Professional Documents
Culture Documents
Ref:
TINGKAT (317 BILIK) DENGAN 2 TINGKAT BESMEN YANG MENGANDUNGI: i. 2 QP23 Form
TINGKAT LOBI DAN SERVIS (ARAS TANAH & ARAS 40) ii. 4 TINGKAT RUANG 01
MEKANIKAL DAN RUANG PEKERJA (ARAS 1 - ARAS 4) iii. 34 TINGKAT HOTEL
Effective
PENGINAPAN (ARAS 5 - ARAS 38) iv. 6 TINGKAT KEMUDAHAN REKREASI / Date :
KOLAM RENANG (ARAS 39 - ARAS 43, TERMASUK ARAS 40 MEZANIN) v. 1 01/07/17
TINGKAT RUANG MEKANIKAL LIF (ARAS 44) vi. TEMPAT LETAK KERETA
CREST BUILDER MEKANIKAL BERTINGKAT (ARAS TANAH - ARAS 18) DI ATAS LOT 790, 791, 792 & Issue: 1
SDN BHD 793, JALAN IMBI, SEKSYEN 67, KUALA LUMPUR, WILAYAH PERSEKUTUAN Rev : 0
UNTUK MEGA CAPITAL DEVELOPMENT SDN BHD
Work
WMS Ref. No: CBSB/CAPRI/WMS/ARCH/18/003
Package
APPROVAL A B C
DATE
APPROVED FOR APPROVED REJECTED
CONSTRUCTION
WITH COMMENT
COMMENTS :
CAPRI HOTEL PROJECT
Ref. No.: WMS/CBSB/CAPRI/ARCH/003 Rev. 0
CREST BUILDER Page 1 of 11
SDN BHD WORK METHOD STATEMENT FOR BRICKWORK AND PLASTERING
TABLE OF CONTENT
3.0 REFERENCE 2
3.1 BRICKWORK 2
1.0 OBJECTIVE
This Method Statement acts as a general guideline for carrying out the all brickwork and
plastering in a safe manner and acceptable method, in order to meet the requirements of
the project as well as to achieve required standards with regards to materials, workmanship
and final product. The execution works and quality control shall be following not limited to the
material specifications.
2.1 This method statement describes all the necessary construction activities for
brickwork and plastering finishes work at Capri Hotel Project.
2.2 All work shall be carried out in according to the construction drawings, project
and material specification & standards.
3.0 REFERENCE
3.2 CBSB/CAPRI/MFSS/ARCHI/18/003, 004 & 018 – Material Submission for Portland &
Masonry Cement for Brickwork & Plastering
4.1 BRICKWORKS
4.1.1 General
4.1.2 Handling
All material for brickworks shall be handled and storage on site in such a manner
as to avoid damage or contamination.
4.2.1 Prepare the plaster by adding plaster powder approx. 10 litres of clean
water per 40 kg bag or as per the manufacturer’s recommendation.
4.2.2 An electronic mixer should be used to stir the mixture.
4.2.3 After mixing, allow the mixture to stand for ten (10) minutes for additives to
dissolve and mix again then the plaster is ready to be used.
CAPRI HOTEL PROJECT
Ref. No.: WMS/CBSB/CAPRI/ARCH/003 Rev. 0
Page 4 of 4
CREST BUILDER
SDN BHD
WORK METHOD STATEMENT FOR BRICKWORK AND PLASTERING
4.2.4 The surface to receive the plaster shall be free from dust, loose particles,
grease and traces of foreign materials.
4.2.5 Dampen dry absorbent surfaces before application of the plaster.
4.2.6 Apply the plaster manually with steel trowel or spatula.
4.2.7 When applying several layers, the layer underneath must be dry before
spreading the sub-sequent layer.
4.2.8 Rejected surface shall be hacked off completely and re-plastered.
5.1 All personnel are required to use the personal protective equipment (i.e.
helmet, safety boots, safety glass, hand gloves) and if necessary, shall use
other PPE according to his work.
5.4 The working area within the exclusion zone shall be barricaded and proper
signage shall be in place.
5.5 Only trained personnel shall be provided and will wear identification marking.
5.6 All works shall be done adhering to the Method Statement and Risk Assessment.
5.7 Control measures shall be fully implemented by all at all times supervised by
main contractor.
6.0 RECORDS
The forms below shall be used throughout the whole work process via SnagR, to ensure
the required quality can be achieved.