Feb 23 Mar 23 Apr 23 May 23 Jun 23 1 1 Lartebiokoshie Apartments 90 days 13/02/2023 16/06/2023 2 1.1 Site Clearing and Establisment of Temporal Structures 7 days 13/02/2023 21/02/2023 3 1.2 Security Post and Fencewall 24 days 22/02/2023 27/03/2023 4 1.2.1 Excavation of for fencewall and security post foundation 4 days 22/02/2023 27/02/2023 2 5 1.2.2 Blockwork and Columns for fencewall 9 days 24/02/2023 08/03/2023 4SS+2 days 6 1.2.3 Blinding, Foundation and Footing Cloumns for Security post 5 days 28/02/2023 06/03/2023 4 7 1.2.4 Footing wall for security post 2 days 07/03/2023 08/03/2023 6 8 1.2.5 Backfilling 2 days 09/03/2023 10/03/2023 7 9 1.2.6 Slab on Grade 1 day 13/03/2023 13/03/2023 8 10 1.2.7 Blockwork for security post 3 days 14/03/2023 16/03/2023 9 11 1.2.8 Columns 3 days 17/03/2023 21/03/2023 10 12 1.2.9 Roofing 4 days 22/03/2023 27/03/2023 11 13 1.3 Main Building and Out House 72 days 09/03/2023 16/06/2023 14 1.3.1 Setting out of Building Positions 4 days 09/03/2023 14/03/2023 5 15 1.3.2 Excavation 8 days 15/03/2023 24/03/2023 14 16 1.3.3 Blinding, Column Bases, Strip Foundation 14 days 27/03/2023 13/04/2023 15 17 1.3.4 Foundation Footing wall 15 days 14/04/2023 04/05/2023 16 18 1.3.5 Foundatin Columns 5 days 05/05/2023 11/05/2023 17 19 1.3.6 Water/ Damp Proofing 3 days 10/05/2023 12/05/2023 18SS+3 days 20 1.3.7 Backfilling 7 days 15/05/2023 23/05/2023 19 21 1.3.8 Tie Beams 15 days 24/05/2023 13/06/2023 20 22 1.3.9 Slab on grade 3 days 14/06/2023 16/06/2023 21 23 1.3.10 Completion and Handing Over 0 days 16/06/2023 16/06/2023 22 16/06