Professional Documents
Culture Documents
For PAGE 1 OF 9
Dynamic REV A3
Replacement
TABLE OF CONTENTS
1. INTRODUCTION
2. SCOPE OF WORK
3. REFERENCES
6. DRAWINGS
11. RESPONSIBILITY
1. INTRODUCTION
This project is named Marjan Increment Program – Onshore Oil Facilities (package 6) located in the
Arabian Gulf, about 85 kilometers north – east of Tanajib.
1.1 Definition
COMPANY
CONTRACTOR
COMPANY REPRESENTATIVE : COMPANY’s authorized representative with overall
authority and responsibility for the project
2. SCOPE OF WORK
This method statement covers all Dynamic Replacement activities (Hereinafter called ‘DR’) stated
hereunder.
- Site preparation (removal of contaminated soil and grass)
- Setting out the area to be improved
- Material delivery, if required (currently planning to utilize the in-situ soil as backfilling material)
- Dynamic compaction/replacement with qualified material
- Leveling
- Pre/Post-test
3. REFERENCES
All design, engineering, material and construction shall conform to the latest requirements of local &
national standards, regulations and the following reference documents. Latest edition at the time of
contract award shall be applicable.
Any conflicts between the following references shall brought to the attention of the COMPANY for final
decision.
Soil density was varying from generally medium dense to very dense in condition from the existing
site grade, water depth various from 1.71m to 1.86m below the EGL and Fine Content is almost less
than 15%.
All the geotechnical data has been obtained from the submitted Geotechnical Investigation Report
which was prepared by approved subcontractor (named ‘Fugro-Suhaimi Ltd.’)
6. DRAWINGS
Geographic coordinates are based on Universal Transverse Mercator (UTM) coordinates system and
referenced to the international 1924 Ellipsoid AIN (AYN) Al ABD 1970 Datum, zone 39N
DR work shall stop when one of below two principles satisfies the requirements:
- Cumulative depth of crater achieves the design depth of replacement column in each DR
area
- Cumulative depth of crater has converged. This will depend on trial compaction results
8.2.3 Mark the Position of ramming point and measure the elevation of site
8.2.4 The DC machine moves in place and the rammer is placed at ramming point
8.2.5 Tamp and record the crater depth of tamping; when the tamping is too deep for
the hammer to be hoisted, stop tamping and fulfill the tamping pit, record the
quantity of filling
8.2.6 Repeat the section 8.2.5 until the design tamping times and quality control
standards are met
8.2.7 Complete the construction of all tamping point. Tamp from inside to outside or
interlacing if necessary
8.2.8 After leveling the site, surface compaction in low energy will be carried out to
densify the loose soil on the surface of the site, and then measure the elevation
of the site after compaction
8.2.9 The DC machine moves in place and the rammer is placed at ramming point
9.2.1 Pre treatment cone penetration tests (CPT) shall be taken at frequencies of
2,500m2 in between two successive pillars
9.2.2 Post treatment cone penetration tests (CPT) shall be taken at frequencies of
1,000m2 in between two successive pillars within two weeks after execution of
dynamic replacement works for comfortably allowing the dissipation of excess
pore water pressure through the pillars drainage paths.
9.2.3 The test results shall meet the design requiremnt stated in Section 5.
10.1.3 Have the main building materials, construction components (equipment) and
equipment used for the project approach test report
10.2 Handover
10.2.1 The system equipment and facilities function normally and are reliable to use
11. RESPONSIBILITY
11.1 PROJECT MANAGER
- Ensure compliance by all personnel involved to this procedure.
- Arrange for all required resources (manpower, equipment & materials)
- Ensure that any and all contractual obligations are satisfactorily complied with and
delivered on time.
11.6 ENGINEER
- Charge of the construction shall be responsible for completing documentation and
implementation of this procedure.
Method Statement MIP6-CV-0013-004
For PAGE 8 OF 9
Dynamic REV A3
Replacement