You are on page 1of 8

SUB-CONTRACTOR LATER NEEDS TANKAGE

K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A

SUB-CONTRACTOR METHOD STATEMENT


FOR Page No. Page 01 of 08

MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL

SAUDI KAYAN PETROCHEMICAL COMPLEX

PETROL STEEL

CONTRACT: LATER NEEDS TANKAGE PROJECT


CONTRACT No: 700-K-019-IK

METHOD STATEMENT

FOR

SITE PREPARATION , EXCAVATION & BACK FILL


(MAIN PLANT 1 & 2)

0 07.09.2008 Issued for Approval

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A

SUB-CONTRACTOR METHOD STATEMENT


FOR Page No. Page 02 of 08

MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL

Prepared by Reviewed by Approved by


Rev. No. Date Description
PSCL PSCL PSCL

TABLE OF CONTENTS

1.0 SCOPE

2.0 REFERENCE

3.0 DEFINITIONS

4.0 ROLES AND RESPONSIBILITIES

5.0 WORK EXECUTION PLAN

6.0 HEALTH, SAFETY AND RISK ASSESSMENT

7.0 QUALITY ASSURANCE AND QUALITY CONTROL

8.0 APPENDICES / FORMATS

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A

SUB-CONTRACTOR METHOD STATEMENT


FOR Page No. Page 03 of 08

MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL

3.0 SCOPE

Scope of this procedure covers all performances, and operations of site grading and earth
work for the LATER NEED TANKAGES Project for Saudi Kayan Petrochemical Complex
at Al-Jubail, Kingdom of Saudi Arabia, in order to elevate the site from existing level to
finished ground level/ HPP level to be carried out at 24 nos. of tanks locations as
specified below:-
1.1 T K- 71307
1.2 T K- 71313
1.3 T K- 82510
1.4 T K- 71302
1.5 T K- 77101
1.6 T K- 77105
1.7 T K- 72861

2.1 T K- 83201
2.2 T K- 83202
2.3 T K- 83203
2.4 T K - 83205
2.5 T K - 83206
2.6 T K- 83207
2.7 T K- 83251
2.8 T K- 83252

3.1 T K- 86105
3.2 T K- 86107
3.3 T K- 86106
3.4 T K- 86111
3.5 T K- 86108A
3.6 T K- 86108B
3.7 T K- 86113

2.0 REFERENCE DOCUMENTS


2.1 Approved IFC Drawings
2.2 Project Quality plan-
2.3 Safety and Medical plan
2.4 Project Specifications & Standards
2.4.1 CO2-SO1 - Site Preparation Specification
2.4.2 CO2-SO2 – Excavation & Backfill Specification
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A

SUB-CONTRACTOR METHOD STATEMENT


FOR Page No. Page 04 of 08

MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL

2.4.3 ASTM-C 136 Sieve Analysis of Fine and Course Aggregates


2.4.4 ASTM-D 422 Particle Size Analysis of Soils
2.4.5 ASTM D 1556 Standard Method for Density of Soil in Place by the
Cone Method
2.4.6 ASTM D 1557 Standards Method of Test for Moisture Density
Relations of soil (Modified Proctor Method)
2.4.7 ASTM D 2922 Test Method for Density of Soil and Soil Aggregate
in place by nuclear methods
2.4.8 ASTM D 2487 Classification of Soils for Engineering purpose
( united soil classification System)
2.4.9 ASTM D 2488 Description and identification of Soils
2.4.10 ASTM D 4253 Maximum Index density and unit weight of soil using
a vibratory table
2.4.11 ASTM D 4254 Maximum Index density and unit weight of Soil
using a vibratory table.
2.5 Occupational safety and Health Administration (OSHA) of USA
2.5.1 29 CFR 1926 Code of Federal Regulations
2.6 Higher Commission for Industrial Security (HCIS) of Saudi Arabia
2.6.1 SSD-29 Safety and Security Directives: The Safe Design, Construction,
Operation and Maintenance of Hydrocarbon Carrying Pipelines

3.0 DEFINITIONS

All terms used in the development of this method statement are defined in the above
mentioned documents.

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A

SUB-CONTRACTOR METHOD STATEMENT


FOR Page No. Page 05 of 08

MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL

4.0 RESPONSIBILITIES

4.1 Contractor’s surveyor has to verify all benchmarks of co-ordinates and levels,
establish all project required levels and co-ordinates using suitable undisturbed
monuments for project reference during the project of works.

4.2 Contractor’s construction engineer shall review and confirm that all works being
implemented as per the activities stated in the method statement and in
compliance with the code, standard and project specifications.

4.3 Contactor’s supervisor shall supervise all clearing and grubbing activities as
required by the project drawings and specifications, prepare and get all required
permits, and fulfil project target of completion or milestone requirements.

4.4 Contractor’s QA/QC Inspector shall monitor and assure all QA/QC requirements
of works and conduct inspections and maintain all records as required by project
QA/QC Program.

4.5 Contractor’s Safety Inspector shall monitor and assure that all works are carried
out in highly safe manner, gearing the workers with full strength of safety
protective equipment, preparation of safety barricading and dust control
screening wherever applicable in safe manner, safe workability of equipment to
be used and fulfilling any other additional safety needs as required during work
executions.

5.0 METHODOLOGY

1.1 EXCAVATION & GRADING


Prior to elevate the site to required level, the existing soil shall be excavated if required as per
drawing to 200 mm deep. Following sequence of works shall be carried under this activity.

5.1.1 Prepare all required permits and keep such documents at site always for the
verification by any authorized personnel at anytime.
5.1.2 Prior to start any excavation works the surveyor shall be establish, mark and
monument all required levels and co-ordinates for easy access and reference and
furnish a contour drawing showing contour levels at five meter ( 5 meter. ) intervals.
5.1.3 Prepare warning sign boards showing the classification of excavation such as
“shallow” or “deep excavation” and “Men at work” etc.
5.1.4 Prepare warning tapes and safety barricades as wide as required in the excavation
areas.
5.1.5 Provide flickering lights in the site for night time indications.
5.1.6 Check and assure the accessibility of equipment to be entered at site without causing
any damaged to any of the permanent or temporary properties present at site.
5.1.7 The sub-grade shall be compacted to required density of consolidation as per project
specification and tested through approved third party testing agency, witnessed by the
owner and certified by third party inspection team.
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A

SUB-CONTRACTOR METHOD STATEMENT


FOR Page No. Page 06 of 08

MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL

5.1.8 Deep of excavation shall be as per drawing and project requirement.


5.1.9 The excavated soil shall be safely remove and dumped at temporary dumping area
for final disposal.
5.1.10 The excavated bed shall be properly leveled and graded before compaction.
5.1.11 Finally the excavated bed shall be compacted to achieve relative density required as
per project specification.
5.1.12 The excavated sub-grade shall be compacted to required density of consolidation as
per project specification and tested through approved third party testing agency,
witnessed by the owner and certified by third party inspection team.

1.2 BACKFILLING
Following to the completion of sub-grade compaction, backfilling and grading shall be carried
out in the following sequence of works

5.1.13 Prior to start any backfilling works, it is necessary to prepare all fill materials approved
and make readily available at site.
5.1.14 Submittal for fill material shall be prepared in advance and submit to the owner along
with all required all laboratory analysis reports.
5.1.15 Availability of fill materials in sufficient quantity shall be assured to deliver at proposed
locations as per project approval and requirement during backfill and grading process
in turn.
5.1.16 Backfilling shall be carried out in layers as specified in the project specification, i.e. it
should be a maximum thickness of 150 mm in each layer.
5.1.17 Lying of fill and backfill material shall be carried out mechanically using pay loaders
and bobcats, provided each layer filled material shall be leveled mechanically or
manually with respect to the proximity and accessibility of fill location.
5.1.18 Each layers of fill shall be compacted mechanically before filling each consecutive
layers of fill until the completion of fill to required grade of elevation.

1.3 COMPACTION & TESTING


A systematic and methodical compaction and testing shall be maintained during backfilling.
Following sequence of works shall be carried out under this section of earthwork.

5.1.19 Prior to compaction works the soil material to be compacted shall be tested for finding
out each optimum moisture content, relative density, CBR value etc. and sieve
analysis to qualify the soil as filling material and find out basic technical data or
conducting the compaction test of fills and backfill.
5.1.20 The approve third party inspection team of agency shall execute all routine compact
tests at site.
5.1.21 Samples shall be taken from the borrow pits and from the site, the samples shall be
identified with proper tagging before sending to approved laboratory for conducting
required tests.
5.1.22 Fill materials shall be arranged as satisfactory marl material free of any contaminated
material or vegetations in order to comply with project specification of fill material.

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A

SUB-CONTRACTOR METHOD STATEMENT


FOR Page No. Page 07 of 08

MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL

5.1.23 All compaction tests related with backfill at its real turn and due courses during the
progress of works shall be properly planned in advance and programmed with third
party testing lab agency according to the requirement of the project.
5.1.24 Compaction of filling shall be done using roller compactor or plate load compactor as
suitable to the site conditions.
5.1.25 Following to the completion of compaction works, tests shall be conducted as per the
requirements specified in accordance with the relevant standards stipulated in the
Article No. 2.0, Reference Documents, of this method statement.
5.1.26 All the compaction works in the field and backfill shall be conducted in each
consecutive layer of 150 mm thick of soil.
5.1.27 All compaction tests carry out in the site shall be inspected, checks and certified by
the approve third party agency.
5.1.28 The compaction test records and certificates shall be properly documented and
preserved for project records.

6.0 HEALTH, SAFETY AND RISK ASSESSMENT

To ensure security directives during the execution of earth works, all activities shall be
monitored in compliance with relevant standards, codes and procedures described in the
company safety manual and project specifications as minimum as follows:

1.4 A safety officer shall be at site during the execution of works.


1.5 Daily tool box meetings shall be conducted as mandatory.
1.6 Following safety requirements shall be fulfilled
1.6.1 Safety barricade shall be prepared wherever necessary.
1.6.2 Necessary safety sign boards shall be provided as required.
1.6.3 All workers shall be provided with job specific Personal Protective Equipment.
1.6.4 Safety flickering lights shall be provided for nighttime indication.
1.6.5 All equipment shall be inspected by the approving authority prior to start of the work.
6.1.1 Working equipment shall be equipped with amber lights, horns, safety guards etc. as
Required per safety provisions.

1.7 Any incident at site shall be immediately reported to company and recorded.
6.2 Weekly safety statistics reports and safety performance reports etc. shall be prepared
and recorded.

6.6 Daily safety task assignment to be prepared.

7.0 QUALITY ASSURANCE AND QUALITY CONTROL

Quality assurance and quality control of the works shall be carried out inline with contractor’s
Quality Control program and approved ITP and method statement.
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A

SUB-CONTRACTOR METHOD STATEMENT


FOR Page No. Page 08 of 08

MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL

8.0 APPENDICES/ FORMAT

Not applicable.

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document

You might also like