Professional Documents
Culture Documents
PRACTICES IN BRIDGES
BRIDGE CONSTRUCTION METHODS
• Precast segmental deck construction is used for long bridges where the
deck depth is difficult for cast in situ construction.
• Box girder deck segments are generally used where the segment can
be 2m or less deep, between 2.5m and 4m long carrying a deck upto
15m wide are generally used.
• Where in-situ post-tensioning is favored the segments can be
prestressed either internally or externally.
• Internal tendons must be protected from moisture attack.
4. Span by Span Casting method of Bridge Construction
• This method is associated with cantilever construction method but
with many advancements in the technique.
• It is considered as most economic and rapid in construction.
• For long bridges and viaducts with an individual span up to 60m, the
method is feasible.
• Decks are begun at one abutment and constructed continuously by
placing segments to the other end of the bridge.
• Segments can be positioned by either a temporary staying mast system
through more commonly using an assembly truss.
• Span by span is a relatively new construction technique historically
associated with cantilever construction but the advancement in external
prestressing has enabled its own potential use to grow.
• Today it is considered to be the most economic and rapid method of
construction available for long bridges and viaducts with individual spans
up to 60m
• Decks are begun at one abutment and constructed continuously by
placing segments to the other end of the bridge.
• Segments can be positioned by either a temporary staying mast system
through more commonly using an assembly truss.
• Before segments are placed the truss with sliding pads is braced over
two piers.
• Depending on the bridge location the segments are then transported by
lorry or barge to the span under construction.
• Each segment is then placed on the sliding pads and slid into its
position.
• Once all segments are in position the pier segment is then placed.
• The final stage is then begun by running longitudinal prestressing
tendons through segments ducts and prestressing entire span.
• Deck joints are then cast and closed and ducts grouted.
• When the span is completed the assembly truss is lowered and moved
to the next span where construction cycle begins until the bridge is
completed.
5. Cable-Stayed Method of Bridge Construction
• Cables are used to carry the bridge deck from one or both sides of the
supporting tower.
• The cables carry and transfer all the loads to the foundations.
• Cable-stayed method of construction is used for constructing bridges
that span more than 300m.
• The technique of cable-stayed construction has been used and
continually developed over the last 50years.
• It is the most common construction choice today when a bridge is
required to span more than 300.
• Cable-stayed bridges can be either concrete or steel though a
combination of both materials is often chosen.
• For concrete cable stayed bridges free cantilever construction is
considered economical.
• With this method the deck segments can be either precast or cast-in-
situ by travelling shutter arrangement.
• In cable stayed bridge, depending on its design, the cables carry the
bridge deck from one or both sides of the supporting tower.
• The stay cables carry the deck and transfer all bridge loads to the
foundations.
• This is done by transmitting the cable stay forces, through its
extremities, at it anchorage points.
• Stay cables are firmly attached to the anchorages which are designed
to resist the buckling forces of the loads.
6. Arch Method for Bridge Construction
• Arch shaped bridge construction is one of the most economical
choices when the bridge under consideration is required to cross over
landscapes that are inaccessible.
• Many modern arch construction methods have made the arch
construction more economical.
• The arch construction can be built with concrete or pre-cast concrete.
• The cast-in-situ free cantilever method and slip formed sections are
two main construction techniques coming under arch methods.
• They are often the most economical choice where a bridge is required
to cross over inaccessible landscapes.
• The development of modern arch construction methods has made the
use of arch construction more economical by removing the need of
expensive centering formwork.
• Though abutments still must be well founded on rock or solid ground.
• Two construction techniques are most commonly used today
(i) Cast-in-situ free cantilever method - This method involves the
partially built arch tied back to rock anchors in the valley side
slopes.
(ii) Slip formed sections - This method involves half arch sections being
held vertically over each abutment and then rotating each arch
section into position.
• Tee-beams are generally used for arch bridge decks for their
functionality and self weight.