Professional Documents
Culture Documents
launching and
Re girdering
Launching: Introduction
Launching : Placement of Super structure on Sub-structure
Safety
◦ Safe handling of span as well as men and equipment used.
◦ Checking the erection stresses in each member of span during
launching and if required temporary strengthening is to be provided.
◦Steel girders need careful handling to avoid damage to
connections.
◦Concrete girders cannot be handled at any point. Depending on the
design, only load may be applied at nominated locations only.
◦ While providing temporary arrangements, proper care should be taken.
Desirable Features of
Launching Scheme
Features of Launching
Scheme
Speed
◦ Completion of the work as per laid
down time frame of project.
◦ Project should not get delayed on
account of bridge construction.
Features of Launching
Scheme
Economy
◦ Scheme selected shall preferably be with available
equipment and supporting false work .
◦ Quality of construction to be maintained as per laid
down specification.
◦ Bridge girders are very costly asset and difficult to repair
during service .
◦ For sake of economy, safety cannot be compromised .
Selection of Suitable
Method
Site Conditions
◦ Height of opening
◦ Wet, dry or partly dry ground/river bed
◦ Depth of water and velocity
◦ Vulnerability of river to flash floods
◦ Condition of approaches - high banks or cuttings
◦ Access to site
◦ Road, rail or water access
Selection of Suitable
Method
Other Conditions
◦ Experience of the contractor
◦ Experience of the supervisors
◦ Availability of bridging equipment and materials
◦ No of spans
◦ Estimated cost
◦ Erection of girders is sometimes as costly as the main bridge
Avoid complicated and extensive staging or auxiliary girders in erection
work.
◦ Simplicity avoids mistakes at site
Design of a Scheme
Girders should be designed/ checked for erection
and handling stresses.
◦ Scheme shall ensure that the girder does not get hit/
damaged during erection
Design of temporary work/false work used in
erection is very important
◦ Adequate extra factor of safety shall be there
◦ Shall cater to mistakes and minor accidents
◦ Shall cater to the “actual site conditions” i.e. loose bolts,
wear and tear etc
Preliminary Arrangements
Before Start of Work
Plan sequence of erection work
Move girder materials to site
◦ Make yard arrangements on one bank or nearby station
Arrange plant and equipment required for launching along with spans
◦ Testing all equipment
Visualize failures
◦ Have “Plan B” ready
Road crane
In situ
erection
In situ erection
Space under the girder is occupied by formwork
Superstructure work starts after sub structure work is completed
Lowering of girder to proper position to be done
In situ erection: All the
space can be used
In situ erection: All the
space can be used
In situ erection: Even in
slightly difficult site
With pre-cast concrete
units
Pieces are cast in yard and transported to site
On scaffolds, all pieces are placed
Stressing is done
◦ Site is occupied for minimum time
◦ Quality is maintained
◦ Speed of work is good
Derrick
Derrick for steel girders
Derrick
A column properly founded and guyed
Has freedom of movement in only one direction: vertical
Difficult to maneuver girder too much in lateral directions
Useful for
Relatively smaller spans
Lesser no of spans
Shockwave Flash
Object
Launching by derrick
Service span pulled
over opening using
Derrick
PSC girder launching using
derrick
PSC girder launching using
derrick
Side slewing
Side slewing
Mostly used for regirdering
For launching, Superstructure can be cast/ fabricated at approach,
pulled in position and slewed in
Slew – in slew – out
method
SHIFT THE
STAGING
TO NEXT
SPAN
GIRDER
Launching of Girders by road
Cranes
Movement
◦ Crawler mounted
◦ Tyre mounted
Boom
◦ Hydraulic
◦ Mechanical
Crawler Mounted Mechanical
Crane
Tyre Mounted Hydraulic
Crane
Launching of Girders by Cranes
Choose adequate capacity crane depending on the total load, radius at
which the load is to be handled
Choose well maintained cranes
Plan the site layout and movement of cranes
Have sufficient standby
Well designed lifting girder
Site Condition
#2
Site condition #2:
features
Difficult terrain
◦ Not accessible by road OR
◦ Height is great
REMOVE
AFTER THE
COMPLETE
WORK IS
DONE
DELAUNCH OLD GIRDER
LEAVES TO RIVER BED OR
APPROACH
ARRANGEMENTS READY FOR SIDE
MOVEMENT OF NEW GIRDER AND
GANTRIES
3-1/2 HRS BLOCK
GRANTED FOR DN
LINE
SR 30 Kmph FOR UP
LINE
GANTRIES TO BE PUT
ON TRACK
GANTRIES TOO FIND THEIR
GROUND (ON LORRIES)
NEW GIRDER AS WELL AS GANTRIES
READY TO MOVE OVER THE BRIDGE
CROSS FRAME OF TWO LEAVES OF
EXISTING GIRDER CUT AT PLACES
BEFORE BLOCK
DISMANTLING OF TRACK STARTED
BUT FULL DISMANTLING CAN BE DONE
ONLY AFTER BRINGING GANTRIES AND
NEW GIRDER
GANTRIES REACHING THE SPAN TO BE
TACKLED
ARRANGEMENT ON PIERS FOR FIXING
THE TWO GANTRIES
GANTRIES IN POSITION ON PIERS –
WAITING FOR GIRDER
GIRDER REACHING THE TARGET SPAN
GIRDER HANGED ON THE GANTRIES
TRACK CAN NOW BE DISMANTLED
TRACK
DISMANTLED
TWO LEAVES OF
OLD GIRDER TO
BE SEPARATED
NEW GIRDER TO
BE LOWERED
LEAVES OF OLD GIRDER SEPARATED
REMAINING BRACINGS BEING
KNOCKED DOWN
NEW GIRDER BEING LOWERED
NEW GIRDER IN
POSITION
HOOK ARRANGEMENTS FOR HOLDING
RELEASED GIRDER’S LEAVES
GANTRY RELEASED FROM IT’S
SUPPORTS ON PIERS
ONE GANTRY MOVED TOWARDS THE
OTHER
BOTH GANTRIES BEING PLACED ON
THE LORRIES
TRACK LINKED AND GANTRIES
PLACED OUTSIDE THE TRACK
LIFTING OF LEAVES OF RELEASED
GIRDER
RELEASED LEAF READY TO BE MOVED
GANTRY WITH GIRDER LEAVES BEING
PULLED TO THE BANK
LEAF BEING PLACED ON CESS FOR
DISPOSAL
Site Condition
#3
Site condition #3:
features
Water in river to depth 4-5 m
Water current is not much
Use of water force for launching
Site condition #3:
options
Barge mounted crane
Launching using tidal variations
Barge
mounted
cranes
Barge mounted crane
Barge Mounted Crane for
Mandvi Bridge (KRCL)
Barge mounted cranes
Used on Konkan Railway for launching of 122 m span
Control of the barge important
Efforts lot less than the transportation of the girders over dip lorries etc
Work similar to the launching of the well curb etc
Slewing in on
barge
Slewing in on barge
Slewing in on barge can be done where
◦ Water 4-5 m is there
◦ Current is not high
◦ Pier not very high above the water
◦ Only jacking involved
◦ Very convenient as weight and height of CG reduces
Slew in with tidal
variations : Vasai Creek
Bridge
INNOVATIVE !!
NO JACKING TO BE DONE
Transportation of girder
by barge
Transportation of girder over
barge: Temporary stressing done
TEMPORARY STRESSING
Lowering by tidal
variations
Site Condition
#4
Site condition #4:
features
River bed not so inaccessible OR
Water in river all round the year BUT
◦ Depth is less
Pre cast
◦ Launched using launching truss
◦ Launched by crane
◦ Launched using derrick
Cast in place:
Lowering by
jacking
Cast in place on
scaffolding
Jacking for lowering of
girders
Cast in place:
Lowering by
gantry
Casting inside
Launching truss
PSC Girder inside
Launching Truss
Launching truss for
precast girder
A different launching
truss: service span also
used
Launching
using road
crane
Crane from approaches
Launching by
derrick
Service span pulled
over opening using
Derrick
Lowering using derrick
Site Condition
#5
Site condition #5:
features
Difficult terrain
River bed not accessible OR
Water in river all round the year
◦ Heavy flow
◦ Depth of water is less (cannot support the barge)
◦ No support possible in the water
Difficult site
Site condition #5:
options
Launching over service span
End launching
Cantilever erection
Other erection methods e.g. Launching using ‘launching gantry or
launcher, ropeway etc
Erection on
service span
Skidding on rail cluster
Lesser span lengths are possible
Dip lorry used for rolling on launching girder/ rail cluster
◦ Friction is lower
◦ Lowering requirement is higher
GANTRY
PORTAL
Expanded Position
(before girder entry)
Contracted Position
(After girder entry)
TROLLEY FOR
GANTRY MOVEMENT
PORTAL OF GANTRY
STEEL LAUNCHING GIRDER OF 72M LONG
DIRECTION
P- 5 P– 4 P– 3
Final Bridge after
launching
Another case: Girder
over service span
Lowering using tendons
Side service span
End launching
End launching
Girders tied together on approach
No need to go to the river bed
Connection between girders shall be properly designed
Front portion acts as counter weight
Front portion droops due to load
Front portion shall have lesser load
Cantilever Launching: girders
under fabrication
End Launching: girders
connected for launching
End Launching: girders
connected for launching
End Launching: girders
connected for launching
End Launching: girders
connected for launching
End Launching: Rails as beam
on bottom
End Launching: rolling
arrangement
End Launching: Rolling
arrangement
End Launching: pulling
arrangement
End Launching: pulling
arrangement
End Launching:
Launching nose
End Launching: girder
pulled half way
Cantilever Launching: girder
nearing launching
Launching in progress
Launching in progress
Cantilever
erection
Cantilever casting
Cantilever erection: steel
open web girders
Most difficult method
Used for very long spans
Light crane used on top boom for
incremental erection
Difficult to provide camber
Cantilever erection
Cantilever erection
Cantilever erection
Cantilever erection
Cantilever erection
Other
spanning
arrangements
Other launching
methods
Launcher
Ropeway
Launcher
LAUNCHING OF
I/T/Box CONCRETE
GIRDERS
Less High Tech ‘Launcher’
Girder Launcher
Can be used for
◦ Complete precast girder
◦ Precast units, held together on scaffolds and then stressed together before
launching
Ropeway
Launcher/ Ropeway
Feasible only where large number of spans are there.
Initial cost is very high
◦ Working is very fast and safe afterwards