Professional Documents
Culture Documents
METHOD STATEMENT
FOR REPAIR & REHABILITATION OF AD-DHANA SOCCER FIELD
Document No.:01-062-00
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
TABLE OF CONTENTS
1.0 PURPOSE 03
2.0 SCOPE OF WORK 03
3.0 REFERENCES 03
4.0 PLANTS, EQUIPMENT AND MATERIALS 03
4.1 PLANT AND EQUIPMENTS 03
4.2 MATERIALS 04
5.0 SITE PLANNING & PREPARATION 04
6.0 WORK PROCEDURES
6.1 WORK METHODOLOGY. 04
6.2 SITE CLEANUP AND RESTORATION. 06
6.3 SITE WELFARE 06
6.4 ORGANISATION, RESPONSIBILITIES & SUPERVISION. 06
6.5 WORK FORCE. 06
7.0 HEALTH & SAFETY 07
7.1 RISK ASSESSMENTS 07
7.2 ES&H CONTRACTOR REQUIREMENTS 07
7.3 PROTECTIVE & SAFETY EQUIPMENT. 07
7.4 CONTRACTUAL REQUIREMENTS. 07
7.5 INFORMATION TO PERSONNEL. 07
7.6 EMERGENCY PROCEDURES. 07
7.7 PERMIT REQUIREMENTS. 08
8.0 ENVIRONMENTAL ISSUES 08
8.1 ENVIRONMENTAL IMPACT ASSESSMENT. 08
9.0 QUALITY ASSURANCE 08
9.1 CONTRACTUAL REQUIREMENTS. 08
9.2 CRITICAL WORKS. 08
9.3 INSPECTION & TESTING. 08
9.4 REQUEST FOR INSPECTION. 08
9.5 FOLLOW UP & EVALUATION. 08
10.0 CONFIRMATION OF INSTRUCTIONS TO OPERATIVES 09
11.0 APPENDICES 09
1.0 PURPOSE
The intent of this document is to provide a complete Method Statement for the use of materials, equipment,
tools and plants; it includes the manpower and construction methodology in compliance with RC requirements,
drawings and technical specification with safety measures and quality control.
3.0 REFERENCES
The following documents has mainly been used in the preparation of this Method Statement
Air Blower
Permits to be attained
1 Encroachment Permit
2 Work Permit
3 Excavation Permit
4 Hot Works (if any)
4.2 Materials
Following materials will be used at site
1. Ready mix concrete
2. Epoxy Coated Reinforcement Bars
3. Waterproofing Membrane
4. Protection Board
5. Geo grid (Extended polymer reinforcement)
6. Non-Shrink Grout
7. Coating with coal tar epoxy at and below grade level
8. Coating concrete surfaces with exposed aggregates with Silane/Siloxane above grade
level
9. Zinc rich primer
10. Joint sealants
The material safety data sheet for all items # 6-10 are attached separately as an Appendix of this
method Statement.
6.1.3.2 Coating concrete surfaces with exposed aggregates with Silane/Siloxane above grade level
Clean the concrete surface by sweet grit blasting.
Apply two coats of the coating as per manufacture’s recommended procedure.
6.1.4 Repair / Replacement of wooden Seats
Replace all the wooden seats with the same size, colour and design should be as per RC IFC as required.
6.1.5 Repair of light poles (up to 3m height only)
Dismantle, remove and transport the light pole to the designated area if the foundation is to be replaced.
(Small light poles < 3m height is considered here)
Protect the luminaries and cables as required for re-use.
Repair of all pole foundation is to be done as procedure described in section 6.1.1
Repair / Replace the pole post luminaries, cables, anchor bolt and base plates as required
The pole having no lights / lamps will not be covered in this repair. However if there is any existing
fixtures, luminaries or any other accessories in the lighting poles (< 3m height) will be replaced as
required.
The light poles greater than 3m height will not be repaired in this scope. However all pole
foundation will be repaired accordingly.
The following are the required permit before implementing the activity:
Encroachment permit
Work permit (Excavation permit & Hot work permit if any)
Transport Permit
We intend to follow up and evaluate our performance by constantly implementing strict quality
control as this is the most critical activity that can affect our progress and constantly monitoring it
and implement measures to expedite this activity. The crewing system shall be monitored constantly
in order to meet the required volume installed and any delays shall be recorded and evaluated in
order to implement measures and improvements to augment the productivity.
Those names listed below confirm receipt of the method statement and have had the contents explained to
them/understand it and are aware of the site ES&H requirements.
Name Position Date Signature
Note to contractor supervisor – Any significant change from this method statement requires it to be revised and
resubmitted to OBI before work can commence.
11.0 APPENDICES