You are on page 1of 22

ZONS TOP CONSTRUCTION GHANA LIMITED

CONSTRUCTION WORK METHOD


STATEMENT
FOR PROPOSED LARTEBIOKOSHIE APARTMENT
PROJECT

01-02-2023

2023
Table of Content Pages
1. Method statement for excavation & Blinding ………………. 2–4

2. Method statement for concrete slabs …………… ……… 5–8

3. Method statement for R.C.C columns construction ………... 9 – 12

4. Method statement for roof beams and slabs …………………. 13 – 15

5. Construction method statement for earthworks ……………… 16 - 20


cutting and filling(site grading works)

1
METHOD STATEMENT FOR EXCAVATION & BLINDING WORKS

1-0 PURPOSE / SCOPE

The purpose of this document is to define the procedure and method as well as all
parameters to perform proper way for excavation & blinding for all the foundations.

2-0 REFERENCES

- All work method documents of the earth working (excavation) & blinding concrete below the
main foundations.
- Specification for all the earth working & concrete work & the safety plans for such works.
- Contract related document for Civil Works.

3-0 DEFINITIONS AND ABREVIATIONS

- b.l: excavation bed level.

- s.s: side slopes for the excavation works.

- g.l: ground level.

4-0 WORK METHOD STATEMENT

4.1 General:

The excavation works should be done under the control of the specification & according to
the drawing of the works and so for the blinding concrete.
4.2 Pre-requisites:

4.2.1 The civil work section shall maintain a set of drawings for the excavation
works & the blinding concrete works of the latest revision in order to
avoid ambiguity.
4.2.2 The civil work section shall pre-prepare all the suitable materials, tools
& equipment for the excavations side-slopes (s.s), dewatering, fencing,
protection and safety.

4.2.3 The Survey section shall perform all the needed bench marks &
illustrate all the axis needed for location & control the excavation.

2
4.2.4 The civil work section shall perform all the needed tests for the blinding
concrete materials (gravel, sand, cement & water) & perform the mix-
design to conform the suitable strength in an approved laboratory if
required.
4.3 Procedure:

4.3.1 - The excavation work procedure shall be as follows:

1 - Clearing the site area & setting-out all the excavation area.

2 - Recording all the important ground levels (g.l) in the excavation area.

3 -. Starting excavation after the approval of drawing & the order of the Client. Excavation shall
extend a sufficient distance from the structure to allow for placement and removal of forms,
installation of services and inspections.

4 - Fencing the excavation area by low soil embankment to protect the excavation from being
flooded by the rainfall & by a red tape to attend the people from being full-in.

5 – If required the side slopes of the excavation should be excavated in a way conforming the soil
properties (the side slopes should be inclined in an angle to prevent the sides from failure,
otherwise the side slopes should be supported by many way approved by the client.)

6 – The contractor should excavate a small bit inside the excavation, in one or two corners to
collect the rainfall water and a pump should be installed to dewater.

7- In case of high water table the contractor should excavate a trench or a drain along the sides of
the foundation & in a suitable distance from the foundation to guide the water to the bits
mentioned above to pump out.

8 - After excavation, level and compact then to proceed with next activity.

3
4.3.2 – The blinding concrete work procedure should be as follows.

1- The materials used to produce concrete would be approved materials (gravel, sand,
cement, water, additives if needed.
2- A formwork (if needed) would be installed to control the concrete levels by the
contractor and pins installed in different places or in the corners of the form to control the
blinding levels.
3- The contractor would undertake the concrete finishing according to specification and
to the required finish level on the drawing.
4- Concrete curing would be carried out using water or an approved curing membrane.

5-0 - QUALITY CONTROL:

1- Pre- concreting inspection and approval should be done by the consultant for the
excavation and all the concreting plan of the contractor and the QC engineer of the contractor
should ensure that all the relevant staff is briefed on the requirements of this procedure and all
the control points noted e.g. hold points, witness etc.

2- The construction manager should fill-up a form (concrete order form) and forward to the
ready mix plant.
3- During concrete placing, samples shall be taken by the concrete laboratory technician in
accordance with sampling .molding & de-molding work instruction.

6-0 - SAFETY

The construction manager is to ensure that all the work requirements are fulfilled .e.g. if required
a job hazard analysis prior to the start of the activities that environmental requirements are
implemented and is conducted. All personnel wear the required personal Protective equipment.

4
METHOD STATEMENT FOR CONCRETE SLABS, COLUMNS & BEAMS

METHOD STATEMENT FOR POURING CONCRETE FOR SLAB ON GRADE

1. Title

Method Statement for Casting Slab on Grade

2. Purpose and scope

The purpose of this method statement is to explain the proper procedure on how to prepare and
cast slab on grade or any horizontal element or member including fixation of steel reinforcement,
MEP embedment’s, fixing of shutter etc. without injuries.

2.1 Preliminary Preparation

- Inspect the compaction of backfilling (FDT Test)

- Check the level for lean concrete of girder, and leveling work if it is less than 50mm and
compaction

- Lay the vapor barrier sheet were necessary/if indicated on drawings

- Lean concrete pouring and curing

- Application of primer and waterproofing membrane on lean concrete

3. Work procedure

1. Site planning

o Delivery – fresh concrete shall be batched from the approved supplier of concrete.
Concrete will be delivered direct to the site and to be received by assistant Quality
Engineer for checking of the required criteria of concrete or if in small quantity
onsite batching would be carried out. The assistant QC Engineer will make sure
the concrete delivered is as per the approved design mix for the situated member
to be casted.

5
o All data for testing on fresh concrete at site shall be recorded on the concrete
pour card.

2. Preparation

o After the blinding is cast and placement of waterproofing is done, the preparation
and casting for slab on grade shall be done.

o Fix the reinforcement steel as per the approved drawings, sometimes A393 BRC
mesh as indicated in the drawing and most commonly use in 150mm thick concrete
grade slab.

o Any loose binder or ties along the splices reinforcement steel shall be retightened.
Bend inward the free ends of the binding wire or ties.

o Use concrete spacer vertical bars and bottom as concrete covers.

o Ensure and coordinate with MEP staff for any MEP works required on the area as
per approved drawings.

o Fix the forms such; supports, sleeves etc., if any.

o Any damaged materials used for form work or shutter like plywood shall not be
used.

o All surface of forms or shutter facing concrete shall be treated with shuttering oil
and dampen with water few minutes before concrete will be poured.

o Clean the slabs on grade using air compressor for dust or any small particles or
deleterious materials that may impair the workability of concrete.

o The surveyor will then check the level of the projected top surface of the slab and
place level strips if necessary to mark the exact level.

o The concreting must be arranged with necessary equipment or tools for concreting
use such as vibrators, power float machine, shovel etc.

6
o Skilled and unskilled labor shall need to use safety requirements such as safety
helmet, safety shoes, goggles, gloves, vest etc.

o Safety devices and safety warnings shall be provided starting from the site entrance
gate till the casting area.
o Proper lighting must be available in case of night concreting

3. Concrete pouring

o The concrete mixer must be stopped at the check point for the inspection of slump
test and to obtain sample cubes for test.

o One set of cubes shall be taken every 50 cubic meter concrete, each set consist of 6
cubes, 3 cubes to be tested on 7th days and 3 cubes to be tested for 28th days.

o Extra three cubes can be made for re-checking if in case circumstances may happen.

o Unload the concrete within 90 minutes from the batching plant loading time.

o Compact the concrete properly by using mechanical vibrators, extra vibrator shall
be available in case of any shortage or mechanical problems.

o Use approved hardener material after casting concrete when required. Make sure
applications shall be as per manufacturer’s recommendation.

o Use the power float or troweling for the smooth finish surface purpose. Store extra
power float near the casting area in case of any mechanical malfunctioning.

o Cure the casted area properly by covering concrete with hessian cloth and
polythene sheet on top (before placing the concrete, wet the hessian with water) or
Cure the concrete by spraying water three times per day for a period of 7 days.

o The casted area or member shall be protected by placing barricade to prevent plants
and machineries damaged the concrete.

o Concrete cube test report shall be submitted to the Site Engineer

7
4. Safety

1. All works shall comply with safety procedure or instruction set out in project safety
plan and municipality rules and regulations.

2. Basic PPE to be worn by all staff and laborers.

3. Trained operator and banksman would be engaged to control or operate heavy


equipment machine.

4. Provide sufficient lighting whenever night casting.

5. Tool box talk shall be conducted before the activity.

5. Equipment and tools

1. Concrete Pump

2. Concrete Mixer

3. Mini truck

4. Concrete vibrators

5. Wheel borrow

6. Slump tray

7. Slump cone and other associated tools

8. Rubber hammer

6. Materials and References

1. C30 & C25 Concrete Grade

2. Deformed bars or A393 BRC mesh

8
3. Approved drawing

METHOD STATEMENT FOR R.C.C. COLUMNS CONSTRUCTION

1. Purpose/Scope

The purpose of this method statement is to explain the proper procedure on how to prepare and
cast reinforced columns.

2. EQUIPMENT’S & TOOLS REQUIRED

 Hand saw, wire cutter, brush, Shovel


 Steel Brush
 Plumb bob
 Line dory
 Vibrator
 Trowel
 Spirit Level

3. SAFETY & HEALTH REQUIREMENTS

Safety of the personnel and properties is to be given prime importance and all the works to be
carried out without causing any accidents or property damages. Concrete works involves the
following activities.

1. Shuttering and de-shuttering


2. Fabricating and fixing reinforcement steel.
3. Transportation of concrete.
4. Placing concrete at site

Adequate access and egress should be provided to the site for work. All the personnel should
wear basic personnel protective equipments. All the equipment, tools and tackles being used for
the work should be in good working condition and maintained. All the personnel will be provided
with toolbox talk on the procedures to execute the work safely.

9
4.0 PROCEDURE OF INSTALLATION & SEQUENCE

 Prior to start any activity on site, the consulting engineer must be notified.
 Ensure that all workers are aware of the evacuation plan.
 Cordon off the work area to prevent unauthorized entry.
 Discuss the method of working with all supervisors.
 All the related documents such as shop drawings, method statements, material
approvals, test certificates etc. must be approved and available upon request. Ensure
the source of supply of ready mix and grade of concrete. As well when batching on site.
 Spacer block shall be provided with the same grade of concrete.
 Arrange the concrete testing area with proper shading/and lighting.
 Polythene sheets, hessian cloths, water etc. shall be arranged for the proper curing.
 Ensure the position and alignment of starter bars of columns and walls.
 Clean the starter bar from cement paste or grout.
 Access scaffoldings, ladder etc. will be erected to allow reinforcement to be fixed.

Reinforcement

 The rebar diameter, number and shape are to be as per the approved drawing and bar
bending schedule.
 Rebar spacing and lap length should be as per the approved drawing.
 Adequate concrete cover to be maintained on all rebars.
 Links shall be provided as per the space provided in the drawings.
 Joints shall be staggered to minimize congestion.
 The line and level of rebar is to be checked prior to casting.
 The rebar will be fixed in such a manner that its stability is assured in all respect.
 Rebar and existing concrete will be presented for inspection before placing shutters.

Prior to erecting the shutters, box out and cast in items will be installed. These will be fixed
securely to ensure that they do not move during casting operation. The area will be
cleaned thoroughly by handpicking debris, blowing out sand if any with a compressed hose.

10
Form works
 All materials use for temporary form works should be clean strong and clear from any
deflection.
 Shutter will be treated with approved shutter releasing agent to enable easier stripping.
Install formwork to its dimensions correctly and ensure that lines and levels are within
the tolerances.
 The shutters will be braced and anchorages properly as per the drawings to maintain the
proper alignment and plumpness of the forms.
 Line and level of the shuttering will be set out by the surveyor. Shutters must be checked
for correctness in their final position.
 Tie rods shall be used for proper alignment.
 Tie rods are to be correctly tightened and rechecked prior to casting.
 Gaps in the shutter must be plugged out to minimize the possibility of grout loss during
the casting operation.

5.0 Concrete Placing, Compaction & Finishing

Concrete placement shall not start until all other trades have completed / installed their
embedment. Once all embedment are completed CLIENT approval shall be obtained.

Preparation for Placing

All surfaces shall be cleared thoroughly, remove any water. De-shuttering oil shall be placed on
the formwork.

Concrete Pouring
 Appropriate arrangement and approval for conveying concrete (pump or manual) shall
be obtained from client.

 Shovel and manual (use of head pan) methods will be used as per the elevation’ quantity
of concrete and to suit the site condition towards conveying & spreading concrete.

11
 Concrete shall be batched from a Pre-mixer supplier and transported via transit
mixers and discharged in concrete pump for depositing in forms.

 Concrete, during and immediately after depositing, shall be thoroughly compacted. The
compacting shall be done by mechanical vibrator.

 The vibration shall be of sufficient duration and intensity to compact the concrete
thoroughly but shall not be continued so as to cause segregation.

 Pouring height should not exceed more than 1.5m to prevent segregation.

 Each layer shall be compacted so as to avoid the formation of construction joint with the
previous layer which has not taken initial settlement.

 Concrete cover to be maintained as per drawings during casting operation.

 Concrete temperature shall be maintained below 30 C at the time of pour.

 Adequate illumination shall be provided during night concreting.

 Concrete temperature shall not exceed 30°C at the time of placing and during hot
weather the forms shall be shaded and sprayed with water. To prevent the premature
drying of concrete. It shall be covered with polythene sheets.

 During hot weather, pouring will be carried out in such a way that there will be no
formation of cold joint. If concreting activities are carried out during night time adequate
illumination shall be provided. Concrete shall be placed in shallow layers enough to assure
vibration well into the layers below and the elapsed time between the layers be
minimized to avoid cold joints.

Concrete Finishing and Curing

 Finish concrete surface as specified in the approved construction drawing and


specifications.

 Curing shall start immediately after initial set of concrete and finishing as free water has
disappeared from the surface of concrete. Curing shall be continued for minimum of 7
days.

12
Form Removal

 Forms and shoring in the formwork used to support the weight of concrete in
beams, slabs and other structural members shall remain in place until concrete
has reached a minimum of 70% of the specified 28 day strength i.e. 25 N/mm .
In absence of concrete cube results periods specified in clause 2.3.3 of Spec. shall
apply to the removal of formwork.

 Concrete shall be thoroughly wetted as soon as the forms are first loosened and shall
be kept wet during the removal operation and until the curing media is applied.
Great care shall be exercised during the removal of forms to avoid shocks or reversal
of stresses in the concrete.

 Surface defects if any corrected as per the engineer instruction.

METHOD STATEMENT FOR ROOF BEAMS AND SLABS

1. Purpose/Scope

The purpose of this method statement is to explain the proper procedure on how to prepare and
cast roof beams and slab.

2. REFERENCE STANDARD
- Surface Preparation
- General Requirements to Civil Works & Structures
- General Requirements to Concrete Works

3.0 Work Procedure

3.1 Preliminary Preparation

- Install the support of beam, girder and slab as per shop drawings. And temporary wooden
plank to be laid for suspended works.

13
- Supervisor stay to advice and to supervise the scaffolding and support system whether
it erected as per drawings.
- Install the external safety scaffolding conforming to safety regulation.
- Chip out the unsound concrete on construction joint of column to receive the new concrete.
- Remove rust, dust, residue or contaminated concrete on rebar with steel brush.

3.1.1 Formwork for Beam, Girder and Slab

- Install the soffit form of beam and girder on under floor support beam which are shown on
the drawings.
- Install the internal side form of beam and girder.
- Lay the slab form on underfoot support beam as per the drawings.
- Check the level and coordinates for beam, girder and slab by Surveyor
- Adjustment for level to be carried out with drop head
- Survey the location of opening/embedment’s
- Install the opening box and embedment
- The supervisor from supplier will check the conformance of shop drawings.
- Inspection requests for electrical and mechanical works should be submit
- The supervisor form supplier will check the conformance of shop drawings - Cleaning is to be
provided prior to rebar work

3.1.2 Rebar for Beam, Girder and Slab


- Rebar of Girder will install first as per drawings
- Rebar of beam will followed as per drawings
- Slab rebar is to provide at bottom/top bar where necessary - Conduit for electrical and
mechanical is also to be installed.
- Inspection requests for electrical and mechanical works would be submitted
- Installation of external side form of girder.
- Wall plate to receive roof trusses would be embedded where provided.

14
3.1.3 Final Scaffolding Inspection
- Installation of tie rod through the beam and girder @ 1000mm
- Installation of external side form of girder
- Check the fixing connection of each scaffolding / vertical stability
- Supervisor from consultant will give the certificate or confirmation for stability
(Subcontractor have the full responsibility for scaffolding system, safety during all the
work time)

3.1.4 Inspection for formwork and concrete


Inspection Points prior to QA/QC
1. The coordinates at each corner and level of slab by surveyor (using total station device)
2. The concrete cover of beam, girder and slab
3. The coordinates of 4 top corners of each girder by surveyor
4. The shoring for shuttering
5. The method of concrete pouring and preparation of equipment
6. The status of cleaning
7. Receiving the inspection of QA/QC and Company
8. For the roof beams, positioning of anchor bolts and base plate for steel trusses have to
be checked by consultant.

3.2 Concrete Pouring


- Check the climate for concrete, and follow the procedure of wind speed.

- Confirm the availability of concrete from own batch plant; otherwise contact the other batch
plants from outside.

- The beam or girder where the depth is over 400mm, the concrete to be placed 2(two) times
with 20minutes interval in order to reduce the settlement. (Concrete shall be always poured
in layer of max. 400mm)

- Plywood or polyethylene sheet to be laid around perimeter of beam/girder to avoid any


concrete debris during concrete placement of beam/girder.

15
3.2.1 Concrete Finishing

- If next new concrete is awaited, the surface to be rough otherwise the surface to be
finished with steel trowel.

- Areas where power float steel trowel could not be access, the steel trowel by manual to
be carried out.

4.0 Health and Safety

- All works shall comply with the safety procedure or instruction as set out in project
safety plan and municipality rules and regulations.

- Basic PPE shall be worn by all staff or laborers.

- All operatives shall be inducted before entering the site.

- Tool box talk shall be conducted before the activity.

- Statements to be reviewed and improved when necessary at any stage of construction.

Supervisors must enforce all safety procedures for compliance at all times

CONSTRUCTION METHOD STATEMENT FOR EARTHWORKS CUTTING


AND FILLING (SITE GRADING WORKS)

1.0 OBJECTIVE
The purpose of this method of statement is to define the procedures to ensure that the proposed
materials and workmanship to be used at the site are complying with the condition /
requirements as stipulated in the specifications.

2.0. SCOPE
This method statement covers the requirements for all earth works up to and including the
preparation of formation level. This method statement is to be adopted during earthwork
activities for widening and strengthening of highways. This method statement describes the
controlling elements during the exaction of earthworks.

16
3.0 REFERENCE

• Profile
• Construction Drawings

4.0 EQUIPMENTS
• Excavator/Backhoe
• Dump Truck
• Service Vehicle for General Workers
• Roller
• Grader

5.0 MANPOWER
• Supervising Engineer
• Supervisor / Foremen
• Operator
• Driver
• Skilled Workers
• Surveyor
• Unskilled Workers

6.0 SAFETY, HEALTH AND ENVIRONMENTAL ISSUES

• Conditions and precautions listed in the project specifications shall be followed as


minimum.

• All staff involved in the project shall be inducted on the safety, health and environmental
issues associated with the work.

• Only trained personnel with relevant experience shall be allowed to handle machinery.

• Appropriate Safety Signboards, barriers and lighting and other safeguards shall be
provided as required by the nature of and location of the works. All operations shall be
carried out in accordance with the safety requirements.

• All field personnel will use PPE safety requirements like safety shoes, helmets, cover all,
dust mask etc. are required.

17
7.0 PROCEDURE

• METHODOLOGY:

A. SETTING OUT:
Prior to any commencement of any physical works, a professional land surveyor shall be
appointed to carryout demarcation works and establish bench marks on site. Upon obtaining all
the necessary survey data, a joint survey to check existing ground levels shall be carried out with
the consulting engineers.

B. PREPARATION OF SITE:

• When any material is disposed outside the site, the disposed material shall be graded to
a neat appearance and shall not obstruct natural drainage or cause damage to highways
or property. All precautions shall be taken to prevent any erosion of the soil on the
affected areas.

• All unsuitable material and surplus suitable material shall be run to spoil in tips approved
by the Engineer.

C. EXCAVATION OF CUTTINGS

• The excavation of cutting shall be carried out in accordance with the relevant approved
drawings and to the levels, widths and heights shown thereon.

• Hauling of material from cuttings or the importation of fill material to the embankment
or other areas of fill shall proceed only when sufficient compaction plant is operating at
the place of deposition to ensure compliance with the specification requirements.

• Any excess depth excavated below the formation level exceeding tolerance of 300mm
shall be made good by backfilling with suitable material of similar characteristic of that
removed and compacted in accordance with specifications.

D. EXCAVATION FOR SITE LEVELLING AND SOIL REPLACEMENT


• Finish level shall be recorded in accordance to survey practice and jointly inspected in the
presence of Engineer.

• The side slopes of cuttings and embankments shall be as per the approved drawings.

18
E. EXCAVATION GENERAL
Removal of Unsuitable Material and Soft Spots

If during the progress of the work the soil encountered has characteristics, as determined by tests
conducted under the direction of the Engineer, that render it unsuitable for incorporation in the
road embankment, the Contractor shall excavate and remove such unsuitable material to the
extent directed by the Engineer.

Where Contractor finds isolated soft spots during excavation, this material shall be removed to
the extent directed by the Engineer.

No excavated suitable material shall be removed from the site without the approval of the
Engineer. Should the Contractor permitted to remove suitable material to suit his operational
procedure then he shall make good any consequent deficit of fill material arising there from.

Where the excavation reveals a combination of suitable and unsuitable material the excavation
shall, unless otherwise agreed with the Engineer, shall be carried out in such manner that the
suitable materials area excavated separately for use in the works without contamination by the
unsuitable material.

The hauling of excavated material to areas of fill shall proceed only when sufficient spreading
and compacting plant/equipment are operating at the place of deposition to ensure placing and
compaction.

Unsuitable excavated material shall be removed and carted away to an approved area after
approved by the Engineer.

Excavating High Level Areas

The Contractor shall excavate high level areas in all materials including rock for the full width of
the road construction down to the top of the required sub grade.

F. ROCK EXCAVATION

• Excavation in rock may be carried out by a tracked bulldozer and ripper or by the use of
blasting with explosives or any other method approved by the Engineer.

• After it has been established that the excavated material is rock and after the area where
such rock exists has been defined, the Contractor shall incorporate the rock in the
embankment.

19
G. EXCAVATION FOR PITS AND TRENCHES

• All trenches and pits under roads shall, where possible, be excavated, backfilled and
compacted before road construction commences.
• The sides of the excavation shall be adequately supported all times.
• Trenches and pits shall be kept free of water.
• Trenches for pipes or ducts shall be excavated to the levels and gradients indicated in the
contract documents.

H. FILLING GENERAL

• Filling low-level areas shall be to the level of sub grade as designated. After completion
of clearing and grubbing, the Contractor shall carry out the necessary leveling in order to
control the thickness of the layers of fill.

• The existing natural ground shall be scarified in place to a minimum depth of 75mm for
the full width of the embankment. The scarified material shall be leveled and compacted
to a minimum of 95% maximum dry density.

• Where an existing embankment is being widened, the existing embankment slope shall
be trimmed and compacted into benches of minimum width 1m and depth
500mm before placing and compacting each layer of new embankment material unless
otherwise directed by the Engineer to suit particular circumstances.

• The Contractor shall not proceed with filling and compaction any subsequent layer before
testing and securing the approval of the Engineer for the previous layer.

• Each fill thickness shall not exceed 300mm.

I. FORMING OF EMBANKMENTS AND OTHER AREAS OF FILL

• In areas of shallow filling, where after the removal of top soil, before embankment
construction is compacted, the surfaced of the ground shall be graded and compacted.

• Embankments and other areas of fill shall be formed of suitable material.

• All earthworks material placed in or below embankments, below formation level in


cuttings or elsewhere in the works shall be deposited and compacted as soon as
practicable after excavation in layers of thickness not exceeding 250mm.

20
• Embankments shall be built up evenly over the full width unless otherwise indicated
and shall be maintained at all times with a sufficient camber and a surface sufficiently
even to enable surface water to drain readily from them. During the construction of
embankments, construction traffic or water erosion shall be made good.

• Compaction of embankments and other areas of fill shall be undertaken to the


requirements of specifications. The embankments shall be constructed to sufficient width
to permit adequate compaction at the edges before trimming back.

J. PLACING & COMPACTION OF EMBANKMENTS & OTHER FILLS

• Earth fill on the embankments shall be spread so as to produce uniform distribution and
gradation of the earth fill throughout.

• Cluster of rock, which would interfere with proper compaction, will not be permitted. The
earth fill shall be placed in continuous, approximately horizontal layers over the length
being constructed for the full width of the embankment.

• Material which has been compacted to a dry density less than required or at a moisture
content outside the tolerable range shall be removed or reworked and re-compacted until
the required properties are achieved.

21

You might also like