whether there is an
established stream or not
13 Bridge Assignment
JIMMA UNIVERISTY 2021
Where there is an established stream, the culvert should follow the existing alignment,
unless the alignment can be improved
The gradient of the culvert should be the same as the gradient of the stream.
Measures may be necessary to ensure that the watercourse does not move. This could
cause severe damage and the consequent change of location of the culvert would be
expensive.
15) Why do you inspect and maintain bridge structure?
The objective of bridge inspection comprises monitoring and evaluation of the
performance of each bridge structure throughout its service life so that any deficiency in
performance could be detected and corrected early.
The object of maintenance inspections is to detect in good time any defect which may
cause an unacceptable safety or serviceability risk or a serious maintenance requirement
in order to safeguard the public, the structure and the environment and to enable
appropriate remedial action to be taken.
We have to maintain, because of the bridge have to serve for its life time safely without
causing any default. Since bridges were constructed with huge amount of nation
investment we need to conserve this notational investment and to secure public safety.
14 Bridge Assignment