You are on page 1of 19

Doc. No.

: 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

Method Statement for Erection of Steel Structure

PROJECT : Engineering, Procurement and Construction (EPC) Inside


Battery Limits (ISBL) and Outside Battery Limits (OSBL) for
the Refinery Development Master Plan (RDMP) Project RU V
Balikpapan

LOCATION : RDMP Balikpapan, East Kalimantan, Indonesia

OWNER : PT PERTAMINA (Persero)


PO NO. : RDMP-R-SC-SSE-004-02

001 12 Sep 23 ISSUED FOR Ainaya Fatikhah Leland Adam Jefri Prabu
REVIEW Rokhni Syakuro Wijaya

REV. DATE DESCRIPTION PREPARED CHECKED APPROVED

PT. BIMA NUSAPERSADA SAKTI

1 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

2 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

REVISION LOG

REV. NO. DATE PAGE DESCRIPTION

00A 08 September 2023


001 12 September 2023

3 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

CONTENTS:

1. PURPOSE
2. SCOPE OF WORK
3. DEFINITION
4. REFERENCE
5. WORK PREPARATION
6. METHOD OF EXECUTION
7. ROLES AND RESPONSIBILITIES
8. TOOL & EQUIPMENT
9. ATTACHMENTS

4 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

1. PURPOSE
This procedure is to describe all activities to be performed for the lifting of steel structure in
order to ensure that all works are properly planned and executed safely in accordance with
all the requirements as stipulated in the contract document.
2. SCOPE OF WORK
This method statement covers for all activities related of erection steel structure for RDMP
JO Project PERTAMINA Balikpapan, Indonesia.

3. DEFINITION
Terms Definition
Project Engineering, Procurement and Construction (EPC) Inside Battery
Limits (ISBL) and Outside Battery Limits (OSBL) for the
Refinery Development Master Plan (RDMP) Project RU V
Balikpapan.
Owner PT PERTAMINA (Persero)
Contractor RDMP Balikpapan JO

4. REFERENCE
Doc No. Title
26071-100-GCX-00005 Procedure for Construction Method Statements
Structural Steel Standard Drawing General Notes and
26071-100-S0-000-00001-02
Abbreviation

5. WORK PREPARATION
5.1. Job Site Planning & Preparation
5.1.1. Make sure there is space and firmed pathway for truck delivery, crane truck
erection operation. The suitable truck & crane capacity must be clarified (and listed
in the equipment register).
5.1.2. Survey the wind direction to have plan for roof material storage and Installation
direction.
5.1.3. Decide the plan for unloading and material storage. Choose a firm and dry location.
Materials shall be stored in designated areas for each building and clearly identified
for their location in that area. Make sure that materials supply and storage schedule
is appropriate and not conflict with the installation schedule and other
subcontractors’ schedules.
5.1.4. Register the available power & water supply source locations at the site. Make sure
there is a safe method to lead the supply to the working area.

5.2. Receiving Material at Site


5.2.1. All delivery to sites hall be informed by production people to the site manager 24
hours earlier to have plan for unloading.
5.2.2. A delivery note is always enclosed with the supplied materials to clarify name of
project, location, building number, type of materials, quantity, date of delivery,
etc.

5 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

5.2.3. Upon arrival of materials at the storage yard, the material controller will match
delivery notes and shall verify the consignment. The material controller then
reports to the site supervisor the received material list and quality condition.
5.2.4. Unloading can be done use manual handling or with cranes. A spreader should be
used for lifting long components. Lifting nylon or cloth belts with suitable SWL
shall be used for unloading the materials to minimize the damage. Be sure to hook
belts to the component with the right no. of points and position so that the load of
component itself do not damaged or broken.
5.2.5. Always attach a tagline to the lifting component.
5.2.6. All materials receipt at site shall be visually inspected by site supervisor for any
damage. Remedial works to the damage shall be taken immediately, if possible, to
avoid any delay to erection and to be documented by report.

5.3. Loading-Unloading Material


Materials were shipped to job site separately or on the skid put in container. They are
unloaded by crane of worker manually up to the material properties. The average load
of trucks/trailers carrying materials is about 40 tons, this load is also the safety working
load of crane 25 ton. Therefore, the temporary road in the job site must be prepared
properly for crane and trucks/trailers working and required using 3 lashing to secure
structure material on trucks/trailer during mobilization to job site.Before unloading
materials out of trucks or containers, it is required to take pictures of real material status
delivered to the job site. Equipment and personnel shall be deployed as per requirement

5.4. Material Arrangement


5.4.1. Members should be checked park mark as packing list enclosed before unloading
for safe unloaded positions.
5.4.2. Columns should be arranged close to their anchor bolt position.
5.4.3. Rafter members should be arranged to ensure easy assembly movement.
5.4.4. Small components (nuts, bolts, clips, fasteners etc.) are stored in a given area
convenient to all parts of the building.

6. METHOD OF EXECUTION
6.1. Unloading Material
a. Make sure to have the Inspection Equipment before using it for unloading work.
b. Make sure the positioning direction of the Crane next to the trailer for the still
material on site.
c. Ensure a safe area for unloading the steel structure designated and crane capacities
not overloaded when lifting material off the trailer.
d. Make sure no other object at placement area on the ground and area has been
prepared to keep distances of ground to the material ±30cm.
e. Positioning steel plate on place for crane outrigger position.
f. The trailer backwards approaches the crane slowly and make sure materials on the
trailers does not exceed the capacity.
6 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

g. Unload steel structure material one by one from top of trailer to the area been
prepared on ground.
h. Access for outrigger cranes is strength and resistant to crane movement.

6.2. Chipping and Padding Works


a. Check the foundation will worked refer civil or erection drawing. Make sure
foundation has enough curing time of concrete.
b. Make sure all equipment and tools in good condition and been inspected by JO
c. Make sure there area safe for chipping and padding work.
d. Remove the laitance layer of the foundation concrete until gravel appears and
remove dust or rubbish with brush for concrete surface of pad area.
e. Keep wetting condition for concrete by watering before pad setting.
f. After inspection for padding setting, mark outside base form the centerline
g. Set padding plate on both side of anchor bolt and place where load may be
concentrated.
h. Put the pad cement/material on the board required and purring water then scrambled
manually until mixture cement has compacted.
i. Fully compact the mortar with hammer or a striking bar with mortar put in the form
little by little.
j. The baseliner surface shall be free from flow and others
k. Try to sink the baseliner in mortar while patting in with a wooden hammer is
compacted
l. Check dimension for anchor bolt and gap between foundation. Position and number
of top padding elevation using calibrated auto level tool refer drawing and ITP.

6.3 Ground Assembly


a. Transport material to assembly area and make sure assembly area shall have permit
from RU V in brownfield area.
b. Use crane for fit up column of the steel structure.
c. Fit up girder as per drawing and check gap between column.
d. Setting column and girder forming as frame in one row.
e. Install bolt & Nut, tighten the bolt until 60%-80% for column and girder.

6.4. Lifting Plan


a. Preparing all supporting document for lifting activities in area and make sure the
document has signed validation.
b. Ensure all equipment and tools in good condition has been inspected and verified by
JO and RU V.
c. Before lifting make sure the crane radius and load chart are in accordance with the
lifting plan, lower the block crane to install webbing sling lifting.
d. Install webbing sling in the pipe rack structure refers to lifting plan method and

7 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

install taglines before the structure is lift, and slowly during lifting the pipe rack
structure.
e. After the steel structure lifted hold a few minutes to ensure the condition of crane,
with crane indicator condition below 85%. Point swing crane right or left to
positioning the installed structure.

6.5. Main Frame Erection


a. Column materials were arranged close to design position.
b. Columns materials need to be cleaned and assembled before erection.
c. Attach driven rope to column.
d. Check level and position of level nuts and anchor bolts with design.
e. Use temporary lashing to hanging material erection structure
f. Temporary anchor points should be arranged out of the working area to avoid
hanging materials can be caught by temporary cable, this can cause collapse to
erected structures.
g. Check lifting weight, crane position with capacity of applied crane base on crane
specification issued by manufacturer.
h. Column materials were arranged close to design position.
i. Columns lift column and move slightly to design position.
j. Slightly down column on cast anchor bolts.
k. Remove webbing sling or wire after erection by tagline.
l. Tighten anchor bolts nut after column in right position.
m. Temporary cables will be applied to keep the column in position

6.6. Erection Sequence


a. After completion frames of braced bay, all components such as brace rod, flange
brace, etc. of this bay must be completed as design, to set up the space stable place
for next frames. Temporary bracing should be applied to this bay during erection for
safety.
b. Braced bay frames must be temporarily aligned before installation purlins, bracings
to avoid difficulties may get if conducting alignment for remained frames after that.
c. After completion frames alignment, request to have approval of client before
sheeting task.
d. Complete erection of main and secondary framing
e. Upon completion of all secondary framing in the braced bay the braced bay,
installing secondary framing in the end bay, paneling may commence and be worked
in conjunction with the completion of the balance of the secondary framing. This
could save time on larger buildings if separate sheeting crews are used.

6.7. Plumbness
a. Make sure all steel structure pipe rack is installed before doing plumbness and
verticality work.
b. The first step is to complete the column bolt to the girder, the girder to the bracing,
8 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

check that the bolt installation is according to the procedure.


c. After installation, all bolt fixtures are installed and equipped with a segment (1
segment 4 rows), attach the wire slings to row A and B column, and see the picture.
d. Wire slings are installed at a height of six meters and fixed with a chain block or
lever block, one row of columns using four chain blocks or lever blocks.
e. During plumbness, all wire sling positions that have been attached to the chain block
or lever block hold the column.
f. During that time the surveyor looks with the surveyor's equipment from the front and
the side, to as certain the alignment of the vertical column.
g. The surveyor team has ensured that the position of the column in the first row is
straight from the same front distance, then the fitter tightens the bolts of column A
and B.
h. Then tightening the material structure bolts between rows.

6.8. Bolt Tightening


a. Check the tools before use for bolt thightening works in good condition and passed
JO Inspection. Make sure all equipment and tools are ready.
b. Prepare the crane in a hard and not soft ground position, use steel plates as a crane
base (Outrigger crane). Prepare for the main basket near the crane and the tools
required for bolt tightening work. All the equipment for the job of tightening the
bolts has been prepared in the main basket.
c. Electric generators and cables of about thirty meters were prepared in advance. Bolt
tightening work starts from the foundation of the column, starting from the screw
tightening of the column plate base (A) and (B) then row coloumns (A) and (B)
continued with column precision.
d. Use scaffolding platform when structure connection and bolt tightening.
e. Make sure every worker who is at risk has a JSA and has been approved.
f. Worker shall familiar & understand operate if impact machine will be utilized to
eliminate possibility damaging bolt due of over tension.
g. Thighten the bolts and mark the bolt tightening that have been completed.

6.9. Grouting
a. Mixing, placing and curing of the grouting material shall be in accordance with the
manufacturer specification intended material for the grouting of foundation.
b. Prior to grout equipment, formwork has to be installed around the foundation by
using ½” thickness ply wood material and consider water PH.
c. Pouring of grout Material on to foundation should be done at one pouring point and
should let the grout follow by gravity force to prevent and air pocket occurred below
the base of equipment.
d. Grout temperature during placings hall not exceed 32°C or manufacture
specification, unless otherwise specified.
e. Maintenaned with minimal moisture loss at relatively constatnt temperature
minimum 3 days until hardened.

9 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

6.10. Touch Up Painting


a. The surface of material must be clean from spatter, debris, oil, salt, or another
chemicall organic. Power tool cleaning shall be used to be a feasible equipment for
cleaning in accordance with SSPC-SP3.
b. Preparation of all work equipment for repair, all work tools have passed the test for
use and tag by the JO.
c. Before applying the painting, the weather condition shall be monitored.
d. Make sure that all materials are delivered to the site according specification and
requirements.
e. A mixing ratio of the components shall strictly be adhered to where multicomponent
paints are used.

6.11. Install and Dismantle Scaffolding


Scafolding installation proposing for tightening bolt works and inspection. Base Plate
of the scaffolding shall be constructed on base of area/land. Soleplate at scafolding in
most cases when erecting a scaffold on the ground or on a foot path, a continuous
sole plate on 200mm x 38mm timber will be satisfactory. In addition to compacion, it
may be necessary to increase the thickness and the area of the soleplate. Guardrails
and toe boards shall be provided at the outer edges and ends of all scaffolding from
which a person could fall a distance of 2m or more.
A ladder raising a vertical height of more than 7m shall be provided with an
intermediate-landing place. The vertical distance between any two successive
landing places shall not exceed 7m. There should be at least 200 mm vertical and
horizontal clearances behind each rung of a ladder to permit a safe foot hold to be
obtained when ascending and descending. Each landing places hall not be less than
1400x700mm and shall have guardrails.

7. ROLES AND RESPONSIBILITIES


7.1. Construction Manager - Responsible during the process of lifting and ensuring all in
accordance with procedures.
7.2. Supervisor - Responsible for the overall planning, coordination and control of the
erection job.
7.3. Safetyman - Responsible for ensuring that all activities are carried out in a safety
manner and compliance with the established safety procedure.
7.4. Quality Control Inspector - Responsible to monitor and inspect the steel structure (pipe
rack) erection ensuring it is being done in compliance with this procedure, ITP
(Inspection and Test Plant), Drawing, Project specification and other reference
standard document and procedure.
7.5. Crane Operator - Responsible of the crane being operated during the lifting process.
7.6. Rigger and signal man – Responsible to ensure the crane properly operate safely
including mutual understanding with operator during the movement of crane,
maneuver, and lifting up/down in accordance with approved lifting procedure as well.

10 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

8. TOOL AND EQUIPMENT


8.1 Rigging Tools
No Description Capacity
1. Webbing Sling 3 Ton
2. Webbing Sling 2 Ton
3. Webbing Sling 5 Ton
4. Shackle 1” 6 Ton
5. Chain block 3 Ton
5. Lever Block 2 Ton

8.2 Lifting Equipment


No Description Capacity
1. Rough Terrain crane 25 Ton
2. Rough Terrain crane 50 Ton
3. Truck Mounted Crane 9 Ton

8.3 Inspection Tools


No Description Capacity
1. Auto Level
2. Total Station

9. ATTACHMENTS
1. Lifting Plan Drawing
2. Plan & Checklist for Lifting Works
3. Steel Structure Pipe Rack Drawing
4. Applicable Crane Load Chart
5. Method Chipping and Padding Plate Installation
6. Plot Plan

11 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

Attachment:
1. Lifting Drawing

Crane data’s Plan Remark


1. Crane type and model Rough Terrain crane 1 unit
2. Crane capacity 25 ton Crane assembly
3. Crane condition 100 % Test load
4. Main boom length 23,5 meter Boom exit
6. Load line revving sling Full line Block pulley
7. Hook block capacity 25 ton Block crane
8. Working radius crane 9 meter Lifting plan
9. Lifting capacity crane 7.850 kg Loadchart crane
10. Load lifting 3600 kg Column structure
11. Crane accessoris 230 kg Extra Load
12. Total load lifting 4210 kg Total load
13. Safety factor crane 53,67 % Crane Condition

12 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

Crane data’s Plan Remark


1. Crane type and model Rough Terrain crane 1 unit
2. Crane capacity 50 ton Crane assembly
3. Crane condition 100 % Test load
4. Main boom length 21,5 meter Boom exit
6. Load line revving sling Full line Block pulley
7. Hook block capacity 20 ton Block crane
8. Working radius crane 9 meter Lifting plan
9. Lifting capacity crane 11300 kg Loadchart crane
10. Load lifting 5000 kg Material structure
11. Crane accessoris 330 kg Extra Load
12. Total load lifting 5860 kg Total load
13. Safety factor crane 51,88 % Crane Condition

13 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

Attachment: 2. Plan & Checklist for Lifting Works


Heavy Equipment to be used
Crane data's Crane 25 Ton Crane 50 Ton Remarks
Crane Type and Model Crane Crane
Crane Capacity 25 Ton 50 Ton
Crane Condition 100 % (load test) 100 % (load test)
Luffing boom jib Length - -
Main boom length 23,5 meters 21,5 meters
Weight Counterweight full Counterweight full Counterweight
Load line revving sling full line revving full line revving
Hook block capacity 25 ton 30 ton
Working radius crane 9 meter 9 meter
Lifting Capacity Crane 7.850 Kg 11300 Kg Crane Load Chart

Lifting Load
Crane data's Crane 25 Ton Crane 50 Ton Remarks
Erection / lifting weight 3,6 Ton 5 Ton
Weight Chain block - -
Weight of shackle 0,02 Ton 0,02 Ton
Weight of webbing sling lifting 0,01 Ton 0,01 Ton
Weight of wire rope revving - -
Weight of hook block 0,2 Ton 0,3 Ton
Total load lifting 4,2 Ton 5,86 Ton

Lifiting gear to be used


Lifting Used (25 Ton) Used (50 Ton) Remark
Equipment s
Webbing sling Capacity 1" = 6 ton x 2 = 12 ton 1" = 6 ton x 2 = 12 ton
Sling Equipment Webbing Sling Steel Webbing Sling Steel
Sling Length 6 meter 6 meter
Sling Angle 60 deg 60 deg
Chain block - -
Webbing Sling Total 2 pcs 2 pcs
Webbing Sling Arragement Angle deg Angle deg
Shackle Capacity 8 ton 8 ton
Chain block Capacity - -
Shackle Total 3 3

14 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

Attachment: 3. Steel Structure Pipe Rack Drawing

15 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

Attachment: 4. Applicable Crane Load Chart


Table of Rated Lifting Capacity LoadChart Crane – 25 Ton
Crane data’s Plan Remark
1. Crane type and model Rough Terrain crane 1 unit
2. Crane capacity 25 ton Crane assembly
3. Crane condition 100 % Test load
4. Main boom length 23,5 meter Boom exit
6. Load line revving sling Full line Block pulley
7. Hook block capacity 25 ton Block crane
8. Working radius crane 9 meter Lifting plan
9. Lifting capacity crane 7.850 kg Loadchart crane
10. Load lifting 3600 kg Column structure
11. Crane accessoris 700 kg Extra Load
12. Total load lifting 4400 kg Total load
13. Safety factor crane 57,09% Crane Condition

Load Chart Crane – 25 Ton

16 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

Table of Rated Lifting Capacity Load Chart Crane – 50 Ton

Crane data’s Plan Remark

1. Crane type and model Rough Terrain crane 1 unit

2. Crane capacity 50 ton Crane assembly

3. Crane condition 100 % Test load

4. Main boom length 21,5 meter Boom exit

6. Load line revving sling Full line Block pulley

7. Hook block capacity 20 ton Block crane

8. Working radius crane 9 meter Lifting plan

9. Lifting capacity crane 11300 kg Loadchart crane

10. Load lifting 5000 kg Material structure

11. Crane accessoris 330 kg Extra Load

12. Total load lifting 5860 kg Total load

13. Safety factor crane 51,88 % Crane Condition

Load Chart Crane – 50 Ton

17 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

Attachment : 5. Method Chipping and Padding Plate Installation.

Chipping in 10 - 20 mm Chipping in 10-20 mm

A B

PAD Plate 6-8 mm


100 mm

25-35 mm

100 mm

18 of 19
Doc. No. : 26071-100-VSC-SSE4-2-00001

Job No. : 26071 Rev.001

Attachment : 6.Plot Plan.

19 of 19

You might also like