METHOD STATEMENT Page No.

: Page 1 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

METHOD STATEMENT FOR


LAUNCHING OF PRESTRESSED I-20
BEAMS AT
RB 014 : JALAN TAPAH – TELUK INTAN
(ABUTMENT A2 TO PIER P2)

Prepared by: Date: Reviewed by: Date: Approved by: Date:


Sheikh Faizal 16 Feb 04 Mohd Fauzi 16 Feb 04 Ramli Noordin 17 Feb 04

IMPORTANT:

The information contained herein is the proprietary property of UE Construction Sdn Bhd

The holder agrees to the following:


1. Not to reproduce; copy; reveal; publish; or, distribute it in whole or any portion of it
without authorisation; and,
2. To maintain this document in confidence.
METHOD STATEMENT Page No. : Page 2 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

CONTENTS

1.0 SCOPE

2.0 MATERIAL

3.0 EQUIPMENT & RESOURCES

4.0 METHOD

5.0 QUALITY CONTROL PROCEDURE

6.0 HEALTH, SAFETY AND ENVIRONMENT

7.0 TRACK POSSESSION

8.0 APPENDIXES
METHOD STATEMENT Page No. : Page 3 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

1.0 INTRODUCTION

This method statement describes the method and procedures for


launching the prestressed I beams at span 3 (Pier 2 to Abut 2) at RB
014 - (JALAN TAPAH – TELUK INTAN).

The launching layout and other relevant information on machinery


and equipment used in this work are included.

2.0 MATERIALS

2.1 Prestressed “I” Beams

The prestressed “I” Beams must achieve the required design


strength prior to the launching activities. Test cube results should
be submitted to the Supervising Engineer prior to the launching
activities to ensure the 28 days required strength had been
achieved.

The permanent position of the I-beams sitting on the crosshead


and abutment shall be marked before launching activities started.

3.0 MANPOWER & EQUIPMENT

3.1 MANPOWER

 1 Engineer
 1 Supervisor
 2 Operators
 4 Bar benders
 10 General Workers
 2 Welders
 1 Safety Officer

3.2 EQUIPMENT

 4 units of 45 tonne mobile crane


 Trailers
 1 units of launching truss consisting of 2 nos ‘A’ frame
truss
 Welding set
METHOD STATEMENT Page No. : Page 4 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

 Timber wedges
 Steel bar bracing

4.0 METHOD

4.1 Work Access And Area

 The working access and platform shall be leveled and


compacted to form a firm ground.

 Steel plate shall be provided if necessary wherever heavy


machine operating at the soft ground.

4.2 Launching Sequence And Methodology

 Audit survey shall be carried out to confirm the top level of


cross head and abutment prior to the launching works.

 The supporting structure including epoxy plinth shall have


reached the required strength and acceptable to the Resident
Engineer before beam launching.

 All relevant quality control records including beam hogging


and bowing report for the beams will be submitted before
launching.

 Rubber bearing pads will be placed at the position marked by


surveyor prior to launching activities.

 For this launching, 2 units of 45 tonne mobile crane will be


used to load the beam onto the trailers at the casting yard.

 Before transporting the beams from the casting yard, the 2


units ‘A’ frame truss shall be launched across the span and
laid on the cross head of Pier P2 and pilecap of Abutment A2
respectively.

 For launching of this span, 1 unit of 45 tonne mobile crane


will be designated on top of middle span (Pier P1- P2) deck
slab while another unit of 45 tonne mobile crane will be
designated behind Abutment A2.
METHOD STATEMENT Page No. : Page 5 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

 The I-beams shall be transported to the built-up


embankment behind Abutment A2.

 One end of the beam shall be lifted up and placed onto the
launching truss and subsequently pushed across towards Pier
P2.

 The beam shall then be lifted off the launching truss and
placed onto its respective bearings.

 Two general workers will be designated, one each on the Pier


crossbeam and Abutment pilecap to ensure the 'I' beams will
be sitting in place (centre of the bearing pad).

 Launching procedure and schematic sketch is enclosed in


Appendix 1.

5.0 QUALITY CONTROL PROCEDURE

Not applicable

6.0 HEALTH, SAFETY AND ENVIRONMENT

6.1 Working Hour


Launching activity will be done during line block. Line block is
required for 10 days.

6.2 Regulations
All site activities shall comply strictly with KTM regulations and
requirements. Before commencement of works all relevant staff
will be briefed and trained to comply with KTMB regulations. All
staff will also be familiar with the Construction Crisis Team’s
Handbook.

6.3 Launching Safety Briefing


A safety briefing will be conducted by the launcher prior to
beam launching to ensure that all people involved are familiar
with the works (Designated Launcher will be fully in charge
during the launching activity). The safety officer with knowledge
METHOD STATEMENT Page No. : Page 6 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

of the launching works will supervise the safety aspect of the


whole launching activity. Before starting the works, this safety
officer will brief the workers on the general hazards of beam
launching activities.

6.4 Equipment Checks


The safety officer will check and ensure that all cranes are with
valid PMA and fully operational and that there are no
irregularities prior to the launching. The launching will be halted
if any irregularities are observed. Pre-Lift Checklist Crane
Operation is attached in Appendix 3.

6.5 Safety Pre-caution After Launching


All beams shall be braced immediately after launching works is
completed to avoid any accident while waiting for the
subsequent activities. Beams will be braced using extreme load
case as per calculation and sketch attached in Appendix 4.
Adequate timber wedges, temporary welding or other supports
shall also be provided to ensure the I beams remain stable on
bridge bearing pads.

Upon completion of beam launching, works on diaphragm


beams shall be completed within 7 days, with first beam
completed by 5th day.

6.6 General Safety


All workers are to wear High Visibility Vest (Orange colour),
safety helmet and safety shoes within KTMB Right Of Way
(ROW). All safety issues will be governed by the DRB-HICOM’s
Safety And Health Plan. DRB-HICOM procedure for heavy lifting
attached in Appendix 4 will be adhered to. The crane operator
must possess a valid certificate of competency on crane
operation.

The area shall be barricaded from construction equipment,


machinery and general public.

6.7 Environment Issues


The Environmental Management Plan will be adhered to strictly
on site.
METHOD STATEMENT Page No. : Page 7 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

7.0 TRACK POSSESSION

Line block is required for 10 days.

8.0 APPENDIXES

a) Appendix 1 - Sketch and photographs showing the launching ‘A’


frame truss and positioning of cranes and trailer for
launching beams.

b) Appendix 2 - Design calculations for steel launching truss.

c) Appendix 3 - Pre-lift Checklist Crane Operation &


Pre-commencement Checklist

d) Appendix 4 - Temporary Bracing Calculation and


Welding Details For Beams Launched

e) Appendix 5 - DRB-HICOM Heavy Lifting Operation

f) Appendix 6 - Welder Certificate & Sling Certificate

g) Appendix 7 - Location Plan.

h) Appendix 8 - Site Organisation Chart.


METHOD STATEMENT Page No. : Page 8 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

APPENDIX 1
METHOD STATEMENT Page No. : Page 9 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

APPENDIX 2
METHOD STATEMENT Page No. : Page 10 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

APPENDIX 3
METHOD STATEMENT Page No. : Page 11 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

APPENDIX 4
METHOD STATEMENT Page No. : Page 12 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

APPENDIX 5
METHOD STATEMENT Page No. : Page 13 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

APPENDIX 6
METHOD STATEMENT Page No. : Page 14 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

APPENDIX 7
METHOD STATEMENT Page No. : Page 15 of 15
Revision : 1
Issued : Feb 2004
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

APPENDIX 8