1. PURPOSE
The purpose of this procedure is to Re-calibration of the PSV-039. Related work will be on the
PTTLNG Jetty Development and LNG Receiving Terminal Project to be built at Map Ta Phut
Indutrial Estate, Rayong, Thailand.
2. DEFINITIONS
2.1 COMPANY” means PTTLNG Company Limited, its successors and assignees.
2.2 CONTRACTOR” means the GS Consortium that GS Engineering & Construction Corp. leads
under Process and Utility piping, for the PTTLNG Jetty Development and LNG
Receiving Terminal Project.
2.3 “SUBCONTRACTOR” means any company, firms or person with whom CONTRACTOR
enters into a subcontract.
2.4 “SITE” means the areas where the WORK shall be performed as indicated in the PROJECT
SPECIFICATION situated at Map Ta Phut Industrial Estate, Rayong Province, Thailand.
3. REFERENCES
3.1 Drawings
4. PERSONNEL RESPONSIBILITIES
4.2 Field QA/QC Manager (FQM) is responsible for assuring the construction activities
and his personnel are responsible for inspection and reviewing the witness/holding points
PMC
Method Statement Statement Doc. No.: 7S92-06011-CO-TP-541
Rev. :0
for GRE Pipe Modification Date : 28 Dec. 2012
(ORV-D) Page : 3 of 4
and the activities to be monitored as surveillance. Quality control personnel give the
organizational freedom to identify and prevent quality problems.
4.3 Mechanical Superintendent is responsible for all orders and directions issued by the
Construction Manager. He is responsible for supervising his designated work, controlling
activities for Supervisors and Foremen, assignment of major equipment, ensuring works
executed safely, subcontractors execute works in safe manner and monitoring the work of
Subcontractors.
4.4 Safety Manager is responsible for monitoring and observing the safe execution of the work,
the safety work plan, compliance with project SHE requirements and procedures, works
conducted as mentioned in approved WMS / JSA and work permit.
5. WORK PROCEDURES
5.1 Isolation
5.1.1 Preparation blind isolation, tools, support standing and etc.
5.1.2 Sea water pump "0500-P-001A/B/C" De-Energize power supply confirm with PTT
operation.
5.1.3 MOV061 Valve check close position and confirm with PTT operation.
5.1.4 MOV061 Confirm De-Energize power supply.
5.1.5 Disconnect power cable and electric cable.
5.1.6 Water drain in the line to empty.
5.1.7 GRE Pipe line cutting.
5.1.8 Loosen bolt flange joint connecting remove out and pipe spool take out.
5.1.9 Blind flange install and tightening.
5.1.10 Clear tools and do cleaning.
6.1 All safety precautions shall be taken care as required as per JSA.
6.2 Testing area will be barricaded and warning signs for pressure testing shall be displayed.
6.3 All testing equipments and instruments shall be inspected prior to testing commencing.
6.4 During high pressure testing, if required, nearby area work will be suspended till test is
complete.
6.5 GSC supervisors and safety shall ensure all required work permits approved and JSA .
6.6 All testing personnel shall be provided with and use required PPE i.e. safety helmet,
safety glasses (clear & dark), safety shoes/boots, hearing protection, gloves, safety harness
for working at height etc. additional PPE shall be supplied as required.
6.7 Disciplinary action will be taken against personnel committing safety violations, action
taken will depend on the severity of the violation.
7. ATTACHMENTS
1.2 Speeding 1.2.1 Follow traffic rules and signs GSC Mechanical S/V GSC SHE S/V
1.3 Truck load Exceeding 1.3.1 Observe and follow regulatory GSC Mechanical S/V GSC SHE S/V
allowable units truck load limits
1.4 Equipment inspection 1.4.1 Prepare and provide necessary GSC Mechanical S/V GSC SHE S/V
equipment certificate prior moving to
the site ( Kor-Por 2, Insurance,
certificate and other official document
i.e. truck registration, driving license,
Certificate of lifting operation trained)
2. Lifting pipes and 2.1 Sling, shackle, hook, 2.1.1 Crane must pass an inspection GSC Mechanical S/V GSC SHE S/V
Lowering pipes from truck to damaged causing pipes by TPI with certificate and gets
lay down area, either at area fallen down or crane boom approve by PTTLNG inspector with
nearby temporary parking broken color coded. Slings, hooks, shackles
lot at gate #2 at must also pass inspection by TPI and
Subcontractor site office PTTLNG inspector prior to allow to be
used at site
Page 2 of 9
2.1.2 Lifting tackle shall be inspected
by daily basis prior to be used
2.2 Crane tipped over 2.2.1 Ensure that the location for
crane sitting must be firm. If not, Steel
plates must be placed for support the
crane
2.3 Moving loads hit to 2.3.1 Barricade shall be installed GSC Mechanical S/V GSC SHE S/V
workers around crane radius while working
Page 3 of 9
JOB SAFETY ANALYSIS ( JSA )
SEQUENCE OF ACTIVITY POTENTIAL HAZARDS HAZARD CONTROLS RESPONSIBLE BY CHECKED BY
STEPS
3. Remove pipe from lay 3.1 A lot of pieces of the 3.1.1 Only necessary amount of pipe, GSC Mechanical S/V GSC SHE S/V
down area to workplace pipes are storage at site which can be laid down and connected
causing obstruction to for each day’s work, will be moved to
traffic and create unsafe workplace
condition
3.2 Obstruction to traffic 3.2.1 Avoid blocking the entire traffic GSC Mechanical S/V GSC SHE S/V
during lifting pipes into route. Incase this can not be avoided,
excavated area an advance communication to other
personnel in the affected area must be
informed. Sign reading road closed
ahead and flagman must be provided
during pipes offloading
Page 4 of 9
worker fainted or out to the opening end where a
breathing difficulty due watchman is standing by to pull out the
to inhaling excessive workers in case of emergency
chemical odor, etc.
5. Cutting and welding / 5.1 Personal injury / 5.1.1 Supervisor & Worker must ensure GSC Mechanical S/V GSC SHE S/V
PWHT carbon steel pipe health that the RPM of cutting disc is matching
(pipe rack & ground level) Body from with grinder RPM
broken cutting / grinding
disc 5.1.2 Grinders must have handle and
Dust inhalation safety guard fitted
from grinding / cutting /
welding PWHT 5.1.3 Correct discs used for cutting &
Burn from grinding works
welding / PWHT
Fall from height 5.1.4 Damaged discs must be changed
& old disc kept in containment box
Page 5 of 9
5.1.7 Welding habitats shall be provided
were possible to protect others from
welding flash / glare and for cutting
operations
Page 6 of 9
5.3.5 Welding blanket used to stop
welding splatter drooping to ground
level
Page 7 of 9
JOB SAFETY ANALYSIS ( JSA )
SEQUENCE OF ACTIVITY SEQUENCE OF SEQUENCE OF ACTIVITY STEPS SEQUENCE OF SEQUENCE OF
STEPS ACTIVITY STEPS ACTIVITY STEPS ACTIVITY STEPS
6 Modification or Adjust the 6.1 Personal injury / 6.1.1. All hot work locations shall have GSC Mechanical S/V GSC SHE S/V
rubber ailment fire extinguisher
(Hot & Cold work)
Fire / explosion 6.1.2 All oxy/acetylene equipment shall
be leak tested daily, cylinders
Electrical equipment and contained outside CS area, hoses
cables complete not joined or spliced to prevent
leakage, hoses inspected for damage,
flash back arrestors fitted on torch and
cylinder gauges, cylinder pressure
gauges in good condition
Page 8 of 9
6.1.8 Appropriate PPE issued and used
for hot work activity
Page 9 of 9