Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
Date:
1 DESCRIPTION OF WORKS 4
3 RESPONSIBILITY 4
5 WORK METHODOLOGY 7
6 RESOURCES 8
8 ENVIRONMENT 9
10 RISK ASSESSMENT 10
2
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
11 APPENDIX 10
1. Description of Works
Describe the works covered by this Method Statement. Include or attach sketches, maps, drawings if applicable.
This method statement describes the procedure for mobilization of contractor’s site office/ portacabin,
workshop, storage area setup at site location as per the attached plot allocation – Reference (R12-012000-
TRS-PLN-PM-0207), including loading, offloading the portacabins, lifting operation, Erection of cabins, MEP
works, generator installation and power supply.
The methodology for the mobilization of contractor site office/ portacabin is described below.
3. Responsibility
Project Manager:
To ensure that all the preparation and application works are carried out according to the contract
specification and the approved drawings and method statement and risk assessment and rsg
applicable procedures and instructions.
To ensure that all the equipment and material required to execute the work are available according
to the planned program.
To coordinate with logistics coordinator, construction manager, site engineer and safety officer, for a
safe and proper execution of the works.
3
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
Construction Manager:
Overseeing the logistical requirements of a project.
Delegating work to colleagues within team.
Meeting regularly with clients, third parties and other managers to report on progress.
Setting targets, objectives and responsibilities for all supervised staff.
Regularly reviewing timings, budget, labor, risk and project plans to ensure work stays on track.
Setting and agreeing budgets.
Conducting site visits to inspect work, check materials and ensure staff are following health and
safety guidelines.
Dealing with contracts and mitigating the impact of any issues.
Ensuring the delivery of high-quality work within contract timescales.
Working in an office and on a construction site.
Foreman:
The foreman will carry out his duties by maintaining continuous coordination with the logistic
coordinator on daily basis and ensure proper distribution of the workforce in the required and planned
locations.
To ensure that his group is aware of the job requirements, and they have enough information to carry
out their duties properly.
To control disposal of waste materials according to the instructions received from the Site Engineer.
To ensure full coordination with the Safety Officer to maintain safe working and proper housekeeping of
the site, following the approved safety measures and further ensure that all his work team are aware of
the same to prevent accidents and losses.
To inform the Site Engineer about the areas ready for inspection. Distribution and the control of
material shall be monitored by Foreman and storekeeper.
4
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
Shall ensure that the safety of the workers is always taken into consideration.
He shall make sure that all materials used must be in safe condition.
All BKGCC-IHCC-JV workers and visitors should evacuate the working area to the nearest assembly
point.
Switch off all the running equipment and vehicles.
Park vehicle on side of the road that shall not block the access road.
Notify client representative and site management at the same time about the emergency.
Call all emergency number on 011-2127111
No one shall be allowed to come near the fire or accident area except for the authorized.
Head counting shall be done in assembly area by site supervisor.
All individuals shall stay in assembly area until all clear alarm activated or someone responsible
person give information of all clear.
5
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
Ambulance
997
Traffic
Police Civil
Defense
998
993
Police Road
Safety
999 996
SEC
933
5. Work Methodology
The necessary confirmation form client (RSG) and permits need to be obtained prior to mobilization of
the project site office.
The proposed site location to be checked with all existing utilities and all existing utilities to be
identified, marked, and protected as per requirement.
This methodology describes the details of survey works, site preparation, Installation of Porta cabins,
Erection of cabins, Office preparation, MEP works, Generator installation and power supply.
The demarcation of the proposed site office is to be carried out as per the approved shop drawing. The
surveyor will mark the location of the site office on the ground by driving pins not exceeding 300mm in
depth into the ground.
Location of cabin corners and location of all support points are to be marked on the ground.
Site Preparation:
The access route to the proposed site office for light vehicles and heavy vehicle/ plant for mobilization
of portable cabins is to be identified and all the traffic management to be in place with proper
illumination if required.
All required and necessary permits are to be obtained from concerned department.
Toolbox talk to be provided to all workers prior to commencement of any site work.
All exiting services/utilities are to be identified and protected.
The proposed site location is to be cleaned, surface to be compacted and masonry blocks to be laid for
the portable cabin foundation as per drawing.
The platform is to be prepared for the mobile crane works/ trailers movements and working location.
Erection of Cabins:
Each cabin must be connected properly and office to be prepared as per the drawing.
For working at height, permit to work at height to be obtain from concerned department. Only trained
and experienced workers are allowed to work at height. The ceiling joints will be attached and secured.
The flooring to cover with PVC floor covering as per approved material. All required cables and pipes to
be fixed and tested. Access doors will be fixed.
7
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
MEP Works:
All offices are to be equipped with required MEP works, Air conditioning system are to be installed as
per requirements and all electricals and plumbing works are to be carried out with certified electrician
and plumbers. Underground septic tank is to be constructed close to site office for office sewerage
network and periodically emptied by sludge tankers. In case an existing sewerage network is available in
the area of the offices, proper connection will be done to the nearest manhole after obtaining necessary
approval from the client/authorities.
6. Resources
Manpower:
Site Engineer----------------1No
Logistics Coordinator ---- 1 No
Supervisor-------------------1No
Charge hand-----------------1No
Safety officer----------------1No
Carpenters-------------------2No
Labors------------------------4No
Banksman--------------------1No
Rigger ------------------------1No
Electrician-------------------1No
Plumber----------------------1No
Plant/Machinery:
8
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
8. Environment
Dust control
High dust levels may occur during the mobilization stages. In case of high dust level, dust must be
suppressed by sprinkling water. Personnel exposed to dust shall wear dust masks.
Waste management
Waste skips shall be deployed in the area in order the general waste to be disposed of. The hazardous
waste shall be disposed separately in a hazardous waste area.
Wastewater shall be removed and pumped out as required by an approved contractor. Approved
company to be appointed to dispose and replace containers.
Noise control
High levels of noise are not expected to occur during the mobilization stage.
9. Night-time if required.
The following control measurements shall be fulfilled in case of nighttime working:
• Permit shall be obtained from client RSG.
• Each person shall be wearing high visibility jackets
9
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
11. Appendix
Risk Assessment
Proposed site office location drawing
10
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
Severity (S)
10 8 6 4 2 2 Minor Minor / <3 Days Injury Low – L 1-3 Acceptable
15 12 9 6 3 3 Moderate Moderate / >3 Days Injury Medium - M 4-9 Before task commences
Major / Permanent Disability 10-16 Before task
20 16 12 8 4 4 Major Injury High - H commences
25 20 15 10 5 5 Catastrophic Catastrophic / Fatality Very High - VH 20-25 Immediate
Certain or Imminent Very May
Likely Unlikely
Likely Happen
11
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
4 1 4 Pedestrians’ paths shall be segregated from the 16 4 4 Hit by, run over by Uncontrolled
maneuvering vehicles and plants as far as the maneuvering plants and
reasonably practicable. plants and equipment
All the equipment and plants shall be equipped equipment, serious maneuvering
12
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
3 1 3
Work area shall be graded / levelled to avoid slips,
9 3 3
Fall on same level, Slips and Trips
trips, and falls. Personal injuries hazards
All workers including staff shall be provided with
high visible vests (mandatory).
Mushroom caps or softener shall be provided for Protruding
3 1 3 9 3 3 Laceration
protruding steel reinforcement and sharp edges elements
Storage of material shall be in proper way.
Maintain good housekeeping all the time.
Work area shall be maintained with good
housekeeping, storage of material at designated
area only, good staking of material, barricade the
storage area with provision of adequate
illumination. Snakes and scorpion
Venomous
4 1 4 TBT Specific to Venomous Reptiles bites shall be 20 5 4 bites, internal organs
Reptiles
delivered to the work groups stating control failure
measures.
Long shoes and hand gloves shall be provided to
the workers.
Unfamiliar with
All employees shall undergo site safety induction.
4 1 4 16 4 4 Personnel injuries the site
Daily TBT shall be conducted by activity foreman.
condition
Permit to be obtained. Unauthorized
1 1 4 16 4 4 Fine from authority
Only permit holder to perform work. Photography
Gate pass for to be obtained. Unauthorized
1 1 4 Material gate pass to be obtained prior to entering 16 4 4 Fine from authority entry inside
inside the Red Sea premises. Red Sea
13
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
14
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
Multiple fractures,
No one allowed to stand or rest near/under the
fatality
parked equipment and plant. Resting under
Foreman/chargehand must ensure that no parked
5 1 5 20 4 5
operative resting under the plant and equipment. equipment and
Operator also has to ensure that no one resting plants
under their plant/equipment.
15
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
Electric shocks,
Keep the area of work dry and clean. - Wet conditions
burns, serious
5 1 5 Don’t use in wet condition. 20 4 5
injuries severe to
Pre-check of all the tools. fatality.
Never use damaged or faulty worn, blunt or
damaged bits and other accessories.
Conversion of power supply of 220 V into 110 V.
Contact with live
Management required ensuring provision of
electrical
correct and appropriate electrical tools and that
are being used for a particular purpose. components and
Be certain daily visual check by the operative prior cable causing
electrical shock, Faulty or
5 1 5 to use. 20 4 5
burns or damaged tools
Equipment should be capped by safety guards.
Select correct drill bits for the drill machine. electrocution.
Specific training of staff.
Fatality/Serious
Ensure periodical inspection of all electrical tools,
injury
equipment and -
Machines are carried out by completed electrician
and colour coded.
4 1 4 Hot work permit shall be obtained. 16 4 4 Fire/Burn/flying Unsafe carrying Hot works 5
Only trained operative shall be deployed particles out hot work (Welding, Cutting,
Face shield and leather apron and hand gloves shall activity Griding)
be used.
Fire extinguisher and trained fire watcher shall be
deployed.
Combustible material shall be removed for the
18
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
location.
Flash back arrestor shall be installed end of the
cutting set.
Fire blanket to be provided.
Hose shall be connected with jubilee clamps and
hose shall not be damaged.
Training, Discussion in Toolbox Talks, Kinetic lifting Permanent Back
Incorrect
4 1 4 technique - work to be done by leg muscles and 12 3 4 Posture when Manual Handling 6
Injury
not by back lifting
Employees shall be trained in safe lifting and
handling techniques.
Experience operatives shall be deployed for manual
handling. Incompetent /
Employees must avoid their hand / fingers placing
3 1 3 9 3 3 Personal Injury inexperienced
underneath of any object to prevent getting
crushed. crew
Supervision must ensure before involving
employees in manual handling that they are fit for
the work.
Back injury or hernia,
Ask for help - Team Lifting, Use Mechanical aids;
Load dropped on Excessively
4 1 4 Use pulling/pushing technique where appropriate. 16 4 4
Body Parts causing Heavy Load
Avoid manual lifting as far as reasonably practical.
Personal Injury
Plan before lift and maintain good communication Improper
Load may fall causing
4 1 4 during lift. 12 3 4 communication
damage/ injury
Route Survey shall be done by the operatives. during team lift
3 1 3 Training, Supervision, Assessment of load prior to 9 3 3 Load may fall causing Odd Shaped
lift, Balance and position body before shifting load, damage/ injury Load,
avoid manual lifting as far as reasonably practical. Imbalanced
Employees must avoid their hand / fingers placing Load/ Sharp
underneath of any object to prevent getting Objects
19
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
crushed.
Sharp edge shall be bend or removed from the
object.
Appropriate hand gloves shall be worn by the
operatives.
Clear route Before the Lift no obstruction in the
walkways. Route - steep
May result to
3 1 3 Alternative method / Use Mechanical Aids where 9 3 3 or narrow,
tripping or fall injury
applicable. slippery
Good Housekeeping shall be maintained
Lifting permit shall be obtained.
No person shall be stand under the load and load
Injuries severe to Falling of load Cabins- - Lifting
5 1 5 shall not pass over the operatives. 20 4 5 - 7
fatality on to operations
Area shall be properly barricaded warning signs
shall be provided personnel
Failure of lifting
Logistic / Engineer to ensure that crane/Hiab, all operation, collapse
lifting gears and operator are 3rd party valid of the crane/Hiab on Unapproved/
certificates. to person and
4 1 4 12 3 4 - uncertified
Site HSE team shall ensure that crane/Hiab material causing
crane/Hiab
inspection has been done and inspection tag injuries to person
provided. and property
damage.
4 1 4 Logistic/ Engineer to ensure that crane/Hiab, all 12 3 4 - Fall of material on to Faulty and
lifting gears, and operator are 3rd party valid workers and injuries, uncertified
certificates. lifting gears
Site HSE team shall ensure that crane/Hiab Property damage
inspection has been done and inspection tag
provided.
Competent lifting supervisor/rigger shall inspect
the lifting gear prior to lift.
20
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
-Absence of
MSDS for the
chemical
Emergency contact numbers must be displayed at
site. Workers not
Adequate PPEs shall be provided and worn by all as briefed about
mentioned in the MSDS. the MSDS of
Respiratory mask and full body coverall for the
the chemical.
painters.
Ensure proper information instruction training an Contact with
Supervision is provided. hazardous
Dip tray provide in the chemical storage area. chemicals
Adequate illumination shall be provided in work
area. Impact injury due to
4 1 4 16 4 4 Poor visibility
High visibility vest shall be worn by all engaged collision
operatives
Disruption of the
Site management to implement job rotation internal body clock
Supervisor to ensure all involved in night shift work (circadian rhythms)
are briefed regarding night shift hazards and
4 1 4 16 4 4 - Sleeping difficulties Sleep disorder
control measures.
Supervisor shall ensure that operatives had Stress, fatigue,
enough rest and sleep before deployment on task.
serious injuries
4 1 4 Daily attendance prior to starts the shift work and 16 4 4 Injuries due to lack of Lone working
at the end of shift. decision,
Lone working shall strictly be forbidden in the
night shift (at least two workers). Delay in emergency
Give brief regarding lone working and emergency being unconscious or
procedure. unable to inform
Foreman to inspect the area and ensure no one is
23
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
Dehydration,
Awareness training e.g. signs, symptoms,
emergency procedure and safe working practices Dizziness, fainting,
shall be provided to the all engaged team. vomiting, slurry
Heat and
Provision of cool, sufficient, and chilled water. 9 3 3 speech, Night shift Activity 9
Humidity
3 1 3 Rehydration drinks shall be provided.
Recess periods to be introduced during peak Un consciousness
hours.
Heat stress, heat
exhaustion severe to
fatality
4 1 4 16 4 4 Flying debris, Dust and storm
Weather forecast shall be monitor by the site interruptions,
logistic and safety team. property damage
If visibility is poor no diversions shall be carried out Adverse weather
10
All the works shall be ceased during dust and Uncontrolled traffic condition-
sandstorm/ rains until the weather conditions flow
restored to normal.
Personnel injuries
4 1 4 16 4 4 Slippery road may Rain/mist
No work shall be carried out in rain/mist or wet
lead to road traffic
road condition has been observed.
accident
Ensure all employees are made aware of how the COVID – 19 Working on 11
virus is transmitted and precautions to take.
Temperature shall be screened to all operatives Contracting the Exposure to the site
5 1 5
and staffs prior to entering site. virus,
20 4 5 COVID19 in different level with
The principles of social distancing shall be trained
Close Contact
24
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
to all workers and staff and shall include instruction Virus, spreading and multi
to keep 2m distance from other persons wherever
possible. COVID19, COVID personal contractor’s employees
Regular reminders and message reinforcement to transmission
19
observe the 2m rule shall be conducted.
Cross
Dispose used mask and gloves in designated infected / ill
contamination
Work shall be planned and arranged to prevent or
reduce the need for close contact work. health / Fatality
surface contact
Shift patterns shall be reviewed and split if
necessary
Small work groups 3 to 5 shall be considered
PPE such as surgical or N95 mask, or any mask
approved by authority hand gloves and safety glass
is mandatory for all site employees.
Not to share any personal item like drinking water
bottles, cups, glasses, dishes or cutlery, PPE and
other personal belongs.
Individual water bottles to be supplied
The drinking water stations shall be maintained and
cleaned on regular basis along with regular water
quality
testing and filter changing.
Nurses and first aiders shall be available at site to
deal
with any employee presenting with corona virus
symptoms
Information signage and posters shall be displayed
at strategic locations in multi languages.
Group site inspections shall be kept to a minimum
25
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
26
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies
27
Building Knowledge General Contracting Company LLC - KSA
A BK Gulf Group of Companies