Professional Documents
Culture Documents
: 1 of 6
METHOD STATEMENT Revision : 0
Issued : Oct 2001
UE Construction Sdn Bhd UEC/MS/MPKCM/AR/015
IMPORTANT:
CONTENTS
1.0 SCOPE
2.0 MATERIALS
4.0 METHOD
9.0 DOCUMENTATION
Page No. : 3 of 6
METHOD STATEMENT Revision : 0
Issued : Oct 2001
UE Construction Sdn Bhd UEC/MS/MPKCM/AR/015
1.0 SCOPE
2.0 MATERIALS
b) Crusher run
e) Wooden pole
Page No. : 4 of 6
METHOD STATEMENT Revision : 0
Issued : Oct 2001
UE Construction Sdn Bhd UEC/MS/MPKCM/AR/015
f) Netting guard
a) Survey equipment
c) Excavator/backhoe
d) Compactor
e) Back pusher
3.2 All plants and machinery will be with valid documents or licences.
4.0 METHOD
4.1 Project Engineer (PE) to carry out joint inspection with Project
Management Consultant (PMC) or Supervising Engineer (SE) or both at
the proposed route for approval and to confirm the requirements and
identify any obstacles.
4.4 Obtain approval from Tenaga Nasional Berhad (TNB) for services
relocation and permission for crossing underneath 22kV TNB
transmission line.
4.5 Obtain approval from Telekom Malaysia Berhad (TMB) for services
relocation.
4.6 Inform Jabatan Kerja Raya (JKR) and Majlis Daerah Tapah (MDT)
regarding construction of the access road.
4.10 Relocate Telekom pole routes and TNB pole routes along the existing
tar road.
Page No. : 5 of 6
METHOD STATEMENT Revision : 0
Issued : Oct 2001
UE Construction Sdn Bhd UEC/MS/MPKCM/AR/015
4.11 Relocate Telekom pole routes and TNB pole routes along the existing
road inside R.O.W. which is under the scope of permanent relocation
by DRB utilities subcontractor.
4.12 Carry out site clearance as per Method Statement for Site Clearing
inclusive of felling and prunning existing palm trees, stripping
topsoil and dispose surplus material to approved dumping area.
(Ref : UEC/MS/GEN/M/002)
4.16 Provide temporary drainage alongside the proposed access road where
required.
4.18 Supply, spread, level and compact 300mm thick crusher run for the
running surface.
4.19 Provide flat netting guard at location where access road crossing
underneath 11 kV and 22 kV TNB transmission line if necessary.
4.20 However, changes may be made to the above method of construction and
alignment of the proposed access road to suit existing ground
condition and local requirements subject to PMC/SE approval.
Not applicable.
6.1 Work will be carried out in accordance with the Project Safety Plan.
6.4 Provide PPE to all workers including safety helmet, safety shoe,
vest, ear protector, etc.
6.6 Advanced traffic warning signs will be positioned in place along and
at entrance of access roads and designated flagmen will be used when
working in the vicinity of existing roads if required.
6.9 Inspect all machinery at site and ensure that it has competent
certificate and is safe to operate.
Not applicable.
Not applicable.
9.0 DOCUMENTATION