Professional Documents
Culture Documents
(DK0+44 ~ DK26+461)
MS-08
Rev. B
Ref.Letter No :
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
CONTENT
This method statement provides the details of the materials, the equipment, the procedure
and relevant documents related to the construction of reinforced concrete box culverts.
2.2 BS 8666: 2000 Dimensioning, scheduling, cutting and bending steel reinforcement for
concrete structures
Construction manager, structural engineer, site engineer and other relevant personnel within
whose scope of works shall be responsible for referred construction activities in related to
construction of reinforced concrete box culverts shall carry out according to the method
Initially, the boundary of box culvert will be set out considering culvert width, working space
1/8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
The existing canals, drainage will be temporary diverted appropriately so there will be no
disturbances to the users. Temporary drains, ditches, earth berms will be constructed to
In the areas where soft soil exist other than preloading areas, the exaction will be carried up
to the design invert level of the proposed box culvert. After reaching the designed level, DCP
1. The DCP testing will be carried out to competent level where Penetration Index is less
than 10mm/blow.
2. Using penetration index, the SPT N will be obtained using the chart published by
Minnesota Department of Transportation. (refer annexure 3, figure 7a- relationship
between SPT N and PI)
3. After obtained SPT N value for sound bearing level, calculation for bearing capacity
will be calculated using conventional geotechnical equations and submit for
Engineer’s approval.
2/8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
If the fill height is greater than 0.5m, the filling will be done using 125 – 500 mm rock
material, blinded with 40mm graded aggregate at the top of the layer, to form dense
interlocking foundation. It will be compacted thoroughly to obtain firm surface. If the fill
height is less than 0.5m, the filling will be done using 40mm graded material and compact
thoroughly to obtain firm layer. The number of layers will be decided based on the height of
In areas other than soft ground areas, boulders, logs and other objectionable material
encounters during excavation will be removed. After complete the excavation the engineer
will be notified. No further construction activity will be carried out until the Engineer
Rock and other hard materials will be cleared off all loose materials and cut to a firm surface
either leveled, stepped or serrated as specified and shown in the drawings or as directed by
the Engineer.
All loose disintegrated rock and thin strata will be removed. When the foundation is to rest
other than rock, special care will be taken not to disturb the bottom of the excavation,
3/8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
4.2 Material
4.2.4 1.5mm thick, Highpolymer modified asphalt water proofing membrane (500mm width)
4.2.5 1.5mm thick, Polythene waterproof coating (660mm wide) – for movement joint
4.2.7 C40 concrete – 40mm thick cover layer for movement joint
4.3.8 C 30 concrete for retaining wall and culvert foundation at inlet and out let
4.3.9 C40 concrete for culvert, retaining wall and cap block
4.3 Construction
After completing the excavation up to design invert level, the bearing capacity verification
4/8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
will be done. If the bearing capacity is sufficient, a layer of rubble will be spread with
thickness not less than 100mm, under the foundation. The foundation concreting can be
b). Culvert inlet and outlet section foundation – C30 concrete layer, (2000mm x 2800mm x
5/8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
Before placing foundation concrete, the formwork will be setup using timber planks as
sideboards and steel rods as anchors, so that the sideboards will hold tightly.
The Retaining wall and culvert inlet - outlet foundation will be concreted together. The
internal vibrators will be used in culvert inlet-outlet foundation which thickness is 1m.
The freshly laid concrete will be kept undisturbed and protected from the effects of sun and
rain and from drying out /loss of moisture until it hardens. Once hardened, the concrete will
Reinforcement will be clean and free from loose rust and mill scale, dirt, oil, grease and paint
at the time of fixing in position and subsequent concreting. Reinforcement will be handled
Bars will be cut and bent cold by applying a slow, even pressure with equipment and
methods approved by the Engineer to the dimensions given in the Bar Bending Schedules
All reinforcing bars will be placed in positions shown in the Drawings and will be firmly held
in position, with the specified spacing, prior to concreting operations using necessary wire
ties at bar intersections, spacer bars, steel chairs of approved type or by other approved
means. Wire ties(binding) will be black annealed M.S or G.I. wire, not less than 1.0mm in
diameter and will be firmly tied and folded so that they do not project into concrete cover
region. The adequacy of supports and ties to secure the reinforcement properly will be
subject to the approval of the Engineer. Layers of bars will be separated by spacer bars,
concrete cover blocks All horizontal and vertical reinforcement will be supported on mortar
blocks, of approved shape conforming to cover requirements, with tie wires embedded in
them, made out of 1: 1 ½ or 1:2 cement sand mix. Supports which are in contact with the
external face of the concrete will all be concrete cover blocks. The use of small stones or
wood blocks will not be allowed. As far as possible, bars of full length will be used. In case
this is not possible splicing of bars will be done as specified in the Drawings or as directed by
the Engineer. Lap splicing (as per BS 5400 part -4 and design drawings) will be staggered for
different bars and will generally not be located at points, of maximum tensile stress.
No concreting will commence until the reinforcements have been inspected and approved by
the Engineer.
Reinforcement after being placed in position will be maintained in a clean condition until
7/8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
4.3.3 Formwork
The formwork will be timber, steel approved by the Engineer. Timber forms will be of
approved quality, well seasoned and of uniform thickness, sound, free from warps, loose
knots, twists, wavy edges, saps and shakes or other defects affecting the strength of the form
work and appearance of the finished surface of the retaining wall. Metal sheets use for
formwork will be kept free from rust and dents with no surface blemishes that will impair the
The supports and scaffoldings will be of metal, sawn timber, round timber or of any other
performed in the required sequence and in a safe manner. The false work will be properly
constructed to provide the necessary rigidity and to carry out loads, which will be required to
support. Where necessary it will include safe walkways to enable Engineer to inspect the
All formwork will be constructed that there will be no loss of materials from the fresh
concrete. Forms will be mortar tight, will be made sufficiently rigid by the use of ties and
bracing to prevent any displacement or sagging, and will be capable of withstanding all
Where internal ties, they will be extracted without damage to the concrete to a depth of at
8/8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
least 25mm from the finished concrete surface and the resulting holes filled with .non
shrinkage mortar. No permanently embedded nuts will have less than 25mm concrete cover
Immediately before concreting, the forms will be thoroughly cleaned either by water jetting
or by any other suitable method, temporary openings being provided for the purpose. Inside
surfaces will, coated with an approved material such as mould oil to prevent adhesion of the
concrete. This material will not be allowed to come in to contact with the reinforcement.
No concrete pouring will be carried out unless the Engineer has inspected and approved the
The engineer will be informed in advance, as to when the formwork removed. The minimum
period between concreting and formwork removal for culvert wall will be 01 day. For the slab
4.3.4 Concreting
When a truck mixer or agitator is used for transporting concrete, the concrete will be
delivered to the site of the work and discharged within one and half hours after the addition
of the cement to the aggregates. Each batch of the concrete delivered at the job site will be
fresh concrete will not allow exceeding 32°C unless otherwise specified. The addition of
9/8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
water after completion of initial mixing will not be allowed. Concrete that is not within the
Prior to placing of concrete all formwork and reinforcements therein will be cleaned of all
extraneous material, dust and made free of any standing water. It will be ensured that all
formwork is made leak proof and that there is no loss of mixing water or grout from the
concrete. No concreting will be started without the prior approval of the Engineer.
All mixed concrete will be placed and compacted in the formwork, using approved vibrators
of the internal, external or combinations thereof depending on the type of job. In all cases of
continuous concreting, fresh concrete will be placed before the already laid concrete is less
than 30 minutes old and where this time gap is exceeded further placing will be subject to
testing the already placed concrete surface to be live. In the event that the surface is not live,
All concrete generally will be placed and compacted in horizontal layers normally not
exceeding 300mm in depth except where adequately sized internal vibrators are used when
No concrete will be dropped from a height greater than about 1.5 meters except with the
prior approval of the Engineer. Where chutes are used for placing of concrete they will be
kept clean and used in a manner to prevent segregation. When concrete is conveyed by
chute, the pouring will be carried out in a way that to ensure practically continuous flow.
10 / 8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
Slope of the chute will be so adjusted that the concrete flows without the use of excessive
quantity of water and without any segregation of its ingredients. The delivery end of the
chute will be as close as possible to the point of deposit. The chute will be thoroughly flushed
with water before and after each working period and the water used for this purpose will be
When concreting has to be resumed on a surface which has hardened, the surface will be
roughened, swept clean thoroughly wetted and covered with a thin layer of cement grout or
cement mortar as approved. Semi-hardened surfaces will be well brushed to remove all
laitance, cleaned and covered with a thin layer of cement grout prior to overlaying with fresh
concrete. A concrete surface, which has hardened, will be treated as a construction joint for
further casting after not less than 24 hours. The surface will be free of laitance and leaned
until the surfaces of the larger aggregate are exposed. The aggregate stones will not be loose.
11 / 8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
100mm thick kicker will be casted by pouring additional concrete height above from the
100mm
12 / 8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
The lateral brace supports will be setup on formwork founded on culvert base to avoid
swaying of the frame during concreting of step 3. The brace supports will be independent for
each wall. The spacing will be same as vertical studs in longitudinal direction of the culvert.
The foundation bed concrete, which named as part one in above will be placed together
(sequence A).
Then the part 2,3and 4 will be concreted in different segments separated by the movement
joints.
E E
settlement joint
B C B C
D D
A
The sequence of concrete is A B C D E
The concrete pouring will be carried out using pouring buckets handled by a crane.
Whenever the concrete falling height will be more than 1.5m, especially in cases of
concreting sidewall of the box culvert, concrete will allowed to pour through a chute
arranged in a way that the free falling of concrete is less than 1m. The internal vibrators used
13 / 8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
during concreting work sufficiently, so the concrete will spread, compact in even along the
entire layer.
After completion of the structure tie holes will be filled with non-shrinkage cement mortar.
Prior to the backfill, the excavated area will be dewatered until existing bed exposes, and
the slope prepared 1: 0.5 gradient from the bottom of the excavation. The debris and other
unsuitable materials within the excavation area will be removed using excavators during the
0.5m
H 1:0.5
The back filling of two sides of culvert will be carried out using graded granular material or
permeable soil. The permeability requirement of back filling material will be 10-4 m/s.。 The
light compaction equipment will be used to compact the back fill adjacent to structure. The
compacted layer thickness will not be more than 150mm. The compaction will be not less
14 / 8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
than 93% of the maximum dry density. The backfilling work will be carried out both sides
simultaneously. The difference of the two sides filling height will not allowed to exceed
300mm.
5.1 Bearing capacity testing will be carried out at proposed foundation level after excavation.
5.3 Material for concrete will be from approved sources, compliance with requirements.
5.5 Reinforcements only from approved suppliers, brands, and in a acceptable conditions,
5.6 Binding wires shall be minimum thickness 0f 1mm, free from corrosion.
5.7 Cube samples will be collected 3 per each 10m3 and for each new pouring .
5.8 Temperature of the fresh concrete will be kept less than 32oC at the pouring time.
5.9 Slump of the concrete before pouring shall comply with the mix design requirements
5.10 After reinforcement fabrication completed, Engineer’s inspection will be called upon to
5.11 During the concrete pouring, internal vibrators are used adequately.
5.12 The pouring work will be carried out in approved manner, the layer thickness and time
5.13 The structure back billing will be strictly according to the drawings
6.1. Site staffs are allowed to enter the construction site only with the safety helmets on
their heads.
6.2. Mechanization of the sub base construction is applied in this trial section. All the
6.3. Safety measures must be taken during the excavation close to buildings, facilities’
6.4. To control the speed and keep the distance from other vehicles during the tipper is
running; Lighter vehicles should give way to heavier vehicles when passing each other;
6.5. It is forbidden to stand within the operating area of a running machine. All the
operations of machines shall strictly conform to the regulated process of safety operation.
6.6. When the soil structure is unstable, when the collapse happens and when the water
level rises suddenly or any other dangers occur, all the site staffs should immediately stop
16 / 8
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta Sector
the work and be evacuated to safe places. They can go back and resume the construction
17 / 8