Professional Documents
Culture Documents
METHOD STATEMENT
1 May 2023
Table of Contents
1.0 OBJECTIVES
Pipe jacking is a technique of installing underground pipelines, ducts and culverts. It consists of
jacking specially designed pipes through the ground behind a jacking shield with hydraulic jacks.
The method provides a flexible and structurally sound finished pipeline. Pipe jacking is an
economical alternative to open trench works as well as to other forms of tunneling and is practically
useful in limiting the risk of surface settlement.
The scope of work covers the laying of VCP pipes and construction of pre-cast manhole
chamber from the toilet areas to the external manholes and including connection to the
existing IWK’s manhole on the main road for ASE Plant 4 & 5 Project.
3
PROJECT :
UNITE PERFECT METHOD STATEMENT
ENGINEERING SDN
BHD
a) In general, all the construction materials shall be planned and delivered near to the
workplace to avoid double handling.
b) All Materials to be used for construction shall be of approved type prior to delivery to site.
Correct or suitable machine shall be used during loading and unloading the material.
c) All pipe stacks shall be made on sufficiently firm, flat ground to support the weight of the pipes and the
necessary lifting equipment.
d) The stacking of material at the work areas shall not block any access.
4
PROJECT :
UNITE PERFECT METHOD STATEMENT
ENGINEERING SDN
BHD
blinded at the required level. The reinforcement for the structural concrete base will then be fixed and the
based poured
10) If micro tunnelling or pipe jacking is to be carried out immediately / not done immediately. Plastic
barrier will be placed around the top of the shaft and traffic management will be kept. This action will
only be carried out absolutely necessary.
11) After the micro tunnelling / pipe jacking work has been completed, inspection will be carried out for
all caisson joints to ensure no leakage / seepage of water. Then the permanent manhole will be constructed
from the bottom and up to the surface. Water plug mortar plug will be applied on joint area if water
leakage /seepage are detected.
12) Upon completion of manhole cover installation, the road surface will be reinstated
o) Clear & remove all the debris at the work area.
6
PROJECT :
UNITE PERFECT METHOD STATEMENT
ENGINEERING SDN
BHD
k) Lay the Sewerage Pipe for the sewerage line and connect to sewerage manhole.
o) Clear & remove all the debris at the work area.
8
PROJECT :
UNITE PERFECT METHOD STATEMENT
ENGINEERING SDN
BHD
9
PROJECT :
UNITE PERFECT METHOD STATEMENT
ENGINEERING SDN
BHD
All works and testing shall be accordance with the Quality Assurance Plan and the Inspection and Test Plan.
All inspection and testing shall be recorded on the proper forms and reviewed by QA/QC personnel.
10