You are on page 1of 1

No.

Task Name Duration Start Finish Predecessor 2Q23


Feb 23 Mar 23 Apr 23 May 23 Jun 23
1 1 Lartebiokoshie Apartments 90 days 13/02/2023 16/06/2023
2 1.1 Site Clearing and Establisment of Temporal Structures 7 days 13/02/2023 21/02/2023
3 1.2 Security Post and Fencewall 24 days 22/02/2023 27/03/2023
4 1.2.1 Excavation of for fencewall and security post foundation 4 days 22/02/2023 27/02/2023 2
5 1.2.2 Blockwork and Columns for fencewall 9 days 24/02/2023 08/03/2023 4SS+2 days
6 1.2.3 Blinding, Foundation and Footing Cloumns for Security post 5 days 28/02/2023 06/03/2023 4
7 1.2.4 Footing wall for security post 2 days 07/03/2023 08/03/2023 6
8 1.2.5 Backfilling 2 days 09/03/2023 10/03/2023 7
9 1.2.6 Slab on Grade 1 day 13/03/2023 13/03/2023 8
10 1.2.7 Blockwork for security post 3 days 14/03/2023 16/03/2023 9
11 1.2.8 Columns 3 days 17/03/2023 21/03/2023 10
12 1.2.9 Roofing 4 days 22/03/2023 27/03/2023 11
13 1.3 Main Building and Out House 72 days 09/03/2023 16/06/2023
14 1.3.1 Setting out of Building Positions 4 days 09/03/2023 14/03/2023 5
15 1.3.2 Excavation 8 days 15/03/2023 24/03/2023 14
16 1.3.3 Blinding, Column Bases, Strip Foundation 14 days 27/03/2023 13/04/2023 15
17 1.3.4 Foundation Footing wall 15 days 14/04/2023 04/05/2023 16
18 1.3.5 Foundatin Columns 5 days 05/05/2023 11/05/2023 17
19 1.3.6 Water/ Damp Proofing 3 days 10/05/2023 12/05/2023 18SS+3 days
20 1.3.7 Backfilling 7 days 15/05/2023 23/05/2023 19
21 1.3.8 Tie Beams 15 days 24/05/2023 13/06/2023 20
22 1.3.9 Slab on grade 3 days 14/06/2023 16/06/2023 21
23 1.3.10 Completion and Handing Over 0 days 16/06/2023 16/06/2023 22 16/06

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Lartebikoshie Apartmen
Milestone Inactive Summary Start-only Critical
Date: 08/02/2023
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1

You might also like