TRANSMITTAL DOCUMENT Document Transmittal Number:

Attn : Ko Pyae Phyo Zaw


AAGC 048 / 06 / 2020

Job Title : QA Manager

Company : KST GROUP OF COMPANIES LIMITED Date : 1/6/2020

Project : PTTEP TOWER PROJECT

Subject : Method Statement for Aluminium Door and Window Installation

We forward herewith the following: For your Approval


Drawings Specification
Sketches Photostats
Site Instruction No. Other

Item Ref. No. Description


1 KST/AAG/RFA-M.S-024 Method Statement for Aluminium Door and Window Installation
12 sheets , 3 Sets (Color Print)

Sent via Courier TTZ Additional Information(s):…....................................................


Deliver at Site
Deliver at Office KST SITE OFFICE

Our Messenger
Your Messenger
Sender's name U THAN TUN ZAW

Receiver : Time : Date :


( )
PROVISION OF PTTEPI NEW OFFICE IN YANGON,MYANMAR
KST
Request for Approval ( RFA )

Project: Provision of PTTEPI New Office in Yangon,Myanmar Reference No: KST/AAG /RFA-MS-024
From: ASIA ALUMINIUM AND GLASS CO.,LTD Date: 1/6/2020
To (Company): KST Group of Companies Limited No: of Page(s): 12
Attention: KST Project Mananger
Subject : Method Statement for Door and Window Installation

Type of Work: Civil & Structure Archi Mechnical & Electrical Plumbing Sanitary

We forward herewith the following for your approval :


Shop drawings Specifications Materials
Calculations Test Report Others
`
Title:
Please kindly would like to submit Method Statement for Door and Window Installation

Area Required :
Reference Drawings :
Reference Specifications :
Attachments :

Sketch / Drawings Material Data Sheet / Catalogue Further Information


Submitted by,
Sign : Received Approval Date
Name : THAN TUN ZAW
Position : Deputy Project Mananger
Date : 30/5/2020

( Designer to Consider ) (Client) Others

CONSULTANT TO DESIGNER DESIGNER COMMENT TO CONSULTANT

From: From:
Sign : Sign :
Name : Name :
Position : Position :
Date : Date :

CONSULTANTS' COMMENT ( ATT To KST)

Approved for Construction Amended and resubmit as per comments Rejected

Approved with comments Approved with comments ;


- no resubmission required - Resubmission required

From: From:
Sign : Sign :
Name : Name :
Position : Position :
Date : Date :
METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION

PROJECT

PTT EP OFFICE TOWER PROJECT

MAYANGON , YANGON, MYANMAR

OWER

MYANMAR OIL AND GLASS ENTERPRISE (MOGE)

CONSULTANT

ATT Consultant Co., Ltd


Architectural Designer: SQ Architest & Planner Co., Ltd

SUBMITTED TO

KST GROUP OF COMPANIES LIMITED

SUBMITTED BY

Total 10 Pages (Including cover sheet)


Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

CONTENTS

SECTION PAGE

1. General……………………………………………………………………………………… 3

2. Definition……………………………………………………………………………………. 3

3. Scope of Work……………………………………………………………………………….. 3

4. Tools and Material…………………………………………………………………...…….… 3

5. Work Procedure…………………………………………………………………………… 4-8

6. Job Safety Analysis……………………………………………………………………….. 9-10

Page |2
Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

General

The method statement explains the detailed requirements and procedures for Aluminium Composite panel
installation.

Definition

Project owner: Myanma Oil and Gas Enterprise (MOGE)


Project Management Consultant:ATT Consultant Co., Ltd
Architectural Designer: SQ Architest & Planner Co., Ltd
Contractors: KST Group of Companies Limited

Scope of Work

This Method Statement is applicable for Aluminium window installation for PTTEP OFFICE TOWER
project as specified in Project specification.

Tools and Material

1. Pre fabricated Aluminum windows frame


2. M8 -50 mm Screw and PVC wall Plug
3. Backer rod
4. Paper tape
5. Weather Sealant
6. Theodolite Survey instrument
7. Laser leveling and Plummet
8. Electric Hammer Drill
9. Electric Drill

Page |3
Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

A-Work Procedure
Survey
• The main builder should provide major gridlines/ offset at each floor.

• Site survey will be performed when the area are ready


• All dimensions and actual site conditions will be collected

• Offset lines and reference level will be located for installation

• Any problems and discrepancy will be reported to consultant. The correction have to be
approved by consultant
1. Measure the Reference line bld and set out all positions of panel on the floor by chalk-line.

2.Prefabricated Aluminium windows delivery to site.

Page |4
Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

3.keep prefabricated frame near opening area

4.Checking again windows opening area ready to fixed or not

Page |5
Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

5.Fix the Aluminium window frame to the wall by Screw 450 mm spacing in horizontally and vertically.

a. Leveling and adjustment

b.Fixed the screw

Page |6
Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

6.Weathered Sealant after installation both in and out

• Apply silicone sealant at aluminum window frame boundary. Cleaning is required before
applying silicone sealant to ensure that the contact surfaces are clean enough.

Page |7
Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

Joint Backer Materials


Backer mate

JOINT WIDTH
DEPTH OVER CROWN OF BACKER ROD

3 mm (1/8”) MIN
BACKER

TO 10 mm (3/8”) MAX 5/10


6 mm (1/4”)
MINIMUM

8.Weather Sealant

Page |8
Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

Figure 1

Cleaning & Hand over:


The protective tape will be pulled out after installation is completed. Clean panel and silicone joint
before hand over.

Job Safety Analysis

Table No.1 Job Safety Analysis Title

Job Safety Analysis (JSA) No. 002


Job Description Date: 14 AUGUST
ALUMINIUM WINDOW INSTALLATION 2019
Reviewed by
Company Name AISAALUMINIUM AND GLASS Co.,Ltd

PTT EP Office Tower project Approved by


JSA no: 001
Location Mayangon TSP
Rev: 00

Signature: Revision by
Analyzed by ( )
KST ’s Safety Advisor

1. Safety Helmet
2. Safety Boots New Developed:
3. Safety Glasses
PPE Required 4. Glove Revised:
5. Life line wire 10/10

1. Electric Drill
Revised:
Tool Required 2. Electric Hammer Drill
3. Electric Screw driver
Date of Rev.:

Page |9
Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

Table No. 2 Job Safety Analysis

Potential Accidents or Recommended Safety


Sequence of Responsible Person(s)
Hazards. What can Job Steps and Control
Basic Steps and Completed
happen at each step? Procedure
- Hand or finger - Using glaves
High speed cut by griding while cutting - Workers
cutting wheel the objects. - Safety
macine - Eye injury by - Using the eye Coordinator
Hazards dust fr griding cover while - Supervisor
wheel cutting object
- Hand or finger - Use gloves
- Safety
burned by surface while the
Coordinator
Chemical cleaning liquid cleaning
- Supervisor
Hazards - Eye injury objects.
- Workers
because of cleaner - Ware the cover
liquid . glass .
- Check all
- Electrocution. - Safety
electric tools and
Electrical - Electric short Coordinator
coil. They must
Hazards circuit. - Electrician
be in good
- Workers
conditions
- While using High
speed cutting - Use dust
- Safety
machine/welding protective mask.
Dust Coordinator
machine / CNC - Use safety
Hazards - Supervisor
machine glasses while
- Workers
- working.

- Inspect trestle
before use.
- Hand/finger
- Use hand gloves,
Trestle and pinched by trestle - Safety
safety harness.
legs. Coordinator
Ladder - Falling objects.
- Do not put any
- Supervisor
Hazard tools on trestle.
- Falling from - Trained workers
- Do not put
height.
walking plank
between trestles

P a g e | 10
Project: PTTEP OFFICE TOWER PROJECT Rev. No.: 00
Doc.No: AAG-J-001/ENG/005 Date.: JUNE-1-2020
Doc.Title: METHOD STATEMENT FOR ALUMINIUM WINDOW INSTALLATION Page.:

P a g e | 11