The Employer The Engineer The Contractor

Project : Upgrade of M41 road section between Avicenna Monument and the West Gate, km 0 – km 1.2; km 1.94 – km 4.0; km 4.0 – km 4.9
RISK ASSESSMENT

Method Statement No: Assesed By: Ahmatbekov Ilhom Activity: Super Structure Construction

1 2 3 4 5 6 7 8
Factors of Harm Factors of Harm (after PCM)
Hazard Risk Rating Control Measures
Proposed Control Measures (PCM)
Likelihood Severity Risk Rating Likelihood Severity x<4 Implemented by

1) Good hosuekeeping habit must be maintained at all the time


2) Trenches/ excavation must be properly enclosed with barriers and
warning signboard.
Enviromental Engineers,Foreman &
2 1 2 3) Dust supression must be carried out as the need arises 1 2 2
Risks Chargehand
4) Close supervision during work in progress
5) Provision of proper training for all operatives.
6) Ensure all operatives using PPE propperly
1) Mandatory/ informative / directional signs must be posted on all
strategic points.

3) High reflective jackets must be worn by operatives all the time while
at work
Site Accidents 3 3 9 1 2 2 Engineers & Foreman

5) Close supervision during work in progress


6) Provision of proper training for all operatives.
7) Proper housekeeping must be carried out to avoid fire hazard.
8) Proper PPE must be used
1) Provision of tool bags while working.
Hand &
2) Inspecting tools for loose and deflecting parts.Reports and replace Engineers,Foreman &
Mechanical 2 2 4 1 2 2
immediately. Chargehand
Tools
3) Wear appropiate PPE.
1) Drinking water when hot.
Weather Engineers,Foreman &
1 1 1 2) Resting in suitable shaded areas in hot weathers 1 1 1
Conditions Workers
3) Adequate clothing and protection from cold and rain
Chemicals in 1) Wearing appropriate PPE (Gloves, Glasses)
1 1 1 2) Direct touch with concrete without PPE is forbidden 1 1 1 Workers
Concrete
Rigging 1) One supervisor as rigger must manage rigging operations
Engineers,Foreman &
(Lifting) 2 3 6 2) Slings must be tied and inspected by riggers and site supervisors 1 2 2
Riggers
Operations 3) Passing under the lifted load is prohibited, rigger shall organize
1) Provision of proper training to the person at risks.
Working at 2) Workers shall use full body harness Engineers,Foreman &
3 3 9 1 2 2
Height 3) Onauthorized person entry is prohibited Workers
4) Proper edge barricading shall be provided.
Classification
Likelihood of harm : Likely = 3, Possible = 2, Unlikely = 1
Severity of harm : Major Injury/death = 3, Notifiable = 2, Minor = 1
Risk Rating = Likelihood x Severity