B 4 Oct 2023 ISSUED FOR APPROVAL (IFA) Ranjith Riaz Yang Yang
A 27 Sep 2023 ISSUED FOR APPROVAL (IFA) Ranjith Riaz Yang Yang
CONTRACTOR :
Ace Water Pte Ltd
9 Jurong Town Hall Road, #02-14/15,
Singapore 609431
NTS CRISP-SUT2-SY2-MSRA-4-019 B 1 of 20
Doc No.
MSRA
Rev No. B
REMOVING OF EXISTING CABLE Rev Date 4-OCT-2023
FROM MCC & INSTALL NEW JUNCTION RA Ref.
BOX AND CABLE TERMINATION WORK Page No. 1 of 19
Project:
Crisp Project - SERAYA DEMIN PLANT
Contractor:
Title: P950-A SERAYA MSRA FOR REMOVING OF EXISTING CABLE FROM EXISTING MCC &
INSTALL NEW JUNCTION BOX AND CABLE TERMINATION WORK
Competent Person
HSSE
TABLE OF CONTENTS
1) SCOPE
2) PURPOSE
3) ROLE & RESPONSIBILITES
4) WORK ACTIVITY
5) HEALTH, SAFETY AND ENVIROMENT
6) HOUSE KEEPING / GENERAL
7) ORGANIZATION CHART
8) EMERGENCY ASSEMBLY AREA
9) EMERGENCY CONTACT LIST
10) EMERGENCY RESPONSE FLOW CHART
11) APPENDIX
1. SCOPE
2. PURPOSE
This work method of statement covers all the below given works in CRISP Package 1 process
Project scope of works. This document defines the method of statements and requirements
to,
Dismantle the existing cables then install the new junction boxes and terminate the existing
cables remove from MCC and new cables to new MCC at each side of junction box according
to approved Single Line Diagram. Do the necessary inspection upon completion of the above
work.
3.1. REFERENCES
3.3.1. Ensure that all rules and regulations as stipulated in the WSHA (Construction)
Regulations are met.
3.3.2. Plans, implements, and coordinates program to reduce or eliminate, occupational
injuries, illnesses deaths and financial losses: Identifies and appraises condition
which could produce accident and financial losses and evaluates potential of given
system, operation, or process.
3.3.3. Conducts or directs research studies to identify hazards and evaluate loss
producing potential of given system, operation, or process.
3.3.4. Develops accident prevention, loss control system and security programs from
incorporation into operational policies organization.
3.3.5. Maintains liaison with outside organizations such as fire departments, mutual aid
societies and rescue teams to assure informant exchange and mutual assistance.
Develops methods to evaluate safety program and conducts or directs evaluations.
3.3.6. Ensure that a project risk assessment is complete as is required by Singapore
legislation and is reviewed periodically.
3.3.7. Ensuring a training needs analysis is undertaken and the necessary training.
3.4. PROJECT ENGINEER
3.4.1. Familiarize himself with the Company’s environmental, health and safety
management system.
3.4.2. Review any new or changes in processes, equipment, and materials to ensure that
safety, health, and environment are not disregarded.
3.4.3. Ensure work is being carried out in accordance with the safe work practice and
method of statement.
3.4.4. Establish and maintain a programmed for the identification and assessment of
hazards.
Doc No.
MSRA
Rev No. B
REMOVING OF EXISTING CABLE Rev Date 04-OCT-2023
FROM MCC & INSTALL NEW JUNCTION RA Ref.
BOX AND CABLE TERMINATION WORK Page No. 4 of 19
3.5.1. Undergone and possess valid Certificate on WSH Co-coordinator Course and
OPSOC Course.
3.5.2. Liaise with the Client representative on matters relating to health, safety security
and environmental aspects of the project.
3.5.3. Inspect and rectify any unsafe place of work and unsafe practices.
3.5.4. Assist the Safety Manager, Workplace Safety and Health Officer and Environmental
Control Officer in all safety, health & environment matters.
3.5.5. Carry out site safety, health and environment programs and procedures.
3.5.6. Coordinates and assures compliance with the Risk Assessment Program.
3.5.7. Ensure that the issuance of personal protective equipment is properly recorded and
documented.
3.5.8. Coordinates and assures compliance with the Risk Assessment Program
3.5.9. To ensure all personnel working at site attended SembCorp in-house SIC.
3.6.1. Conduct daily Pre-task talk and Tool Box Meeting before commencement of work.
3.6.2. Ensure that workers know safety, health and environmental rules and regulations,
follow safe job procedures and be aware of all major hazards associated with their
work and work areas.
3.6.3. Responsible for the safety, health & welfare of all workers either assigned or not
assigned to him but may be working temporarily in his area.
3.6.4. Maintain satisfactory standards of housekeeping in his assigned area.
3.6.5. Investigate all incidents to workers and or equipment in his area and assist
Workplace Safety and Health Officer to put up accurate incident report on all such
investigation.
3.6.6. Ensure that all workers working in this area use the appropriate personal protective
equipment.
3.6.7. Ensure all PTW is approved, and all safety precautions are implemented as
indicated in the PTW.
3.6.8. To make sure the area where the work is to be carried out is barricaded out and
ensure safety.
3.7.1. Accepting individual responsibility for their own safety behavior as well as sharing
responsibility with their fellow workers and line supervision to look out for their own
as well as their co-workers.
3.7.2. Assist the skilled personnel / workers during the execution of assign task by the
Foreman and ensure that he understand and complied all the safety measures and
precautions.
3.7.3. Attend daily toolbox/ pre-task meetings.
3.7.4. Inspect all tools before use and daily.
3.7.5. To report potential hazard to supervisor.
Doc No.
MSRA
Rev No. B
REMOVING OF EXISTING CABLE Rev Date 04-OCT-2023
FROM MCC & INSTALL NEW JUNCTION RA Ref.
BOX AND CABLE TERMINATION WORK Page No. 5 of 19
3.8.2. Tools
3.8.3. Materials
4. WORK ACTIVITY
4.2. Removing of existing cable from MCC, install the new junction box and
cable termination work
• Ensure correct location where MCC and cables to be dismantled properly
identified according to the Single Line Diagram.
• Ensure respective breaker of all feeders is turned off at existing MCC side and
applied the lockout/ tagout by SUT Operation persons.
• Then, start to remove the cable from respective feeders.
• Do not apply excessive force when using hand tools. Use the right tools for the
job.
• Then, install the new junction box at the designated location as shown below.
• Finishing junction box installation, terminate the existing cables removed from
existing MCC and new cables to new MCC at each side of junction box.
• Completing the cable termination, ensure that the loop check is done.
• After finishing the task, housekeeping should be done.
The following list of items that is removing existing cables from existing MCC - A & B then
installing the new cables to new MCC – A & B at each side of new junction box.
5.1. Supervisor’s must ensure that method of statement (MS), Risk Assessment (RA).
5.2. Other necessary permits are available on site as well as preparations are checked.
5.3. Reviewed before allowing any work to commence.
5.4. Supervisors must brief all the workers with the contents all the method of statements,
Risk assessments during the daily toolbox meeting.
5.5. Ensure all workers and supervisors has attended and passed the Safety Induction
5.6. Course and other relevant training as prescribed by the Client.
6. HOUSEKEEPING / GENERAL
7. ORGANIZATION CHART
Proposed Project Delivery Organization Chart for Seraya Demin Plant Project
SEMBCORP (SUT)
Micheal Anandaraj Joseph Mic Stalin Lead Project Engineer 8339 5774
Accident Occurs
SUT PM / CCR
In House ERT
Housekeeping
General
2. Housekeeping / General
Doc No.
MSRA
Rev No. B
REMOVING OF EXISTING CABLE Rev Date 04-OCT-2023
FROM MCC & INSTALL JUNCTIOTEN RA Ref.
11. APPENDIX BOX AND CABLE TERMINATION WORK Page No. 14 of 19
RA Team RA Team Member
Company Approved By RA Leader RA Team Member 2 Last Review Date
Member 1 3
Ace Water Pte Ltd 19/7/2023
Process / Location Vinoth / Next Review Date
Yang Yang / Gabi / Kevins /
Ranjith / Electrical Engineer Project
CPVC Pipe Installation in existing plan at SUT Project Manager Project Engineer WSH Officer
Engineer 18/7/2024
Seraya Demin water plant Jurong Island
RA Ref No.
Signature
S/N Work Activity Hazard Possible Existing Risk Control S L Additional Risk Control S L
Risk Level
Risk Level
Risk/Accident Action Party and
Date of
Implementation
S/N Work Activity Hazard Possible Existing Risk Control S L Additional Risk Control S L
Risk Level
Risk Level
Risk/Accident Action Party and
Date of
Implementation
2. Isolate the power from existing MCC and apply the LOTO
• Lockout & Tag out. 5 2 10 • Close 5 1 5
• To wear standard PPE supervision
like Safety helmet, • Brief on manual
Turn OFF the safety shoes, nitrile handling safe
respective coated gloves. working
breaker at Electrical shock, procedure Site Supervisor
1.2. Electrical Hazard
feeder and Fatal • LOTO by immediate action
LOTO at the authorized
MCCB person and
verified by
supervisor and
officer.
3. Dismantling the existing cables from existing MCC then install the new junction boxes and termination of new cables
• Always inspect all 3 2 6 • Supervisors ensure 3 1 3
May cause bodily hand tools before use to check all tools are
Slip and fall.
injuries. every time. inspected before
Mobilization and
• Never use defective use.
demobilization Contact with sharp Site supervisor
1.3. Hand injury/lace tools on site.
resources and objects. immediate action
ration cut. • Use appropriate tools
tools
for respective jobs.
Manual handing.
Back injury • Adapt correct body
posture.
Doc No.
MSRA
Rev No. B
REMOVING OF EXISTING CABLE Rev Date 04-OCT-2023
FROM MCC & INSTALL JUNCTIOTEN RA Ref.
BOX AND CABLE TERMINATION WORK Page No. 16 of 19
• Use proper tools to 2 2 4 • Close supervision 2 1 2
open the bolt and nuts. • Brief on manual
• To wear standard PPE handling safe
Loosening nut Cuts and abrasions Site Supervisor
1.4. Pinching and cuts like safety helmet, working posture
and bolt to fingers. immediate action
safety shoes, safety
googles and safety
gloves.
S/N Work Activity Hazard Possible Existing Risk Control S L Additional Risk Control S L
Risk Level
Risk Level
Risk/Accident Action Party and
Date of
Implementation
S/N Work Activity Hazard Possible Existing Risk Control S L Additional Risk Control S L
Risk Level
Risk Level
Risk/Accident Action Party and
Date of
Implementation
S/N Work Activity Hazard Possible Existing Risk Control S L Additional Risk Control S L
Risk Level
Risk Level
Risk/Accident Action Party and
Date of
Implementation
Likelihood
Severity Rare Remote Occasional Frequent Almost
(1) (2) (3) (4) (5)
Catastrophic (5) 5 10 15 20 25
Major (4) 4 8 12 16 20
Moderate (3) 3 6 9 12 15
Minor (2) 2 4 6 8 10
Negotiable (1) 1 2 3 4 5