SSG-CW269131-OPUC1-AA5760-00001
Classification Status:
Restricted
Revision Philosophy
Revisions for review will be issued at R01, with subsequent R02, R03, etc as required.
All revisions approved for issue or design will be issued at A01, with subsequent A02, A03, etc as
required.
Documents approved for Construction will be issued at C01, C02, C03, etc as required
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc as required
Narrative sections revised from previous approved issues are to be noted in the table PSL low and/or
highlighted in the RH margin (using the appropriate revision status) thus: A02
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected
areas and by the use of a triangle containing the revision status.
If a document is cancelled the document will be issued at the next sequential number and suffixed with
a X. For example, if 02R is the current revision then 03X will be the Cancelled revision
All revisions to this document must be approved by the relevant Technical authority
Revision History
1.0 INTRODUCTION 3
1.1 Objective 3
2.2 DEWATERING 3
2.3 EXCAVATION 4
2.4 SHORING 4
1.1 Objective
The Excavation Plan outlines how the excavation of the cable trench and pole
foundation will be carried out. It outlines all the requirement that must be met before
excavation can commence.
The excavation plan is in adherence to SPDC approved excavation procedure as shown
below.
A.
Scanning and probing of the cable route area to identify all known and unknown
underground structures shall be completed by PIMO SERVICES LTD with support
from SPDC Ogbotobo Operations/Asset Team before commencement of any other
work on site. The outcome of this will be a scanning and probing report showing
area of any underground facility.
2.2 DEWATERING
All dewatering activities shall comply with PIMO SERVICES LTD dewatering method
statement.
Surface dewatering pumps shall be used to lower the accumulated water within
the trench during excavation.
All pumps shall be placed at least 1.5m away from the edge of the excavation.
Water ingress/egress shall be controlled by continuous dewatering.
Dewatering shall continue till the project supervisor ascertains that the base is
safe to receive cable and that there are no evidences of impending collapse in
the excavation.
2.3 EXCAVATION
The entire excavation operation shall be directed and supervised by the project
Civil Construction lead as the authorized Person (AP).He is conversant with
SPDC excavation procedure, knowledgeable in soil analysis and is trained in
excavation hazard management and protective systems. He shall work in
conjunction with the project QA/QC Engineer and SPDC Civil Supervisor.
They shall be responsible for obtaining an approved PTW from SPDC before
excavation can commence.
Peg out the dimensions of the cable trench excavation portion.
Carry out possible re-routing of water /telecoms/sewage/electrical under ground
facilities, where route can not be diverted.
Ensure all competent excavation personnels are adequately kitted with insulated
tools and rubber PPE’s
2.4 SHORING
Shoring of the excavation trench shall be done in phases. At a depth of
500mm(0.5m), the first level of shoring will be done with the materials being
provided i.e (1x12” facials boards and 2x3”hardwood planks). As the excavation
continues, the shoring material will be lowered and additional materials will be added
at the top. This operation will continue till the proposed depth is attained, then all the
materials will be fastened together at the 4 corners of the trench with nails.
- Fire extinguishers
- Gas tester.
- Underground cable/metal detector.
.