K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A
MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL
PETROL STEEL
METHOD STATEMENT
FOR
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A
MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL
TABLE OF CONTENTS
1.0 SCOPE
2.0 REFERENCE
3.0 DEFINITIONS
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A
MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL
3.0 SCOPE
Scope of this procedure covers all performances, and operations of site grading and earth
work for the LATER NEED TANKAGES Project for Saudi Kayan Petrochemical Complex
at Al-Jubail, Kingdom of Saudi Arabia, in order to elevate the site from existing level to
finished ground level/ HPP level to be carried out at 24 nos. of tanks locations as
specified below:-
1.1 T K- 71307
1.2 T K- 71313
1.3 T K- 82510
1.4 T K- 71302
1.5 T K- 77101
1.6 T K- 77105
1.7 T K- 72861
2.1 T K- 83201
2.2 T K- 83202
2.3 T K- 83203
2.4 T K - 83205
2.5 T K - 83206
2.6 T K- 83207
2.7 T K- 83251
2.8 T K- 83252
3.1 T K- 86105
3.2 T K- 86107
3.3 T K- 86106
3.4 T K- 86111
3.5 T K- 86108A
3.6 T K- 86108B
3.7 T K- 86113
MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL
3.0 DEFINITIONS
All terms used in the development of this method statement are defined in the above
mentioned documents.
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A
MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL
4.0 RESPONSIBILITIES
4.1 Contractor’s surveyor has to verify all benchmarks of co-ordinates and levels,
establish all project required levels and co-ordinates using suitable undisturbed
monuments for project reference during the project of works.
4.2 Contractor’s construction engineer shall review and confirm that all works being
implemented as per the activities stated in the method statement and in
compliance with the code, standard and project specifications.
4.3 Contactor’s supervisor shall supervise all clearing and grubbing activities as
required by the project drawings and specifications, prepare and get all required
permits, and fulfil project target of completion or milestone requirements.
4.4 Contractor’s QA/QC Inspector shall monitor and assure all QA/QC requirements
of works and conduct inspections and maintain all records as required by project
QA/QC Program.
4.5 Contractor’s Safety Inspector shall monitor and assure that all works are carried
out in highly safe manner, gearing the workers with full strength of safety
protective equipment, preparation of safety barricading and dust control
screening wherever applicable in safe manner, safe workability of equipment to
be used and fulfilling any other additional safety needs as required during work
executions.
5.0 METHODOLOGY
5.1.1 Prepare all required permits and keep such documents at site always for the
verification by any authorized personnel at anytime.
5.1.2 Prior to start any excavation works the surveyor shall be establish, mark and
monument all required levels and co-ordinates for easy access and reference and
furnish a contour drawing showing contour levels at five meter ( 5 meter. ) intervals.
5.1.3 Prepare warning sign boards showing the classification of excavation such as
“shallow” or “deep excavation” and “Men at work” etc.
5.1.4 Prepare warning tapes and safety barricades as wide as required in the excavation
areas.
5.1.5 Provide flickering lights in the site for night time indications.
5.1.6 Check and assure the accessibility of equipment to be entered at site without causing
any damaged to any of the permanent or temporary properties present at site.
5.1.7 The sub-grade shall be compacted to required density of consolidation as per project
specification and tested through approved third party testing agency, witnessed by the
owner and certified by third party inspection team.
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A
MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL
1.2 BACKFILLING
Following to the completion of sub-grade compaction, backfilling and grading shall be carried
out in the following sequence of works
5.1.13 Prior to start any backfilling works, it is necessary to prepare all fill materials approved
and make readily available at site.
5.1.14 Submittal for fill material shall be prepared in advance and submit to the owner along
with all required all laboratory analysis reports.
5.1.15 Availability of fill materials in sufficient quantity shall be assured to deliver at proposed
locations as per project approval and requirement during backfill and grading process
in turn.
5.1.16 Backfilling shall be carried out in layers as specified in the project specification, i.e. it
should be a maximum thickness of 150 mm in each layer.
5.1.17 Lying of fill and backfill material shall be carried out mechanically using pay loaders
and bobcats, provided each layer filled material shall be leveled mechanically or
manually with respect to the proximity and accessibility of fill location.
5.1.18 Each layers of fill shall be compacted mechanically before filling each consecutive
layers of fill until the completion of fill to required grade of elevation.
5.1.19 Prior to compaction works the soil material to be compacted shall be tested for finding
out each optimum moisture content, relative density, CBR value etc. and sieve
analysis to qualify the soil as filling material and find out basic technical data or
conducting the compaction test of fills and backfill.
5.1.20 The approve third party inspection team of agency shall execute all routine compact
tests at site.
5.1.21 Samples shall be taken from the borrow pits and from the site, the samples shall be
identified with proper tagging before sending to approved laboratory for conducting
required tests.
5.1.22 Fill materials shall be arranged as satisfactory marl material free of any contaminated
material or vegetations in order to comply with project specification of fill material.
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A
MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL
5.1.23 All compaction tests related with backfill at its real turn and due courses during the
progress of works shall be properly planned in advance and programmed with third
party testing lab agency according to the requirement of the project.
5.1.24 Compaction of filling shall be done using roller compactor or plate load compactor as
suitable to the site conditions.
5.1.25 Following to the completion of compaction works, tests shall be conducted as per the
requirements specified in accordance with the relevant standards stipulated in the
Article No. 2.0, Reference Documents, of this method statement.
5.1.26 All the compaction works in the field and backfill shall be conducted in each
consecutive layer of 150 mm thick of soil.
5.1.27 All compaction tests carry out in the site shall be inspected, checks and certified by
the approve third party agency.
5.1.28 The compaction test records and certificates shall be properly documented and
preserved for project records.
To ensure security directives during the execution of earth works, all activities shall be
monitored in compliance with relevant standards, codes and procedures described in the
company safety manual and project specifications as minimum as follows:
1.7 Any incident at site shall be immediately reported to company and recorded.
6.2 Weekly safety statistics reports and safety performance reports etc. shall be prepared
and recorded.
Quality assurance and quality control of the works shall be carried out inline with contractor’s
Quality Control program and approved ITP and method statement.
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Users are advised to ensure the current revision status of this document
SUB-CONTRACTOR LATER NEEDS TANKAGE
K019-MCC-PSC-MS-
PETROL STEEL PROJECT Doc. No. 002A
MANARAH
SITE PREPARATION ,
AL-JUBAIL CONT. CORP. EXCAVATION & BACK Rev. No. 0
FILL
Not applicable.
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------