Professional Documents
Culture Documents
METHOD STATEMENT
FOR
Page 1
Method Statement for
Salambigar Industrial Park Threading Shop & SMC LBD Project
Table of Contents
5.Safety ········································································································· 5
Page 2
Method Statement for
Salambigar Industrial Park Threading Shop & SMC LBD Project
1. General Objective
This method statement describes the procedure and method of installation Doors and Windows for
Salambigar Industrial Park Threading Shop and SCM LBD Project
1.Doors and Windows Aluminum, Glass, Timber and Metal(As per Shop Drawing)
3.Paint TBA
4.Sealant TBA
3. Work Procedure
Page 3
Method Statement for
Salambigar Industrial Park Threading Shop & SMC LBD Project
3.3 Installation
Page 4
Method Statement for
Salambigar Industrial Park Threading Shop & SMC LBD Project
4. Quality Control
Protect doors and windows as recommended by the manufacturer to ensure without
damage deterioration at the time of completion.
Repair door and window that do not swing, slide or operate freely
Replace door and window that are damaged during installation.
Scratched during construction shall be immediately repaired.
5. Safety
During working time all workers should be worn Personal Protective Equipment such
us safety goggles, gloves, masks etc.
To dispose of waste material to appropriate place.
Page 5