Professional Documents
Culture Documents
: 1 of 6
METHOD STATEMENT Revision : 0
Issued : Sept 2001
UE Construction Sdn Bhd UEC/MS/MPKBP/AR/016
IMPORTANT:
CONTENTS
1.0 SCOPE
2.0 MATERIALS
4.0 METHOD
9.0 DOCUMENTATION
Page No. : 3 of 6
METHOD STATEMENT Revision : 0
Issued : Sept 2001
UE Construction Sdn Bhd UEC/MS/MPKBP/AR/016
1.0 SCOPE
2.0 MATERIALS
b) Pipe culverts
c) Crusher run
a) Survey equipment
c) Excavator/backhoe
d) Compactor
e) Back pusher
3.2 All plants and machinery will be with valid documents or licences.
4.0 METHOD
4.1 Project Engineer (PE) to carry out joint inspection with Project
Management Consultant (PMC) or Supervising Engineer (SE) or both at
the proposed route for approval and to confirm the requirements and
identify any obstacles.
4.2 Obtain approval from Pejabat Tanah dan Galian (PTG) Kampar for the
purpose of using the state land as an access road.
4.4 Obtain approval from Majlis Daerah Kampar (MDK) for felling trees.
4.6 Inform Jabatan Kerja Raya (JKR) and MDK regarding construction of
the access road.
4.9 Carry out site clearance as per Method Statement for Site Clearing
inclusive of felling and prunning existing palm trees, stripping
topsoil and dispose surplus material to approved dumping area.
(Ref : UEC/MS/GEN/M/002)
4.12 Felling trees by the side of Federal Route 1 (FR1) for widening at
the entrance/exit point of access road.
4.14 Provide temporary drainage alongside the proposed access road where
required.
4.16 Cutting existing ground to ramp down to the existing track level.
4.17 Supply, spread, level and compact 300mm thick crusher run for the
running surface.
4.18 Supply, spread, level and compact 300mm thick crusher run and 50mm
thick Asphaltic Concrete Binder Course (ACBC) at the entrance of
access road as per JKR requirement.
4.19 However, changes may be made to the above method of construction and
alignment of the proposed access road to suit existing ground
condition and local authority requirements subject to PMC/SE
approval.
Not applicable.
6.1 Work will be carried out in accordance with the Project Safety Plan.
6.4 Provide PPE to all workers including safety helmet, safety shoe,
vest, ear protector, etc.
6.6 Advanced traffic warning signs will be positioned in place along and
at entrance of access roads and designated flagmen will be used when
working in the vicinity of existing roads if required.
6.9 Inspect all machinery at site and ensure that it has competent
certificate and is safe to operate.
Not applicable.
Not applicable.
9.0 DOCUMENTATION