You are on page 1of 1

Method statement for road crossing works for duct bank (Road # D 2)

Safety

1. Ensure the availability of the PTW from concerned authorities


2. Safety measures to be checked by safety officer
3. Work will be carried out under supervision of xxx staff
Method

1. Surveyor to make the road crossing location as per the drawing


2. Cut the asphalt by asphalt cutter
3. Half of the road portion will be excavated up to 1.5 mtrs from existing ground level by
manual only
4. Compaction of the formation level
5. Place the polythene sheet above the formation level
6. Fix shutterings for concreting the duct bank
7. Placement of UPVC pipes inside sutterings
8. Concrete the duct bank with SRC 370kg concrete
9. Next day remove the shutterings and curing
10. Bitumen paint application on the duct bank
11. Back filling 30 cm, compaction and laying of warning tapes
12. Back filling up to 40 cm. below the asphalt level
13. Next 30 cm. filled with road base and compaction
14. The final layer will be paved with asphalt
15. The same method will follow the second half of the road

Page 1 of 1

You might also like