Professional Documents
Culture Documents
GLASS WORKS
Preparation
1. Ensure that areas where the windows are to be installed are vacant for the duration of the works.
2. Restrict the working area to prevent unauthorized entry and prepare temporary access over the other
work in progress.
3. Wall opening must be finish on all masonry works and should be checked for any physical defects. Any
defects must be rectified before installation proceeds.
4. Wall opening must complied the required height and length of the glass window as respect with
approved shop drawing.
5. Erect scaffolding on the external side of the glass
6. Identifying potential complications in advance will help the installation run smoothly.
Execution
A. Begin for the Layouts
1. General Contractor must provide the Grid line, Finish floor line and other reference line as requested.
2. Surveyor will establish the glass line offset and center line of every window opening on the floor slab and
finish floor line on the wall or columns as respect to the approved shop drawings and working area
coordinates. Door opening reference line shall be establish if necessary and as requested.
B. Installation of Frames
Metrowide Homebuilders Inc.| Unit 2A New Pamplona Bldg. Alabang-Zapote Road, Las Pinas City
1. Before starting work, ensure that the correct Mullion (glass frame) sizes have been placed on the working
area, together with the necessary fixtures and fittings. Mullions should be checked for any damages,
Defective mullion should be repaired or replaced prior to installation.
2. Drill holes into floor slabs in the location of every vertical mullions, clean the holes, place the metal base
plate and put the expansion bolts together with the concrete epoxy.
3. Install the vertical mullion together with the metal insert inside the frames and fix it by welding the metal
insert to the metal base plate on the bottom of frames and also welding the metal insert to the metal
drop wall on the top of the frames.
4. Check for the plumb, level, and alignment of the installed vertical mullion as respect to the reference line.
After confirming the position of the vertical mullion, proceed to the next vertical mullion with the same
procedure as respect to the approved shop drawing.
5. For Transom (horizontal mullion) in between every vertical mullion, drill an 2 inches angle bars in both
vertical mullion where the transom located in top and bottom and fix it by drilling the transom to the
angle bars. Check for plumb, level, and alignment, if necessary, adjust and confirm.
6. After the completion of the glass frames, request for inspection to Engineer in charge. After the first hand
inspection by General Contractor’s Engineer, the installation shall be checked and approved by the
Developer.
F. Installation of Accessories
1. Window installation is completed with the fixing of accessories, including handles, locking devices, etc.
Alignment of the accessories should be checked during and after installation.
2. Precaution should be taken to avoid damage to glass panel and window frame in the course of fixing the
accessories. The accessories should be protected until all construction activities are completed.
3. All hardware shall be installed in strict accordance with the manufacturer’s directions.
Metrowide Homebuilders Inc.| Unit 2A New Pamplona Bldg. Alabang-Zapote Road, Las Pinas City
4. All work shall be installed plumb and secured with proper fastenings so as to make all work rigid and firm.
5. After installation, all finishing hardware shall operate and function smoothly and efficiently in strict accord
with their expected operating performance.
Metrowide Homebuilders Inc.| Unit 2A New Pamplona Bldg. Alabang-Zapote Road, Las Pinas City