Professional Documents
Culture Documents
• In this method, bridge piers are built first in required alignment. Then the
superstructure part to be built is dived into number of sections. Now an
area behind the one of those abutments is selected. In this stationary area,
a setup is made to cast the one section of bridge superstructure.
For bridge decks greater than 250m in length, the method of incremental launching can be considered. With
this method of construction the bridge deck is built in sections by pushing the structure outwards from an
abutments towards the pier. It is most suited to the rapid construction of bridges with a constant radius of
curvature such as constant depth of box girder segments.
The construction sequence begins behind one abutment where a highly mechanized prefabrication deck mold
is set up removing the need for temporary supports with this method. A rigid framework is then attached
enabling the production of cast-in-situ segments. In-situ deck segments range in length from 5m to 30m. when
each segment is complete it is placed on sliding bearings and pushed through into the span.
A steel nose is also positioned at the front of the first span formwork. This allows for the necessary deck
cantilever length as the span approaches the first pier.
Bridge decks of 1km can be built by this method with a rate of construction of 30m per week.
After the casting of one section, it is pushed along the bridge axis
using jack system or friction launching system which is arranged
prior to the casting of structures.
the basic concept of balanced cantilever construction method is to attach the segments in an
alternate manner at opposite ends of cantilevers supported by piers.
this method is easily adaptable to irregular and long span lengths, congested project sites, rough
and water terrain, rail crossings, and environmentally sensitive areas.
it is highly suitable for building cable-stayed bridges. This is because once segments are placed,
they will be supported by new cable-stays in each erection stage. Therefore, no auxiliary supports
are required, and hence it is both economical and practical method for long cable-stayed bridges.
Procedure for balanced cantilever method of cast-in-situ bridge
Construction
• Thereafter, soffit shuttering, shuttering for web & deck shuttering is fixed on both sides of pier
• Then concreting is done on both sides of the pier . The segment production rate for form travelers
is usually one segment every 5 days per traveler.
Cast-in-Situ Post
Tensioned Method
Cast-in-Situ Post Tensioned Method
• more demanding method because of its durability and applicability to complex
bridge curves etc. In this method along with concrete and reinforcement, steel
strands or tendons are also used to introduce post tensioning.
• When the formwork is prepared, strands are arranged with in the
reinforcement and concrete is filled. After the hardening of concrete, the
strands which have been passed through the concrete are pulled by the jack up
to certain tensile force which was pre-determined. Now, the steel stands
should be locked.
This type of construction increases the load
carrying capacity of bridge and improves the
durability of bridge. Post tensioning eliminates the
use of intermediate supports for long span bridges.
Advantages of Cast-in-
Situ Construction
Methods
does not require any heavy lifting equipment or transporting
equipment
Precast beam decks are generally used for short span bridges ranging between
5m to 50m – these may be railway or motorway bridges. Standard inverted tee
beams or M-beams are chosen and positioned by crane.
Precast Decks
• Short line method: In this rate of segment production is slow. Three or four
segments cast at a time.
• Long line method: In this rate of segment production is fast. Segments equal to
one span cast at a time.
Cast-in-Place Segments
Vs. precast segments
Cast-in-place construction proves to be very beneficial when large, considerably heavy segments
are required to be constructed. So, instead of handling the segments, only materials have to be
transported thus influencing the type and size of required equipment.
For concrete cable stayed bridges free cantilever construction is considered economical. With this method the
deck segments can be either precast or cast-in-situ by travelling shutter arrangement. This is done by
transmitting the cable stay forces, through its extremeties, at it anchorage points. Stay cables are firmly
attached to the anchorages which are designed to resist the buckling forces of the loads.
Detailing of all anchorages should allow for their safe construction and accessibility for inspection and
maintenance on completion. In concrete stay-cabled anchorages are placed under the deck.
Advantages:
• Faster construction time compared to other bridge type
• More rigid than suspension bridges
• Cost effective
• Flexible design
Disadvantages:
• Only suitable for short to medium distances( shorter span)
• Cables can be prone to corrosion and high levels of fatigue
• Not suitable for extreme climate conditions or earthquake prone areas
Arch Method of Bridge
Construction
The arch is the most natural bridge shape in nature. Originally constructed of
stone, today such bridges are built of reinforced or precast concrete. They are
often the most economical choice where a bridge is required to cross over
inaccessible landscapes.
The development of modern arch construction methods has made the use of
arch construction more economical by removing the need of expensive
centering formwork. Though abutments still must be well founded on rock or
soiled ground.
Advantages:
• Very strong
• Less force on abutments
• It can be built off site and transported into place
Disadvantages
• Regular maintenance is required to ensure the stability of the hangers and arch
• The size of each span is limited as compared with other bridge type
• Arches are typically more expensive to build than towers or pillars of other types of bridges of the
same length
Common Equipments involved in bridge construction
• Aerial Lifts
• Excavators
• Drones
• Backhoes
• Cranes
• Incremental Launching Machine
Factors Affecting
Selection of Bridge
Construction Methods
Before a bridge can be built an appropriate method of construction must be chosen.
The decision is made by the design team. The principle factors considered by the
design team when choosing a suitable method of construction are given below:
• Wu, Y., & Lu, P. (2022). Comparative analysis and evaluation of bridge construction risk with
multiple intelligent algorithms. Mathematical Problems in
Engineering, 2022 doi:https://doi.org/10.1155/2022/2638273
• Zeng, Y., Wang, Y., Shi, Z., Tan, H., & Gu, A. (2022). Experimental study on stability of long-
span PC cable-stayed bridge during the construction periods. Advances in Civil
Engineering, 2022 doi:https://doi.org/10.1155/2022/8578684