CANTiLEVER
Page No.
METHOD STATEMENT Revision :0
Issued :August 2002
Sdn Bhd CSB/UEC/MS/RB011/LPB/001
IMPORTANT:
The information contained herein is the proprietary property of CANTiLEVER SDN BHD.
CONTENTS
1.0 INTRODUCTION
2.0 MATERIALS
3.1 MANPOWER
3.2 EQUIPMENT
4.0 METHOD
6.0 APPENDICES
2
: 3 of 5
CANTiLEVER
Page No.
METHOD STATEMENT Revision :0
Issued :August 2002
Sdn Bhd CSB/UEC/MS/RB011/LPB/001
1.0 INTRODUCTION
This method statement describe the method and procedures for launching the precast
deck beam for the road bridge.
The launching layout and other relevant information on machinery and equipment used
in this work are included.
2.0 MATERIALS
The precast beam will be cast prior to the launching and the required design
strength achieved prior to the launching.
The position for the precast beam on the crosshead and abutment shall be
marked on the precast beam before launching.
3.1 MANPOWER
· 1 Engineer
· 1 Supervisor
· 1 Operator
· 2 Launcher
· 4 General Workers
3
: 4 of 5
CANTiLEVER
Page No.
METHOD STATEMENT Revision :0
Issued :August 2002
Sdn Bhd CSB/UEC/MS/RB011/LPB/001
· 1 Safety Office
3.2 EQUIPMENT
4.0 METHOD
· The working access and platform shall be levelled and compacted to form a
firm ground.
· Steel plate shall be provided at soft locations whenever it is necessary where
heavy machine will operate
· Audit survey shall be carry out for the top level of crosshead and abutment
where precast beams rest.
· The precast beam will be transported from casting yard to designed location by
trailers.
· The rubbers bearing shall be placed to the position marked by the surveyor
prior to launching.
· 1 no of 65 tonne and 40 tonne crawler/mobile crane will be used to hoist up the
precast beam from the trailer.
· Two general workers will be designated on each side of the crossbeam to guide
the precast beam to its correct position.
· The beam will be launched and placed on to the bearing pad planted in the
abutment bankseat. Any clashing starter bars will be bent by the barbenders
instantly to enable the precast beam to be placed on the crossbeams.
· The launching precast beam panel sequence will be from Span 2, Span 1
followed by Span 3 of the bridge (Appendix 1).
· Precast beam Type 2 shall be launched first, followed by Type 1 and Type 3
(Appendix 2).
4
: 5 of 5
CANTiLEVER
Page No.
METHOD STATEMENT Revision :0
Issued :August 2002
Sdn Bhd CSB/UEC/MS/RB011/LPB/001
5.2 Regulations
All site activities shall comply strictly with KTM regulations and requirement.
Before commencement of works all relevant staff will be briefed and trained to
comply with KTMB regulations. All staff will also be familiar with the
Construction Crisis Team’s Handbook.
6.0 APPENDICES
5
: 6 of 5
CANTiLEVER
Page No.
METHOD STATEMENT Revision :0
Issued :August 2002
Sdn Bhd CSB/UEC/MS/RB011/LPB/001
APPENDIX 1
6
: 7 of 5
CANTiLEVER
Page No.
METHOD STATEMENT Revision :0
Issued :August 2002
Sdn Bhd CSB/UEC/MS/RB011/LPB/001
APPENDIX 2
7
: 8 of 5
CANTiLEVER
Page No.
METHOD STATEMENT Revision :0
Issued :August 2002
Sdn Bhd CSB/UEC/MS/RB011/LPB/001