Doc. No.

CSC- G42-LSP-CSC-S-MST-003
Revision No.
Date:
METHOD STATEMENT FOR BLINDING WORKS

PROJECT : KIZAD LIFE SCIENCE PARK-PHASE-1

CLIENT : CNBG

LEAD CONSULTANT : AVIC/ECG

MAIN CONTRACTOR : CSCEC ME LLC

METHOD STATEMENT FOR BLINDING WORKS

CHINA STATE CONSTRUCTION ENGINEERING CORPORATION (MIDDLE EAST) (L.L.C.) 1|9


P.O. Box: 63932 Dubai, U.A.E
Tel: 00971-4-4537268
Doc. No. CSC- G42-LSP-CSC-S-MST-003
Revision No.
Date:
METHOD STATEMENT FOR BLINDING WORKS

REVISION RECORD

REV DATE PREPARED & REVIEWED APPROVED DESCRIPTION


Sherin Liang
Saravana Vijay Chong
Varghe
Murugan Chavan Gao
se Zhiguo
Constructio
13 JUN Technical QA/QC HSE n Sr. Project MST FOR
0 Manager Manager Officer Manager Manager
2021 BLINDING WORKS

CHINA STATE CONSTRUCTION ENGINEERING CORPORATION (MIDDLE EAST) (L.L.C.) 2|9


P.O. Box: 63932 Dubai, U.A.E
Tel: 00971-4-4537268
Doc. No. CSC- G42-LSP-CSC-S-MST-003
Revision No.
Date:
METHOD STATEMENT FOR BLINDING WORKS

TABLE OF CONTENTS

1. SCOPE & OBJECTIVE

2. REFERENCE

3. DETAILED PROCEDURE

4. HEALTH & SAFETY

5. EMERGENCY ARRANGEMENT

6. HAZARDS FACED WHILST CARRYING OUT THE WORKS

7. ORGANIZATION RESPONSIBILITIES

8. MANPOWER

9. MATERIALS

10. PLANT AND EQUIPMENTS

11. DISTRIBUTION

12. STATEMENT OF INTENT

APPENDIX A – ITP ,

APPENDIX B – CHECKLIST

APPENDIX C- RA

APPENDIX D – TECHNIAL DATA

1. SCOPE & OBJECTIVE


CHINA STATE CONSTRUCTION ENGINEERING CORPORATION (MIDDLE EAST) (L.L.C.) 3|9
P.O. Box: 63932 Dubai, U.A.E
Tel: 00971-4-4537268
Doc. No. CSC- G42-LSP-CSC-S-MST-003
Revision No.
Date:
METHOD STATEMENT FOR BLINDING WORKS

The document details the methods, materials, quality and safety controls to be implemented
in the execution of BLINDING of Concrete.

2. REFERENCES

2.1 GENERAL NOTES DWG

2.2 PROJECT SPECIFICATION – 313116 –Termite control

2.3 PROJECT SPECIFICATION – 312000 EARTHWORK

3. DETAILED PROCEDURE

3. 1 Compaction -

 Compaction to be performed as per required level and All the test for
compaction to be completed prior to start blinding works
 Plate load test, Field Density test , CBR etc. to be completed with
approved laboratory

3. 2 Antitermite Treatment -

 Antitermite Treatment to be conducted by as per approved material for


antitermite .
 Antitermite application to be followed as per manufacturer
recommendation & Technical data sheet of material.

3. 3 Blinding Concrete -

 Make sure that surface area is well compacted and compaction test
results are satisfactory
 Antitermite Treatment is completed & area to be covered with
Polythenesheet and need to cast the blinding within 24 hours of
application of anntitermite .
 Surveyor has to mark the area of Blinding & to be verified as per
approved SD & co-ordinate
 Shuttering for sides to be done with appropriate support system in order
to firm the concrete blinding .
CHINA STATE CONSTRUCTION ENGINEERING CORPORATION (MIDDLE EAST) (L.L.C.) 4|9
P.O. Box: 63932 Dubai, U.A.E
Tel: 00971-4-4537268
Doc. No. CSC- G42-LSP-CSC-S-MST-003
Revision No.
Date:
METHOD STATEMENT FOR BLINDING WORKS

 Use the Approved BLINDING MIX - C25/20 Concrete as per approved


specification & IFC
 Curing to be started immediately upon initial drying of concrete and to
be continued till the curing period as per specification

4. HEALTH AND SAFETY

Workplace inspections will be carried out by the person in control of the specific activity
by CSCEC and Sub-Contractor. Where Sub-Contractors are required to carry out such
inspections, the responsible CSCEC Manager must have a system of ensuring the
adequacy of the inspections process.
Compactor and equipment’s used for levelling will be inspected and ensure all valid
documents are available.
The works will be carried out according to all requirements set out in the site HSE Plan
and applicable

5. EMERGENCY ARRANGEMENTS

A Main Committee, known as the Emergency Planning Committee. (Mainly comprises


of Project Manager, Construction Manager, HSE Manager) which shall be responsible for
all decisions, connected with the handling of emergency. Depending on the type of
emergency, this committee may be called upon to make one or more or a combination of
the following decisions: -
 Shut down the Whole site and evacuate all workers
 Shut down affected part of the site and / or evacuate designated group (S) of
workers.

Adequate fire extinguishers will be provided at the work places and should ensure that
the access towards it is always maintained.
Depending on the situation, the committee shall keep in close communication and liaise
with one or more of the parties detailed in Emergency Numbers. (Police, Ambulance, Civil
Defence)

6. HAZARDS FACED WHILST CARRYING OUT THE WORKS

a) Struck by moving equipment


b) Work at height
c) Collapse / Fall of material while lifting
d) Use of Hand and power tools
e) Electrocution / Fire
f) Heat Stress
CHINA STATE CONSTRUCTION ENGINEERING CORPORATION (MIDDLE EAST) (L.L.C.) 5|9
P.O. Box: 63932 Dubai, U.A.E
Tel: 00971-4-4537268
Doc. No. CSC- G42-LSP-CSC-S-MST-003
Revision No.
Date:
METHOD STATEMENT FOR BLINDING WORKS

Additional hazards involved for the works will be identified, assess the risk and adequate
Control measure must be taken to minimise the potential hazards to a level as low as
Reasonably practicable.

7. ORGANISATIONAL RESPONSIBILITIES

7.1 The Project Manager will:

a) Review and approve the overall Construction Methodology.


b) Ensure the proper resources have been adequately specified.
c) Ensure that all the drawings and materials are approved.
d) Ensure that all the safety measures are being considered.
e) Ensure that all the workforces understand their roles in conducting the certain
activity.

7.2 The Construction Manager will:

a) Interface with Technical department to deploy and agree the best methodology
required for construction.
b) Plan and determine the required resources for conducting the work.
c) Interface with the Safety Personal to ensure that all aspects about the work are
being considered.
d) Brief all the Site Engineers and Foreman with regard to their roles and duties.
e) Monitor the work at site and guide the site team for any areas of improvement.

7.3 The QA/QC Manager

a) Monitor that all the activities are running as per Method Statement and
specification.
b) Prepare necessary inspection requests for materials and site activities.
c) Ensure that all necessary records such as test reports, approvals and other records
are in-place prior to commence with the work.
d) Ensure that all the tools for testing are provided before starting the backfilling work.
e) Coordinate with the Laboratory for collecting the samples and getting the results at
the required dates.

7.4 The Site Manager, Site Engineer & Foreman

CHINA STATE CONSTRUCTION ENGINEERING CORPORATION (MIDDLE EAST) (L.L.C.) 6|9


P.O. Box: 63932 Dubai, U.A.E
Tel: 00971-4-4537268
Doc. No. CSC- G42-LSP-CSC-S-MST-003
Revision No.
Date:
METHOD STATEMENT FOR BLINDING WORKS

a) Shall execute the job as per the approved method statement, drawings,
specifications and job Safety Analysis guidance.
b) Issue the correct and approved materials and explains the daily tasks to his
workforce.
c) Ensure Inspection request are in place on completion of the activity.
d) Work hand in hand with the Project Team to deliver a quality output.
e) Report to the Construction Manager for any discrepancies found in the drawings.

7.5 The Safety Officer: will advise and assist in ensuring that

a) All the requirements prescribed In the HSE plan are in place.


b) Plant & equipment to be used is in good working order and has the correct up to
date certification, where necessary
c) Workers are fully competent to carry out their tasks and are authorised to do so.
d) Required permits are in place before works commence
e) Safe access is provided to the working area.
f) Accident / incidents and near misses are reported promptly.
g) There is suitable provision of first aid.
h) There are suitable measure for the prevention and control of fire.
i) Site safety inspections are carried out on regular basis.

8. Manpower

8.1 The Manpower requirements for Antitermite / Blinding

 Site Engineer
 Supervisor / Foreman
 Safety Officer
 Rigger
 First Aider
CHINA STATE CONSTRUCTION ENGINEERING CORPORATION (MIDDLE EAST) (L.L.C.) 7|9
P.O. Box: 63932 Dubai, U.A.E
Tel: 00971-4-4537268
Doc. No. CSC- G42-LSP-CSC-S-MST-003
Revision No.
Date:
METHOD STATEMENT FOR BLINDING WORKS

 Carpenters
 Concrete team foreman
 Masons

9. Materials

 ANTITERMITE
 BLINDING CONCRETE
 POLYTHENE SHEET
 SHUTTERING
 VIBRATOR
 TROWEL , LEVELLING TOOL ,
 CONCRETING TOOL
 Commpaction testing Equipments
 Blinding concrete

10. Plant & Equipment Requirements

This section includes plant and equipment to be used – including power tools, hand tools,
access equipment, etc.

 RMC Truck
 Mobile Pump
 Shovel
 Excavator
 Cutting & Grinding machines
 Compactor machines
 Mechanical and carpentry tools
 Survey and levelling equipment

11. Distribution

(1) Project Manager


(2) Construction Manager
(3) Consultant
(4) QA/QC Manager / Sr. QAQC
(5) Safety Officer

CHINA STATE CONSTRUCTION ENGINEERING CORPORATION (MIDDLE EAST) (L.L.C.) 8|9


P.O. Box: 63932 Dubai, U.A.E
Tel: 00971-4-4537268
Doc. No. CSC- G42-LSP-CSC-S-MST-003
Revision No.
Date:
METHOD STATEMENT FOR BLINDING WORKS

12. Statement of Intent

CSCEC is committed to comply with national and local regulations and the Client’s
requirements to ensure that the project is delivered on time, within budget and to the
agreed quality and safety requirements. The Consultant will be notified of any changes
required on site and approval will be obtained prior to the works being carried out.

CHINA STATE CONSTRUCTION ENGINEERING CORPORATION (MIDDLE EAST) (L.L.C.) 9|9


P.O. Box: 63932 Dubai, U.A.E
Tel: 00971-4-4537268