PREPARED

SOMJIT 30 May 17
BY PTT Public Company Limited
CHECKED Fourth Transmission Pipeline
PRASOBSUK 1 June 17
BY Midline Compressor Station

APPROVED Project
THUSSAKORN 1 June 17
BY
REV REVIEWED APPROVED
DATE DESCRIPTION
NO. BY BY
A1 17 Mar 16 Sun Xiuquan Zhang Shuiqing Issued for Approval (IFA)
F1 1 June 17 Sun Xiuquan Zhang Shuiqing Approve for Construction (AFC)

METHOD STATEMENT FOR CONCRETE FOUNDATION WORK

IBC-MS.C0-40-1304.04-4800-001 Rev. F1

TOTAL 20 PAGES

PTT CONTRACT NO. : PROJECT NO. : AREA CODE:


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

PTT.SP./2/7258 1304.04 4800

TABLE OF CONTENTS

1.0 PURPOSE...................................................................................................................4

2.0 SCOPE.........................................................................................................................4

3.0 REFERENCE...............................................................................................................4

4.0 MAN POWER AND MATERIAL..................................................................................5

5.0 CONSTRUCTION FLOW CHART..............................................................................6

6.0 WORK METHOD.........................................................................................................7


6.1 Survey........................................................................................................................7
6.2 Foundation trench excavation................................................................................7
6.3 Blinding concrete pouring.......................................................................................8
6.4 PC Pile Cutting.........................................................................................................9
6.5 Rebar Work...............................................................................................................9
6.6 Anchor Bolt Brace Installation..............................................................................11
6.7 Form work...............................................................................................................12
6.8 Anchor bolt fixing and leveling.............................................................................13
6.9 Concrete Work........................................................................................................14
6.10 Covering film, curing............................................................................................15
6.11 Form Removing....................................................................................................15
6.12 Inspection and acceptance.................................................................................16
6.13 Foundation Trench Backfilling and Smoothing...............................................16

7.0 Quality Control Measure.........................................................................................17

8.0 HSE method..............................................................................................................18

9.0 ATTACHMENT..........................................................................................................19

10.0 SAFETY HELATH AND ENVIRONMENT..............................................................20

Page of IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

Page of IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

1.0 PURPOSE

The purpose of this method statement is to describe General Foundation activity(Not

include GTC Foundation)for the Fourth Transmission pipeline midline Compressor

Station Project. Most of them are small foundation near equipment foundation, the

number is about 800.

2.0 SCOPE

This document describes method statement for foundation required for further

construction of buildings, structures, equipment foundations and foundations for the

piping in all area of the project including method of work, materials, Manpower,

equipment, inspection and testing.

3.0 REFERENCE:
ACI-224 Control of Cracking In Concrete structures

ACI-301 Specification for Structural Concrete for Buildings

ACI-304 Guide for Concrete Measuring, Mixing Transporting and Placing Concrete

ACI-305 Hot Weather Concerting

ACI-308 Standard Practice for Curing of Concrete

ACI-318 Building Code Requirements for Reinforced Concrete

TIS 20:2543 Steel Bar for Reinforced Concrete Round Bar

TIS 20:2548 Steel Bar for Reinforced Concrete Deformed Bar

GES.01.40.001 REV.D1 Specification for Civil Work

GES.01.40.001 REV.D1 Design of concrete foundations structures paving

Page 4 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

4.0 MANPOWER AND EQUIPMENT


4.1 Equipment & Tool

Backhoe 1 ea.

o Mobile Crane 25 T.1 crane

o Hiab Truck 5 T. 1 truck

o Plate compactor 2 Machine

o Grinding Machine 4 Machine

o Electric concrete breaker 5 Machine

o Hammer 5 ea.

4.2Manpower

o Safety officer 2 persons

o Surveyor 3 persons

o Forman 2 persons

o Pile cutter 13 persons

o Helper 4 persons

4.3 Organization chart

Page 5 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

Project Manager

QA/QC Manager Safety Manager

Construction
Manager

QA/QC Inspector Safety Officer

Site Engineer

5. CONSTRUCTIONFLOW CHART
Civil Supervisor Surveyor

Page 6 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

5.1 Construction Procedure

Survey

Excavation

Compaction

Pile Cutting

Rebar

Cooling Pipe, Temperature Measurement System Installation Anchor Bolt Brace Installation

Formwork Installation

Chipping Anchor Bolt fixing, leveling

Pouring

Covering film, Temperature Monitoring, Curing

Reject Form Removing

Acceptance Inspection

Foundation Trench Backfilling and Smoothing

Figure 2.construction procedure work flow

Page 7 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

6 WORK METHOD

6.1 Survey

According to general coordination, it shall reference is topographic survey .In order to determine

actual location, area and depth of excavation onsite, it shall ensure elevation of construction site

and range of each area.

6.2 Foundation trench excavation

Before excavation, it must know underground objects which area will be excavated in detail, then

it can start to excavate.

Earthwork Excavation: It shall apply the combination of mechanical excavation and artificial

excavation method for earthwork excavation. For large area excavation, in order to improve

construction efficiency, it shall use large machinery excavator till excavate to predetermined

position, then it shall employ artificial excavation to make the depth and width of the trench

conform to requirements of design and construction. During excavation process, there shall be

enough distance between equipment and pile to prevent extruding pile.

After determining the excavation depth and the area, there is a reasonable calculation of

earthwork balance. In the early period, it will transport the soil while it is excavating. After

confirmed the volume of earthwork backfilling, it shall set pile soil area at the periphery of the

compressor shelter to reduce backfilling transport distance and backfill easily.

Page 8 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

Boundary
line

Excavation
Depth

Figure x: Excavate with the increase offset range of 1 meter from the Footing boundary. Excavation depth

until reach the sand layers to prepare for foundation works.

6.3 Lean concrete pouring

Where lean concrete is used as a base, 50mm thick, and laid over sand after excavation.

Under yard paving, 50 mm thick lean concrete..

Figure X: lean concrete with depth of 50mm., over sand layer.

Page 9 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

6.4 PC Pile Cutting

In order to ensure quality of pile head, there shall cut the section which is higher than elevation of

top pile after concrete cushion construction completed. Sundries shall be cleaned after pile cut

completed. .

It shall chip concrete cover of outside rebar away to exposure steel strand and embed rebar.

Then inside concrete will be punched several holes alone all around of pile. Upper pile head will

be separated with left pile body by tensile force (because of strong compression strength but

weak tensile of concrete). After separated part will be cleaned by excavator or crane, steel strand

will be cut and exposure section of rebar shall be bended according to length requirement of

drawing.

6.5 Rebar Work

Foundation construction demand large amount of rebar. Rebar storage duration shall be

described followed Standard. Rebar shall process in prefabricate yard. It shall use machinery

equipment to cut and bend rebar. Concrete cover of rebar will use mortar precast block or finish

product protect block.

6.5.1 Preparation

a) It shall execute charger sheet audit policy strictly. There shall be sign by rebar foreman on

charger sheet, and then it shall be issued.

b) Material quality is one of the basic conditions to ensure rebar work quality. All rebar must be

with certificate which lists all information. Rebar cannot enter to site without certificate. According

to relevant requirement, entered rebar shall be sampling inspected by batch, and accepted rebar

shall be used.

c) Constructor level shall carry out explanation system. Rebar foreman shall organize technical

explanation before setting out and colligation. It shall let worker know and construct as

specification and solve key construction problem.

6.5.2 Rebar quality requirement and stacking

Rebar on-site shall have quality certificate: There shall be mark on surface of each bundle of

rebar. It shall check mark and surface onsite, greasy dirt shall be clean up before using .Based

on relevant specification, it shall take sample to test mechanical property under witness of owner.

Page 10 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

After retest accepted, it shall be processed. Rebar onsite shall be marked identification and

placed in different area based on specification.

6.5.3 Rebar Processing

a) During cutting progress, it must be cut if there is any rebar with split or seriously elbow. If

hardness and type of rebar are quite different, it shall report to PTT immediately, it shall continue

to process after ascertain cause.

b) Semi-finished rebar shall be applied inspection and acceptance system in whole processing. It

will process in bunch after accepted the first finished rebar. It is key point to check those kind of

rebar which are large amount, difficult to be processed and has a great effect on colligation.

d) Finished and semi-finished rebar shall be managed by special assigned person after

accepted .It shall be marked identification and placed in different area. It will give out according to

demand.

6.5.4 Rebar colligation and installation

a) It need consider sufficiently about construction condition while setting out. To avoid hammering

and prying violently onsite, it need rationally arrange space between rebar and rebar, rebar and

embedded ironware, rebar and installed embedded part.

b) Rebar process shall base on cutting list. Cutting list notes usage part, specification, species,

hook form, bending radius and other requirements. It can be colligated after chalked rebar

location line. Before pouring concrete, it shall ensure that surface of rebar is clean, without sludge

and so forth.

c) Anchorage and lap length of rebar shall conform to requirements.

d) Requirements of bending

All hook and bending work will refer ACI 318.

Page 11 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

Rebar

Figure X: Rebar of the foundation according to requirement.

6.6 Anchor Bolt Brace Installation

Embedded bolt brace installation use auxiliary fixing and setting. See figure below.

Embed bolt fixed steel frame

Steel frame shall be made by 10 U steel. Bolt will be fixed to steel frame by nut.

It will set DN50 steel pipe as outrigger under brace. Bottom of outrigger shall be welded on

embedded steel plate of blinding concrete which will be partly thickened. There is supporting

Page 12 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

steel pipe which one side welded on outrigger and another side fixed on adjacent embedded part

as diagonal brace to fix outrigger. Height of outrigger shall more 20cm than top of foundation.

When steel brace be prefabricated, it will set out and determine location of screw. Holes shall be

punched after ensure accuracy of screw location. Holes which size is greater 10mm than

diameter of bolt. Nut which is to adjust location of screw will be welded in direction of 0, 3, 6, 9

o’clock of each hole. Before install outrigger, there should horizontally weld brace which is 5cm

on column to place steel frame. These needs to be concerned before install steel frame: axis of

frame and bolt are overlapped; level and elevation comfort to requirement. Bolt shall be installed

and fixed with frame after steel frame installation completed, Position of anchor bolt can be

corrected by trim bolt in pouring process. Pipe of outrigger shall be grouted by concrete which is

higher grade after curing.

6.7 Form work

6.7.1 Foundation form will use wood glue board, steel pipe which used to support and fix,

fastener etc.

6.7.2. 1Installation of form brace shall follow specification as below:

a) Embedded part like split bolt must be installed firmly. The supporting surface of stanchion and

diagonal bracing shall be smooth and steady.

b) To prevent leakage of cement paste, joints of form shall be staggered and taped.

c) Surface of form should be smooth and cleaned up, the façade of form shall be vertical, and

splice of form should be tightly. It isn’t allowed using deformed form. Separate shall be brushed

uniformly; it should not brush less or omit to brush.

d) It will set out foundation axis and boundary and splice form after checked without problem.

6.7.3 Form Installation

It will use wood glue board as form of compressor foundation. There is split bolt inside. It will use

batten and steel pipe for fixing outside. In order to make split bolt, there will weld ends of

Φ14round steel with Ф14 screw which length is 100mm. Batten and steel pipe will be fixed by

double nut and butterfly clasp. To reinforcing external part, out board of form will stand batten

vertically and interval should not greater than 200mm. There should set double steel pipe fixed by

butterfly clasp of tie bar on outboard of batten. Foundation sectional dimension is controlled by tie

bar. Outside of transverse steel pipe will set uprightly steel pipe every 1m. Upright steel pipe shall

Page 13 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

be fixed by snap joint with transverse steel pipe to immobilize external diagonal brace, thus form

position will be controlled.

6.7.5 Installation finished formwork

Figure 5 Foundation Form Installation Instructions

6.8 Anchor bolt fixing and leveling

6.8.1 Anchor bolt fixing

Survey construction reference control line: survey and extent central line, set control point in

periphery of foundation

Setting out by total station and 50m steel tape and marking specific location of each embed bolt.

According to marked location of embed bolt, it will tap on steel frame and screw nut initial

calibration by steel tape.

It should accuracy calibrate each embed screw by steel tape and trimming bolt. The exposed

part of embed screw shall be protected by taped before poured and applied by grease and

wrapped up tightly by waterproof material after poured.

Construction precision control of embed part and screw: It shall use total station to axis location

and string iron wire, so that position of embeds part and screw will be located. According to

designed central axis , it will pour concrete after ensure correctness of embed part and screw .It

should use total station and leveling to monitor while concrete pouring ,if there is any excursion or

sinking , it shall take measures at once to correct to ensure construction precision of embed part

and screw:

Page 14 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

Controlling of screw horizontal displacement is to weld trimming bolt on U-bar which is according

to periphery location of embed screw .To ensure accuracy location of embed screw, it shall be

based on displacement to trimmer bolt .

6.8.2 Anchor bolt level

It should ensure process of fixed steel frame by checking strictly. It should check and inspect

relative interval, diagonal, elevation of top surface and verticality of anchor bolt while setting out,

trepanning, embedding and installing upright steel plate, installing anchor bolt and pouring

concrete. If there is any deviation, it shall be rectified immediately. After concrete poured, it take

measures to protect anchor bolt, for example, to prevent corrosion of head of bolt, it shall be

applied by grease and taped.

6.9 Concrete Work

It will use commercial concrete. Supplier of concrete shall be approved by PTT. Quality of

concrete shall be controlled strictly.


6.9.1 Raw material inspection :Raw material should have certificate or recheck report such as
sand, crushed stone, cement, additive etc. proportion report of concrete shall be issued by
qualified lab and approved by PTT. Concrete supplier can conduct concrete based on proportion
after approved.
6.9.2 Preparation: It should check form and its bracing, rebar and embed part and make recheck

record; Inside of form shall be cleaned up. In case of leaking heavily, joint of form and hole

should be stuck up. Timber formwork shall be watered but water logging.

6.9.3 The general principle of concrete casting is continuous. Vibration should be inserted quickly

and pulled slowly. Concrete casting of each part is as follow:

a) While casting, concrete cannot pour into form directly, fall distance from pump pipe to casting

surface shall not greater than 1.5m; otherwise it should take appropriate measures. It should use

delivery pump hose pouring layer by layer prevent concrete segregating. Pouring thickness shall

not over than 0.45m. Each layer should be poured longitudinally from short side. It should stop for

a while since a layer completed. Upper layer shall be poured before initial set of next layer to

release hydration heat as much as possible and avoid cold joint.

When vibrating concrete, vibrate poker shall be staggered orderly, inserted quickly and pulled

slowly. It shall not be missing-vibration or over-vibration. Vibration time should be 20~30seconds.

Page 15 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

In order to ensure integrity of concrete, vibrator shall be stretched into 50mm of lower layer .To

make certain about compactness of concrete, it shall re-vibrating where is embedded part and

fixed amount of bolt

Due to large volume of concrete, there is bleeding during pouring. It shall be constructed strictly

following pouring procedure so as to collecting and draining bleed.

Form Newly pouring concrete

c) Concrete Curing: Compressor foundation shall be cured by covering plastic film and straw

mat, it need to water as well. Curing period is not less than 7 days.

d) Specimen reserving: To check concrete quality, it shall make compression test, concrete

specimen should be cylinder which made by concrete supplier onsite and cured in precast yard of

supplier. There should set at least one standard specimen and another specimen in the same

condition. There should be 3 sets of test blocks per 50m3 for continuous casting of concrete.

6.10 Covering film, curing

6.10.1 Covering film

6.10.2 Curing method

It will apply sluicing water method once concrete casting completed. After 12 hours of concrete

casting completed, it will pile cofferdam reservoir which height is 20cm on surface of foundation.

Due to high specific heat of water, it can delay emanating of heat and running off surface

temperature of concrete. To prevent crack of surface of concrete, temperature difference among

central, surface of concrete and air shall be controlled.

6.11 Form Removing

6.11.1Side form will be removed after cooled down, it is about 7 days.

6.11.2Sequence of removing form shall from top to bottom and remove brace and fixed fitting

then form.

6.11.3 It is forbidden to hammer and pry violently.

Page 16 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

6.11.4 It should be careful while removing form, fastening and pipe will be delivered out till a

segment of form removed completely.

6.11.5Removed form and pipe shall be placed on designed area and cleaned, maintained,

brushed spirant in time.

6.12 Inspection and acceptance

6.12.1 Raw material of concrete mixture need to be inspected, it can be used after accepted. In

order to ensure modeling temperature of concrete, it should concern temperature of each raw

material as well.

6.12.2 Inside of form shall be cleaned up before casting.

6.12.3It should enhance concrete test tube manufacture and maintenance; test tube shall be

identified and cured after remove from form.

6.12.4It should try to construct in lower temperature time within a day.

6.12.5 Enhance maintenance. Before finish setting, it should face-closure second time and shall

be covered plastic film to prevent crack and evaporation of water on concrete surface .it should

pile up 200mm cofferdam to store water for curing alone top of foundation after finish

setting .thus, concrete has high ability to resist deform by air temperature changing and will not

crack caused by shrinking.

6.12.6 In order to release hydration heat and control difference of temperature between concrete

foundation and outside under 25℃, it should use cooling water circular pipe which isΦ50 steel

pipe in compressor foundation. There is water to cool hydration heat of concrete down circularly

in cooling pipe. It will be impounded and cured which is 15 days on form of top of foundation

6.13 Foundation Trench Backfilling and Smoothing

Backfill: It will start after inspected and accepted by owner. It should clean up all form, under

boarding, temporary brace, garbage and construction spoil in foundation trench. Backfill material

shall conform to requirement of design which cannot contain harmful organic materials and waste

residue. When paving filling material, it shall be continuous. Backfill shall be compacted layer by

layer. Before backfill, it shall ensure that spoil of each layer is in optimum moisture content

condition and coefficient of compaction is conforming to requirement of design.

In order to drain temporary water logging in foundation trench, periphery of foundation trench

shall be drainage facilities such as temporary drainage ditch, dam, cofferdam, etc. For storm

Page 17 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

water in bottom of foundation trench, it shall be drained by digging puddle or pump. Before

constructing the superstructure, the foundation trench cleaning shall conform to the requirements

of design.

7QUALITY CONTROL MEASURE

7.1 It should apply technical responsibility system in construction site. Leading by engineer,

organize technical leader team by constructor, surveyor, documenter and each foreman

7.2 Drawing, PTT technical, operation and acceptance specification shall be learned.

7.3 It should audit drawing and make notes, if there is any unclear detail, it shall be

communicated with CPP immediately.

7.4 Prepare rebar setting out, bill of material and each material plan in time.

7.5 Organize technical explanation in time and process handover in advance.

7.6 All survey and measure equipment used in this project must conform to relative

requirement.

7.7 Concrete supplier must be approved by CPP and PTT. Concrete supplier should provide

mix proportion report and material inspection report which include sand, crushed stone,

cement and additive.

7.8 Each construction process is critical. Each foreman is taking primary responsibility for his

task, it will keep strictly rules for reward and punishment .Technicist should make technical

explanation for each process.

7.9 It shall follow construction procedure strictly to solve common problem in constructing.

7.10 Each foreman should get hold of quality issue in time during constructing period. If any

problem found should be solved in time.

7.11 Onsite specific quality inspector should know drawing, operation specification and

acceptance specification well ; check finished process of each construction team and

correct quality problem in time then report it .Rework or rectified activity shall be

executed double check policy. It will start next process after rework conformed to

requirement of design and acceptance specification.

7.12 In order to ensure that construction quality is controlled efficiently; process handover

and inspection policy shall be executed strictly. Operator should self-inspect for his

Page 18 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

process, and next processing operator will inspect for previous process. It shall be

process handover after accepted by self and mutual inspection. For key process and

concealed work, it shall apply for inspecting by CPP and PTT after accepted by specific

quality inspector of constructor. It can start to next process after accepted.

7.13 It shall enhance to inspect purchase order and identification of product, control process

and complete all records.

8 HSE METHOD

8.1 Foundation trench excavation HSE method

a) Foundation trench construction safety method:

When depth of foundation trench is less than 2m,it will be sloping but bracing or supporting.

However, if it is too close to adjacent building, pipeline and road, or geological condition is bad,

there still need brace and support.

b) Soil shall be placed on outer stability line of side slope. To avoid collapsing, soil

stacking cannot too high.

c) Soil cannot obstruct safe exit and embed facilities such as fire hydrant, warning board

and so forth.

d) To keep site be neat, Soil except backfilling and leveling soil shall be transport in time

e) All mount of foundation trench excavation must be placed 2m away from foundation

trench excavation line. There must be warning sign around foundation trench and

set safe ladder in foundation trench. It shall sign safe escape route at the same

time.

8.2 Form work HSE method.

a) It shall organize construction team for technical explanation and inform relevant

professional constructor to cooperate before install form.

b) There shall be fixed measures to pretend toppling during form and brace installing.

c) It shall ensure concrete will not be broken while removing form.

8.3 Rebar Work HSE Method

a) Each kind of rebar equipment shall be tested and labeled before using.

Page 19 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

b) In order to ensure safety and efficiency, it shall be in same movement when there are

many workers deliver rebar together, rebar stacking shall be separate and safe to

prevent collapsing or falling.

c) When machinery processing rebar, it should be careful to worker himself safe.

d) When welding rebar, it should be cared to wear safety equipment to prevent hurt

from electric arc.

8.4 Concrete Work HSE Method

When using vibrating poker, worker shall wear rubber overshoes and gloves at the same time,

worker also should wear safety goggle to prevent cement paste splashing into eyes, it shall not

touch switch while hand is wet, and power wire cannot be broken and electric leakage. It must

clean up all concrete which scattered on construction site or delivering road while constructing.

Pipe line shall not be pulled violently to prevent hurt by pipe line.

8.5 Temporary electricity in construction

Temporary electricity usage, It will assign person to take responsibility for building up and take

charge in electric supplying system. Construction equipment must in good condition; it shall be

make sure that each switch with a current leakage protector just can plug equipment.

9 ATTACHMENT

9.1 Material Preparation

Table 5

No Name Specific Unit Qua Remark


1. Centrifuge Rinsing Pump 2ation
Inch Set 16 Cooling water pump
Measuring temperature
2 Infrared Digital Thermometer 0-100℃ Set 1 of compressor
foundation

Measuring temperature
3 Thermocouple Thermometer 0-100℃ Set 2 of compressor
foundation
4 Steel Pipe Φ50 M 1,000 Cooling water coil
5 Elbow Φ50 Unit 90 Cooling water coil
6 [10box iron [10 M 200 Bolt fixed mount
Fixed mount of
7 Steel Plate 10mm m2 15
embedded part

Page 20 of 21 IBC-MS.C0-40-1304.04-4800-001 Rev. F1


PTT Public Company Limited
Method Statement for Foundation Fourth Transmission Pipeline Midline Compressor Station Project

9 Wood glue board 15mm m2 550 Form

13 Oxygen bottle 20 Technical measure


Acetylene bottle 10 Technical measure
14 Bolt protect cover Set 100 Protecting bolt
15 Grease Kg 10 Protecting bolt
16 Plastic film m2 500 Maintenance
Curing side of
17 Straw Bag Unit 1500
compressor foundation
Including protecting
temperature tube,
18 Scaffolding pipe Φ50 M 4800 compressor foundation
steel split head,
foundation trench etc.、
Form fixing,including
19 Split Bolt φ14 T 4.5 2,000 bolt hats and
butterfly clasps

20 Level Ruler 1m Unit 8 Leveling top

10 SAFETY SECURITY HEALTH AND ENVIRONMENT

Safety supervisor shall ensure that all personnel working at site, are wearing PPE.

Safety Security health and Environment for the pile cutting shall be followed by SSHE

Plan (Document number) and Contract Specification.

JSEA refer IBC-PR.S1-90-1304.04-4800-001 JSEA Procedure on Pilling Activities