You are on page 1of 17

HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED

EPCC LSTK Contractor Owner PMC Owner


DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

OIL INDIA LIMITED

Project Name: - Construction of Field Gas Gathering


Station (FGGS) Package-3 BOP-Mechanical, Piping &
Field Instrumentation at Baghjan, Assam.

JOB PROCEDURE FOR STATIC


EQUIPMENT INSTALLATION

Revision Date Description Remarks


R-A 06.09.2023 Issued for Approval
EPCC LSTK Contractor OWNER / PMC
Prepared By: Checked By: Approved By: Checked By: Approved By:

Dhevendran.M
Sr.QA/QC
RCM PM
Engineer

1
HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED
EPCC LSTK Contractor Owner PMC Owner
DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

SL
DESCRIPTION Page No
.NO

1 INTRODUCTION 3

2 RESPONSIBILITIES 3

3 REFERENCE DOCUMENTS 3-4

4 GENERAL REQUIREMENTS 4-5

5 UNLOADING & TRANSPORTATION 5-6

6 CUSTODY OF EQUIPMENT 6

7 LIFTING MATERIAL 7

8 PREPARATION FOR INSTALLATION 7-9

9 INSTALLATION 9-10

INSPECTION,TESTING &
10 10
DOCUMENTATION

11 SAFETY 10

2
HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED
EPCC LSTK Contractor Owner PMC Owner
DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

1.0 INTRODUCTION

This project is for construction of Construction of Field Gas Gathering Station


(FGGS) Package 3 BOP-Mechanical, Piping & Field Instrumentation at FGGS
Baghjan, Assam.

PROJECT INFORMATION

 Client : M/s. Oil India Limited


 Client’s PMC : M/s. Jayathe Petrotech Engineers & Consultants
Pvt. Ltd
 LSTK Contractor : M/s. HAL Offshore Limited
 PO Date : 19th April 2022
 Duration : 27 Months

PURPOSE & SCOPE

This document is issued to establish a uniform procedure for erection and


alignment of static equipment’s at FGGS Project site

2.0 RESPONSIBILITY

2.1 RCM- MECHANICAL


RCM shall report to project manager to full fill the project specification
requirements; He shall be responsible for implementation of this procedure during
project execution; He shall be also responsible for providing adequate resources for
execution of work.

2.2 MECHANICAL ENGINEER

Primary responsibility of Mechanical engineer shall be verification of all the


materials confirming to the fabrication drawings / standard drawings; He shall be
responsible for preparing lifting plan, & surveillance of all mechanical activities
including lifting and installation of equipment’s, Transportation/Shifting of
equipment within the site, carrying out Alignment of static equipment’s and
keeping records

3.0 REFERENCE DOCUMENTS

 Approved Equipment plot plan.


3
HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED
EPCC LSTK Contractor Owner PMC Owner
DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

 Approved Equipment foundation drawing.


 Approved Piping drawing showing elevation of various nozzles.
 Approved Equipment data sheet.
 Approved Vendor’s drawing
 Equipment manufacturer’s recommendations
 IS Codes & ASME codes & specifications (Wherever applicable)

4.0 GENERAL REQUIREMENTS

All necessary handling equipment’s, tools, tackles and precision instruments


for carrying out the works as specified shall be in good condition; also all tools
and gauges for erection and alignment shall be made available at site with valid
calibration reports

Equipment manufacturer’s recommendations regarding preservation during


storage at site, layout drawings, GAD, nozzle orientation drawings, etc. shall
be strictly followed.

4.1 Precautions for Installation

4.1.1 Where equipment is roped for lifting, pads shall be applied on the corners,
finished surfaces, etc. of the equipment for preventing damage resulting
from wire ropes.

4.1.2 Construction equipment, machines, tools and measuring instruments to be


used in the works shall be thoroughly inspected and certified by competent
authority prior to use.
4.1.3 Where the use of fire is prohibited, flame-free tools and devices shall be
prepared.

4.1.4 When lifting up or down the equipment by the use of a sling, due care shall
be taken to its location and centre of gravity in order to avoid unbalancing of
the equipment. Sling points of the equipment, if specified by manufacturer,
shall be complied with. It shall be determined after careful examination and
shall be distinctly marked in order to avoid injuries to the workmen.
Erection scheme to be submitted to PMC for all Equipment (above 10 Mt)
erection for approval.

4.2 Special Crew


4
HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED
EPCC LSTK Contractor Owner PMC Owner
DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

4.2.1 During heavy equipment installation, a special crew shall be organized.


4.2.2 The crew shall comprise of a general supervisor, signal/flag man, hoist
operator, crane operator, rigger, safety supervisor, etc.
4.2.3 The function of each individual of the crew shall be clearly defined.

5. UNLOADING AND TRANSPORTATION

5.1 Unloading

5.1.1 For the heavy weight equipment, an unloading method procedure shall be
determined on investigating items, and an unloading plan shall be made out
prior to the work.

i) Size, weight and shape of the equipment.


ii) Unloading facilities of the jetty.
iii) Time of sunrise and sunset.
iv) Conditions of the ground at unloading point.

5.1.2 The ground at the unloading point, if it is not firm, shall be thoroughly
reinforced in order to prevent the equipment from overturning etc.
5.1.3 Prior to unloading, the orientation and position of the equipment after
unloading shall be confirmed in relation to the direction of installation.

5.2 Transportation

5.2.1 For the transportation of the heavy weight equipment after unloading, a
transportation method procedure shall be determined on investigating the
following terms, and transportation plan shall be made out prior to work
commencement.
i) Size, weight and shape of the equipment
ii) Maximum allowable loads for roads, bridges, etc. existing in
transportation route.
iii) Width, unevenness and crook of the transportation route.
iv) Buildings, aerial wrings, overhead girders electric poles, underground
facilities and buried objects etc. existing in the transportation routes.
v) Whether or not temporary road is necessary.

5.2.2 Where required proper reinforcements, removals or protections shall be


done to the roads, underground facilities and buried objects, or existing
structures around the transportation route to prevent them from damage.
5
HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED
EPCC LSTK Contractor Owner PMC Owner
DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

And such temporary measures shall be promptly restored to their original


conditions after the works have been completed.
5.2.3 In the field, the equipment shall be temporarily placed at the points shown
in the transportation plan.
5.2.4 Skids for the transporting and temporary placing shall be made suitable for
the equipment so as not to allow permanent distortion.

6. CUSTODY OF EQUIPMENT

6.1 Unpacking

6.1.1 Upon arrival of the equipment in the field, the number and external
appearance of packing shall be checked against the packing list.
6.1.2 After unpacking the specification of the equipment such dimensions and
weight, quantity shall be checked against the packing list, purchase order
and / or invoice. Whether or not there is anything defective in appearance
such as rest, flaw or distortion shall be checked.
6.1.3 Government certification stamp, if required, shall be confirmed.
6.1.4 Centre markings, orientation markings of centre of gravity and sling point
markings if used, shall be checked according to the drawings

6.2 Safekeeping

6.2.1 The safekeeping shall refer to the storage instructions given on the shipping
documents of each individual item. These instructions shall overrule the
general guidelines in this paragraph.
6.2.2 The place and method of safekeeping until the installation shall be
determined by taking the following items, into consideration.
i) Types of the equipment, parts accessories and spare parts, if any.
ii) Property of material used and finished surface.
iii) Period of storing (temporary placing) and weather conditions.
iv) Environmental conditions, such as whether or not dust, sand or soil,
corrosive gas etc. exits.

6.2.3 Cleaning, anti-corrosive treatment or sealing, if necessary, shall be made,


where inspection is required for the insides of the equipment such as
vessels, manhole covers shall be opened after taking necessary measures
such as confirmation of air supply.

6
HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED
EPCC LSTK Contractor Owner PMC Owner
DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

7. LIFTING MEHTOD

7.1 General

7.1.1 The following items shall be considered for the determination of a lifting
method and the erection of lifting equipment’s.

i) Size weight and shape of the equipment to be installed and the slinging
points.
ii) Space in installing location
iii) Space & ground condition of erection point of the lifting equipment.
iv) Building, structures, equipment, etc. existing nearby and whether or not
those can be used without damaging or overstressing the same.
v) Buried objects such as underground piping and cables, and open
trenches, existing in the place where the equipment is erected.
vi) Operating condition of existing plants facilities and equipment.
vii) Condition of roads as to whether or not they can be used.
viii) Existing lifting equipment and whether or not it can be utilized.
ix) Space of dismantling or taking out of the lifting equipment.
x) Performance & maintenance condition of the lifting equipment.

7.1.2 For the heavy weight equipment, the installation manual including
specification of the lifting equipment, routing & method for taking in of the
equipment from temporary place, the direction and sequence of installation,
etc. shall be made out before starting the works.
7.1.3 The rigging/Lifting plan/erection scheme for approval of heavy
equipment’s shall be submitted to OIL PMC before starting the works for
approval.

8. PREPARATION FOR INSTALLATION

8.1 Measuring Instruments & Tools.

All necessary tools such as Theodolite, Dumpy level, Master level etc. will be
made available at site. Proper calibration records for these will be maintained.

8.2 Foundation

8.2.1 Equipment foundation shall be checked for the following items :

i) Period of maturing of foundation concrete.


7
HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED
EPCC LSTK Contractor Owner PMC Owner
DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

ii) Dimension
iii) Position (centre marking) and height (level marking)
iv) Disorders in the foundation concrete, such as honeycombing.
v) No of bolts, bolt circle diameter, size of anchor bolts, and damage or rust
of threaded parts.

8.2.2 Treatment for the surface of the foundation, such as chipping and fitting,
shall be carried out as follows :

i) Foreign matters are to be completely removed & surface shall be


thoroughly cleaned.
ii) Portions which come in contact with liners are chipped and fitted to be in
line with the liners.
iii) Surface, if grouting is to be done after centering, is chipped and then
cleaned completely with compressed air, etc. so as to give good
adherence and avoid cracking, peeling-off, etc. of grouting mortar.

8.3 Liners / Packing Plates

8.3.1 Liners to be used shall be in general, made of carbon steel.


8.3.2 Liners shall be so arranged that the load of equipment is uniformly and
exactly distributed to the foundation within allowable load. In general, the
liners shall be placed as near as possible to both side of each anchor bolt.
8.3.3 In case where only flat liners are used for alignment, these flat liners shall
be piled in layers.
8.3.4 Oil & other foreign matters stuck on surface of liners shall be entirely
removed.

8.4 Equipment

8.4.1 Prior to the installation, the following checks of the equipment shall be
made

i) Appearance of equipment, such as absence of damage and rust.


ii) The number and appearance of auxiliaries.
iii) Size of the anchor bolts, damage and rust on the threaded parts.
iv) Orientation marking
v) Marking of centre of gravity/ centre line.

8.4.2 Oil and other foreign matters stuck on the surfaces of legs, bed, frame etc.
which will be in contact to grouting shall be entirely removed.
8
HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED
EPCC LSTK Contractor Owner PMC Owner
DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

9. INSTALLATION

9.1 Setting

9.1.1 Setting of the equipment on the foundation shall be performed as per


vendor’s recommendations.
9.1.2 Placing of the equipment shall be carried out as follows

i) Liners shall be set so that the top levels of these liners come slightly
lower than the specified installation height thus allowing later
adjustment.
ii) Equipment shall be lowered slowly with chain block, jacks, etc. keeping
it horizontal.
iii) In case of anchor box type, the anchor bolts shall be set to the legs of the
equipment after stabilization of the lowered equipment has been
obtained.
iv) All anchor bolts shall be tightened completely and uniformly.

9.1.3 Centering (or alignment) shall conform of engineering specification


corresponding to each equipment installation work, where specification
covers the requirement for diameter of vessels, columns etc.
9.1.4 Vertical vessels/columns/reactors shall be checked using appropriate
instruments for verticality. Tightening of anchor bolts shall be done
thereafter.

Where the liners are used in multilayers, they shall be intermittently welded
to each other after completion of centering (or alignment) of the equipment.

9.1.5 In Case of anchor box type, fixing of the anchor bolts shall be carried out
as follows :

i) Anchor bolts shall be set so that a few screw threads come out from the
nut.
ii) When mortar is being poured into the anchor boxes, all foreign matters
shall be removed, the mortar shall be poured with spading and
tamped by rod. Threaded parts shall be properly covered to prevent from
sticking to them.
iii) All anchor bolts shall be tightened completely and uniformly after
sufficient solidification of the mortar has been obtained.

9
HAL Offshore Limited JAYATHE PETROTECH OIL INDIA LIMITED
EPCC LSTK Contractor Owner PMC Owner
DOC. NO. -HAL/OIL/FGGS_BAGHJAN/PRO/ME-012 Rev-A

9.1.6 Tolerances for equipment after erection shall be as per approved drawing /
equipment Data sheet/ OEM recommendations

10. INSPECTION, TESTING & DOCUMENTATION :

Inspection, testing, Alignment and other records shall be carried out and
records shall be maintained as per following formats

Inspection Report for Flare Column, Chamber Assembly & Erection

HAL/OIL/FGGS_BAGHJAN/ME/FORMAT-28

Static Equipment Erection & Alignment Inspection Report

HAL/OIL/FGGS_BAGHJAN/ME/FORMAT-29

Equipment check list

HAL/OIL/FGGS_BAGHJAN/ME/FORMAT-30

11. SAFETY

Please refer attached Risk safety analysis for equipment Erection in


Annexure A

10
Jayathe Petrotech Engineers & Consultants Pvt
HAL Offshore Limited Oil India Limited
Ltd
LSTK Contractor OIL Project Management Consultant Owner
Construction of Field Gas Gathering Station (FGGS) Package-3 BOP-Mechanical, Piping & Field
PROJECT:
Instrumentation

LOCATION Baghjan,Tinsukia, Assam

REPORT NO: DATE :

EQUIPMENT CHECK LIST


EQUIPMENT NAME
EQUIPMENT TAG NO
DRAWING NO Rev
S. No. Description YES NA NO Remarks

1 Check for any visual damage to the equipment

2 Verify Equipment foundation/ support steel work has been released

3 Check for Temporary shipping items removed

4 Check for foundation level before mounting equipment etc.

5 Check for Concrete foundation chipped.

6 Check for equipment orientation and location.

7 Check for Correct bolting used for equipment

8 Check for Pre – grout alignment completed.

9 Check for Alignment within allowed tolerance

10 Check for Type of grout used

11 Check for Foundation bolts & jack used

12 Check for Client Asset numbers & Equipment Tag numbers verified

13 check for Piping Interfaces completed

14 check for Electrical terminations completed

15 check for Instrument termination/ hook ups completed

16 check for Preservation covers removed

17 Motor direction of operation confirmed

18 Check for Equipment Installed in accordance with GA / P& ID

19 All vendor installation activities completed and reports submitted

20 Equipment is clean and free from debris internally and externally

FOR HAL OFFSHORE LTD FOR OIL/PMC

NAME: NAME:

SIGN: SIGN:

DATE: DATE:
FORMAT NO.-HAL/OIL/FGGS_BAGHJAN/ME/FORMAT-30
HAL Offshore Limited Jayathe Petrotech Engineers & Consultants Pvt Ltd Oil India Limited
LSTK Contractor OIL Project Management Consultant Owner

STATIC EQUIPMENT ERECTION & ALIGNMENT INSPECTION REPORT


Project Construction of Field Gas Gathering Station (FGGS) Package-3 BOP-Mechanical, Piping & Field Instrumentation Report No.

Location Baghjan,Tinsukia, Assam Date

DRAWING NO Rev

Nozzle elevation Nozzle Orientation Vertical Reading of vessel Inspection Clearance By


Sl. No. Equipment Description Base elevation Nozzle No Remarks
As per Drg Actual As per Drg Actual North East HAL OIL / PMC

PREPARED BY FOR HAL FOR OIL / PMC

NAME

DESIGNATION

SIGNATURE

DATE

HAL/OIL/FGGS_BAGHJAN/ME/FORMAT-29
HAL Offshore Limited Jayathe Petrotech Engineers & Consultants Pvt Ltd Oil India Limited

PROJECT: Construction of Field Gas Gathering Station (FGGS) Package-3 BOP-Mechanical, Piping & Field Instrumentation

LOCATION Baghjan,Tinsukia, Assam CLIENT Oil India Limited

LSTK CONTRACTOR HAL Offshore Limited REPORT NO-

PMC Jayathe Petrotech Engineers & Consultants Pvt Ltd DATE

INSPECTION REPORT FOR FLARE COLUMN , CHAMBER ASSEMBLY & ERECTION


DRAWING NO. DESCRIPTION PAGE NO.

ELEVATION ( ±mm) PLUMBNESS(±mm) INSPECTION CLEARANCE


MARK NO./ASSEMBLY Bottom of base plate BY
QTY DESCRIPTION/
Sl.No. MARK/ REMARKS
NOS. LENGTH AS PER
ACTUAL TOLERANCE NORTH EAST HAL OIL PMC
DRAWING

10

11

12

13

FOR HAL FOR OIL/PMC

NAME

SIGNATURE

DATE

HAL/OIL/FGGS_BAGHJAN/ME/FORMAT-28
EPC Contractor: HAL OFFSHORE LTD EPMC:JPEC CLIENT: OIL INDIA LIMITED
RISK ASSESSMENT FOR EQUIPMENT ERECTION
Document Number : HAL/FGGS_BAGHJAN/HSE/RA-03;Rev-A Annexure-A
Risk Rating Risk Rating
SL NO. Hazard Persons at Risk Control Measure to be Taken
S P R S P R
1 HEALTH

1.1 General ill health All 3 2 M Pre employment medical check 4 4 L

First Aid Kit at work area & tie -up with local hospital with contact
1.2 Non -availabillity of medical services All 4 2 M 4 4 L
number.

Correct PPE (high ankle safety shoe)& awareness of habitats of


1.3 Snake bites/scorpion sting All 2 4 M 4 4 L
reptiles e.g hole, under rock, under stored material.

1.4 Sand Storm All 3 2 M Full coverall with safety glasses and shelter room. 4 4 L

1.5 Heat Stress All 3 2 M Drink plenty of water or fluids & take proper rest. 4 4 L

1.6 Water borne diseases All 3 2 M Testing of drinking water as per WHO standard 5 4 L

1.7 High noise All 4 2 M Use ear plug/muff, Monitor noise level. 4 4 L

Use of proper PPE e.g Full coverall, safety shoe, rubber hand
1.8 Chemical Exposure Painter 3 3 M 4 4 L
gloves, nose mask.

Water sprinkling, dust mask, cartridge mask, Dust storm- stop


1.9 Dust All 4 2 M 4 4 L
work, Evacuate.

2 VEHICLE & EQUIPMENT

Inspection of vehicle & euipment on daily basis. Schedule


2.1 Failure of vehicle & equipment All 1 2 H 4 4 L
preventative maintenance
Traffic flowplan, escort vehicle(for wide load), banks man &
2.2 Movement of traffic All 1 3 H signage. 4 4 L
Speed limit to be strictly followed.
2.3 Improper driving/ operation All 1 3 H Assam driving license, induction, defensive driving training. 4 4 L
EPC Contractor: HAL OFFSHORE LTD EPMC:JPEC CLIENT: OIL INDIA LIMITED
RISK ASSESSMENT FOR EQUIPMENT ERECTION
Document Number : HAL/FGGS_BAGHJAN/HSE/RA-03;Rev-A Annexure-A
3 CRANE/HYDRA OPERATION(loading , unloading,Lifting)

Daily pre use inspection.


Operators, riggers Colour coding.
3.1 Unfit crane (may collapsed) 1 3 H 5 4 L
& near by workers Scheduled preventative maintenance.
Certification by TPI approved Govt of ORISSA
Experience operator with orissa operating license.
Induction & craft training for operator.
Riggers & near by
3.2 Unsafe operation 1 3 H Swing area to be cordoned off. 5 4 L
workers
Over load & over hoist limit switch.
SLI to be fixed
Work as per approved lifting plan.
Operators, riggers Qualified & experienced rigger.
3.3 Improper lifting 1 3 H Use of proper sling & shackles. 5 4 L
& near by workers
Use of tag line.

3.4 Adverse weather crane may toppled All 1 4 H Weather condition to be monitored. 5 4 L

4 LIFTING TOOLS & TACKLES


Periodic checklist to be maintained;Damaged Tools
tackles,lifting items shall be discarded
4.1 Damaged tools tackles Lifting crew 4 3 H 5 4 L
EPC Contractor: HAL OFFSHORE LTD EPMC:JPEC CLIENT: OIL INDIA LIMITED
RISK ASSESSMENT FOR EQUIPMENT ERECTION
Document Number : HAL/FGGS_BAGHJAN/HSE/RA-03;Rev-A Annexure-A
5 WORK AT HEIGHT
Trained & experienced scaffolder to be deployed.
Electrical Sound scaffold with proper platform, guard rails, toe board &
5.1 Improper working platform 3 2 M 5 4 L
crew,erection crew access ladder.
Scaffold tag system to be followed.
Access ladder.
Rigger, scaffolder, Use of full body double lanyard safety harness for working
5.2 Fall from height 2 3 M 5 4 L
erection crew beyond 1.8m from ground level.
Static lifeline to be installed if required.
6 USE OF POWER TOOLS

Certified & recent colour coded tools to be used.


Electrical Crew, Guards for rotating parts.
6.1 Unsafe tools 3 3 M 5 4 L
erection crew Use PPE i.e. face shield, hand gloves, goggle, helmet, safety
shoe etc.
Proper rated power cable through MBC & ELCB to be used.
Civil crew, electrical Proper socket & plug top to be ensured.
6.2 Electrocution 2 3 M 5 4 L
crew, erection crew Proper cable management.

7 ELECTRICAL NETWORKING
Qualified electrician.
Proper hand tools & PPEs.
7.1 Electrocution Electrician 2 3 M 4 4 L
Proper earthing to the system.
Lock out & Tag out system.
8 MANUAL HANDLING
When lifting heavy objects- bend knees, grasp load firmly,
keep head straight, lift by straightening knee do not bend
back.
8.1 Back strain or other injury Material handler 3 2 M Use wheel burrow here possible. If long object(pipe etc.) are 4 4 L
to be moved ensure adequate nos. of persons assist. Use of
rope for lifting of materials along with pulley arrangement.

Use of hand gloves.


8.2 Hand injury Material handler 3 2 M Proper stacking of materials. 5 4 L
EPC Contractor: HAL OFFSHORE LTD EPMC:JPEC CLIENT: OIL INDIA LIMITED
RISK ASSESSMENT FOR EQUIPMENT ERECTION
Document Number : HAL/FGGS_BAGHJAN/HSE/RA-03;Rev-A Annexure-A
9 WELDING, GRINDING & CUTTING ACTIVITY
Face shield/eye protector for welder, grinder & gas cutter.
Wheel guard for grinding m/c.
9.1 Flying particles All 4 2 M Leather hand gloves & apron. 5 4 L
Safety goggles for all, woking nearby.

Store flammable materials away from hot work zone.


9.2 Fire All 3 3 M Flash back arrestor for oxygen & DA line. 5 4 L
Fire extinguisher shall be kept near by.

9.3 Explosion All 3 3 M 5 4 L

10 HAZARDOUS MATERIALS
Store all chemicals & oil in a designated area with secondary
containment.
10.1 Environment pollution All 3 3 M Avoid spillage during application of paint. 4 4 L
Use oil tray for maintenance of vessel & equipment Display
MSDS
Segregate all hazardous & non hazardous waste as per
10.2
Waste segregation & Disposal All 4 2 M specification and disposal it as per local regulations. 4 4 L

Note: S- Severity, P- Potentiality, R- Risk ; Risk Rating H: 1-4; M:5-11; L:12-25