Professional Documents
Culture Documents
CONSTRUCTION
METHODS OF BRIDGE CONSTRUCTION:
Before a bridge can be built an appropriate method of construction must be
chosen. The decision is made by the design team. The principle factors
considered by the design team when chosing a suitable method of
construction are given below:
Where cast-in-situ construction is used for longer span bridges, the falsework
system required becomes more sophisticated. Semi or fully mechanical
falsework will require a specialized contractor. Semi-mechanical falsework will
generally consists of steel beams or trusses which are then spanned between
temporary towers. Fully mechanical falsework system is where a self
launching gantry with steel lined shutters is used.
The type of false work system used will also have a bearing on the rate of
span construction. For semi mechanical system each span will take between
2 to 6 weeks to construct. While for fully mechanical systems a span may be
placed within 1 to 2 weeks.
Where precast beams are considered for a motorway bridge construction, the
bridge cross-section for a typical carriageway will generally consist of four
beams. Erection time of such bridge should have a rate of construction of four
beams per day. A cast-in-situ slab top deck is normally used with an expected
rate of construction of one span a week.
(ii) Precast Decks: Precast deck construction is often used for the
construction of long viaducts. It is a time saving method which is beneficial for
long bridges where construction time for the final completion stage is tight.
A long viaduct can have a complete precast deck speedily placed with this
method. The decks are positioned using either a large crane or purpose made
gantry. A rate of construction of two spans per day is considered normal
where a gantry system is in use, if this pace is maintained a one kilometer
deck can be placed in three weeks.
The repetitive nature of this method allows for a variety of modern placement
techniques to be used, though balanced or free cantilever about a pier is a
preferred choice. With this method a crane or self launching gantry system
can place upto six segments per day.
Before segments are placed the truss with sliding pads is braced over two
piers. Depending on the bridge location the segments are then transported by
lorry or barge to the span under construction. Each segment is then placed on
the sliding pads and slid into its position. Once all segments are in position the
pier segment is then placed.
For bridge decks greater than 250m in length, the method of incremental
launching can be considered. With this method of construction the bridge deck
is built in sections by pushing the structure outwards from an abutments
towards the pier. It is most suited to the rapid construction of bridges with a
constant radius of curvature such as constant depth of box girder segments.
A steel nose is also positioned at the front of the first span formwork. This
allows for the necessary deck cantilever length as the span approaches the
first pier.
Bridge decks of 1km can be built by this method with a rate of construction of
30m per week.
Cable Stayed Method of Bridge Construction: The technique of cable-
stayed construction has been used and continually developed over the last
50years. It is the most common construction choice today when a bridge is
required to span more than 300. Cable-stayed bridges can be either concrete
or steel though a combination of both materials is often chosen.
In ca cable stayed bridge, depending on its design, the cables carry the bridge
deck from one or both sides of the supporting tower. The stay cables carry the
deck and transfer all bridge loads to the foundations. This is done by
transmitting the cable stay forces, through its extremeties, at it anchorage
points. Stay cables are firmly attached to the anchorages which are designed
to resist the buckling forces of the loads.
Detailing of all anchorages should allow for their safe construction and
accessibility for inspection and maintenance on completion. In concrete stay-
cabled anchorages are placed under the deck.
The development of modern arch construction methods has made the use of
arch construction more economical by removing the need of expensive
centring formwork. Though abutments still must be well founded on rock or
soild ground.
This method involves the partially built arch tied back to rock anchors in the
valley side slopes.
Tee-beams are generally used for arch bridge decks for their functionality and
self weight.