INFRASTRUCTURE PROJECT

Operational excellence for results that matter IMPLEMENTATION


Operational excellence for PLAN
results that matter
Operational excellence for results that matter

FORM IPI 08
SITE DAILY REPORT

Project Rehabilitation and construction of Tertiary Date 10/11/2018


Gravel road from Aybak-Beg Mohammad
Quduq Road to Kokjar Village (CH: 0+000 to
10+500 Km)

Contractor New Peak Construction Company Day 28


Contract No ITB/2018/4116 Weather 15 celcius
Work Area Kokjar Village, Hazrat-e Sultan District, Samangan Province
Contractor’s Resources
Project Manager 1 Surveyor 1 Mason 4 Plumber Nil
Site Eng. 2 Laborer 14 Plasterer Nil Electrical Nil
Mech. Eng. 1 Carpenter 5 Welder Nil Pergola carp Nil
Foreman 3 Steel Fixer 5 Operator 17 TOTAL 53
Contractor’s Major Plant
2 Excavators 8 Trucks 2 Roller
1 Grader 2 Water Tanks 2 Mixers

Safety and
Environmental No safety or environmental issues
Issues

Labour (shortages, quality, let downs) Enough labor with quality work.

Material (quality, delivery, issues, damages) Great qulity, Perfect delivery, No damages.
1. Cutting and filling of the road 2. Excavation of Culverts 3. Culverts’
Work in
framework and steel fixing 4. Pouring and curing of Culverts, 5. Delivering
progress
the sub-base material 6. Laying Sub-grade layer 7. Laying of Sub-base
layer.
Delays/
Disruptions/
No delays or disruptions.
Instructions/Mile
stones

Visitors,
comments, No visitors
complaints

Diary Issued by:

Eng. Feredoon Nasratzada

© UNOPS 2013 1
INFRASTRUCTURE PROJECT
Operational excellence for results that matter IMPLEMENTATION
Operational excellence for PLAN
results that matter
Operational excellence for results that matter

FORM IPI 08

© UNOPS 2013 2