Page No : 1 of 7

METHOD STATEMENT Revision : 0


Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/SBRB/003

Electrified Double Track Project Between Ipoh and Rawang

METHOD STATEMENT FOR


SUB-BASE AND ROAD BASE WORK AT
APPROACH OF VBC KG. TITI BESI
(CH 232.457)

(PACKAGE KAMPAR TO BIDOR)

Prepared by Date Reviewed by Date Approved by Date

SHEIKH FAIZAL 15/11/02 MOHD FAUZI 15/11/02 TEE B T 16/11/02


Page No : 2 of 6
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/SBRB/003

Electrified Double Track Project Between Ipoh and Rawang

IMPORTANT:

The information contained herein is the proprietary property of UE CONSTRUCTION SDN


BHD.

The holder agrees to the following:


1. Not to reproduce; copy; reveal; publish; or, distribute it in whole or any portion of it
without authorization; and,
2. To maintain this document in confidence.

CONTENTS

1.0 SCOPE

2.0 MATERIALS

3.0 EQUIPMENT & RESOURCES

4.0 METHOD

5.0 QUALITY CONTROL PROCEDURE

6.0 HEALTH,SAFETY AND ENVIRONMENT

7.0 TRACK POSSESSION

8.0 SUMMARY OF FORM

9.0 DOCUMENTATION
Page No : 3 of 6
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/SBRB/003

Electrified Double Track Project Between Ipoh and Rawang

1.0 SCOPE

This methodology addresses the procedure to construct sub-base and


road base at the approach of Vehicular Box Culvert near Kg. Titi Besi.

2.0 MATERIALS

Summary of material for sub base and road base.

No Sample Purpose Source Remarks

1 ¾” aggregate,limestone Sub-base Granite Indah


2 Sand Sub-base Site
3 Crusher-run Road-base Granite Indah

3.0 EQUIPMENT & RESOURCES

Summary of Machinery.

No DESCRIPTION QUANTITY

1. Motor grader 1
2. Vibratory roller 25 tons 1
3. Back pusher 1
4. Tipper truck 3
5. Water tank 1

4.0 METHOD
Page No : 4 of 6
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/SBRB/003

Electrified Double Track Project Between Ipoh and Rawang

4.1 MIXING OF SUB- BASE MATERIALS

 Sub-base materials shall be a mixture of crusher- run and sand of


1:4 ratio.

 They are either mixed at site or quarry.

 For a site mix, respective material shall be delivered to site and


stock piled.

 Mixing of above mixture as sub-base material shall be carried out


using backhoe and back pusher.

 Each mix of sub-base shall be processed to obtain a uniform mix of


materials and moisture content throughout, acceptable for laying
and compaction. Compacted layer shall achieve 30% C.B.R @
150mm/250mm thick.

4.2 LAYING OF SUB-BASE

 Laying of sub-base shall commence on site upon approval and


acceptance of sub-grade formation. Where required, the works shall
proceed only after completion of surcharging.

 Laying, spreading, and grading to the required thickness and level


of the sub-base material shall be carried out using a back pusher
and a motor-grader. Reference pegs with level shall be provided at
20m intervals along the laying area to control the thickness and
gradient.

 The moisture content of the sub-base material shall be monitored


and water shall be applied to maintain specified moisture content.

 Compaction using vibratory roller shall commence when the


moisture content is +/-3.0% of the optimum moisture value.
Compaction shall be carried out in a single layer.

 Compaction trials shall be carried out to access the suitability of the


compaction plant and to establish the rolling pattern required to
achieve the specified compaction required.

 On completion of laying and compaction, joint survey (by dipping


and in situ density test shall be conducted to check for compliance
with the specified requirements. Reduced levels to be used for dips
shall be summarised at each required chainage as per available
cross sections
Page No : 5 of 6
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/SBRB/003

Electrified Double Track Project Between Ipoh and Rawang

 If the laid sub-base material has met compliance, approved upper


road base material shall be laid immediately.

4.3. CONSTRUCTION OF ROAD BASE

 The Road base material shall be ¾” aggregate (blended with 10mm


aggregate) from Granite Indah Sdn Bhd.

 Laboratory tests will be carried out on the proposed material to


comply with specification requirements.

4.4 LAYING OF ROAD BASE

The procedure of forming roadbase layer is similar to the sub base


construction.

5.0 QUALITY CONTROL PROCEDURE

Material specification for Sub base and Road Base shall follow Technical
Specification Clause 4.1.2 and 4.1.4 respectively.

Testing shall follow the procedure laid out in the Project Inspection & Test
Plan.

5.1. HIGHLIGT OF THE SPECIFICATION

 Criteria / Requirement of Sub Base

Soaked CBR > 30%


Plasticity Index < 6 PI

Test to show compliance with the specified requirements shall be carried


out.

 Compaction Requirement

Method of compaction to achieve not less than 95% of the Maximum Dry
Density as determined by BS 1377 Test 13.

 Criteria / Requirement of Road Base

Soaked CBR > 80%


Plasticity Index < 6 PI
Page No : 6 of 6
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/SBRB/003

Electrified Double Track Project Between Ipoh and Rawang

 Compaction Requirement

Method of compaction to achieve not less than 95% of the Maximum Dry
Density as determined by BS 1377 Test 13.

6.0 HEALTH, SAFETY AND ENVIRONMENT

6.1 Work will be carried out according to the Project Safety Plan.

6.2 Tool box meeting will be carried out on construction area at regular
interval to ensure compliance with the Safety Plan and familiarity with
accident and emergency procedures.

6.3 Conduct safety induction course to workers before commencement of


work.

6.4 Provide PPE to all workers including safety helmet, safety shoe, vest, etc.

6.5 Provide signboards to warn workers and public of dangers associated with
construction works.

6.6 Advanced traffic warning signs will be positioned in place along and at
entrance of access roads and designated flagman will be used when
working in the vicinity of existing road if required.

6.7 Ensure affected utilities, if any are relocated or protected prior to


commencement of work.

6.8 Water browser will be used to control dust when necessary.

6.9 Inspect all machinery at site and ensure that it has competent certificate
and is safe to operate.

7.0 LINE BLOCK APPLICATION

Not applicable.

8.0 SUMMARY OF FORMS

List of form to be used for the work is as follows :


Page No : 7 of 6
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/SBRB/003

Electrified Double Track Project Between Ipoh and Rawang

a) Dipping Form

9.0 DOCUMENTATION

9.1 Appendix 1 – Site Location


9.2 Appendix 2 – Site Organisation Chart
9.3 Appendix 3 – Laboratory Test Results
9.4 Appendix 4 – Dipping Form