Untitled
Untitled
DOCUMENT INFORMATION
The following required information is minimum requirement which need to be updated
each time the document is changed.
Creation by : Mr.Nguyen Huu Phuong
Review Frequency : When new revision issue
File Name :TF1_2Q92_100021_A_Welding Control Procedure
List of Qualified Approvers : Project Manager
Locations of Controlled Copies :
Master Document ☐CV ☐CO ☐CM ☐CE ☐DC
☐EE ☐EM ☐ES ☐FT ☐FF
☐HR ☐IE ☐IF ☐IT ☐MP
☐MR ☐MS ☐PE ☐PL ☐PC
☐PM ☒QM
Copied Document ☒CV ☒CO ☒CM ☒CE ☒DC
☒EE ☒EM ☒ES ☒FT ☒FF
(E-file) ☒HR ☒IE ☒IF ☒IT ☒MP
☒MR ☒MS ☒PE ☒PL ☒PC
☒PM ☒QM
Management of Changes : ☐ Internal (MOC No.)
: ☐ External (Project Correspondence No.)
: ☒ New Issue
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 3 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
REVISION LOG
Date Revised Detail
Rev.
(dd/mm/yyyy) Item Page Article Description
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 4 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
INDEX
1. PURPOSE ........................................................................................................................... 6
2. SCOPE ................................................................................................................................ 6
3. REFERENCES ..................................................................................................................... 6
4. DEFINITIONS .................................................................................................................... 7
5. PROCEDURE ..................................................................................................................... 8
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 5 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
7. RECORD...........................................................................................................................19
8. APPENDIX .......................................................................................................................19
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 6 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
1. PURPOSE
This procedure is to describe the general requirements for the control of welding
activities to ensure all of production welds that are in good quality and satisfied the
requirements of project specification, application rules/Codes/Standards.
2. SCOPE
The scope of this procedure covers all stages of work before welding, which include
selection of WPS, welder qualification, welding machine maintenance, material
identification, welding surveillance during welding, welding sequence and inspection
after welding, visual inspection, control of welding status and records/reports filling.
3. REFERENCES
API Std 650(Latest edition) Welded Steel Tanks for Oil Storage
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 7 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
4. DEFINITIONS
DWG: Drawing
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 8 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5. PROCEDURE
PREPARATION
- WPS Qualification
- Welder Qualification
- Equipment Calibration
- Welding Consumable Handling
BEFORE WELDING
- Material Identification
- Fit-Up Inspection
- Qualified WPS to be applied
- Qualified Welder to be employed
- Welding consumable to be used, etc.
DURING WELDING
AFTER WELDING
- Visual inspection
- PWHT (if any)
- NDT
- Weld Repair
- Record/Reports Filling and Maintain
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 9 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.3.2 If additional WPS is required, the WPS shall be qualified in accordance with
ASME VIII Div. 1/Div.2 for spherical tank, ASME B31.3/ B31.1 for piping,
API650 for cylindrical tank, AWS D1.1 for steel structure, ASME IX and
project specification.
5.3.4 The proposal WPS shall be submitted to PPC/LSP for review and approval
before commencement of qualification test.
5.3.5 Upon approval of the proposal WPS, welding procedures qualification test
shall be carried out in the presence PPC/LSP Representative. PPC/LSPshall
be informed before the testing. Third Party may also wish to witness, or in
absence.
5.3.6 The test piece shall be visually inspected and non-destructive tested in
accordance with project specification, applicable code and standard. The
acceptable test piece shall be sent to mechanical testing in an independent
Third party. PPC/LSP shall be informed before the testing and reserve the
right to witness the testing.
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 10 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.3.8 The Welding Engineer shall issue and update register of all approved WPS’s
applicable to the work to the relevant departments i.e. QA/QC, production,
Engineering, etc, for information.
5.4.2 Those welders/ operators that need to be qualified shall undergo qualification
test as per ASME VIII, AWS D11,ASME B31.3/ B31.1, or ASME IX
requirements for tank, steel structure and piping respectively.
5.4.3 Subcontractor/ vendor shall inform PPC/LSP prior to any welder qualification
test. PPC/LSP welding inspector shall monitor the welders during the
qualification. Third Party may also witness.
5.4.4 The final acceptance of the welders and welding operator qualification shall
be by PPC/LSP.
5.5.2 The Welding Engineer shall develop and maintain a record of welder
performance and submit to PPC on weekly basics.
5.5.3 Subcontractor/ Vendor shall control the failure rate identified by radiography
for any welder shall not exceed 2% of the welds radiographed. If overall
failure rate exceeds 2% of the welds radiographed Subcontractor/ Vendor
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 11 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
shall stop all production welds until the cause of the failures has been
identified and rectified.
The project welder repair rate report shall be issued weekly for PPC checking
and certify.
5.6.1 Prior to all fabrication work, the welding machines andequipments shall be
checked and made good and safe for its purpose.
5.6.2 Periodical checking and maintenance work are essential to the safety,
reliability and accuracy of the machines.
5.6.3 Calibration of all welding machines for the project shall be conducted before
the start of fabrication work and to be witnessed by subcontractor/ vendor QC
inspector. Calibrated certificate shall be valid for 01 year or recommendation
from manufacture.
5.7.1 All material shall be inspected in accordance with latest approved AFC/shop
drawing, mill certificates and cutting plan to ensure correct material as
specification, dimension, cutting profile and piece mark and free from any
surface defects.
5.8. FIT-UP
5.8.1 Subcontractor/ vendor supervisor shall submit fit-up inspection request to PPC
QC inspector for arrangement time before checking.
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 12 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.8.3 All joints shall be checked in conformance to the shop drawings and welding
procedure specification.
5.8.5 Design and tolerances of weld groove shall be in accordance with the
approved WPS. However, in general, the groove shall be beveled to give an
included angle of 700 ÷ 800 for single Vee or double Vee, and 350÷ 400 for
single bevel. The root opening and the root face shall be complied with
approved WPS. If the root opening is larger than maximum specified,
buttering of the joint is required. Request for weld repair and buttering shall
be submitted to PPC approval. In any case, the thickness of the weld deposit
on each side of the joint not exceed 9.5 mm and the maximum gap 19 mm,
the buttered area shall be ground to desired profile, visual and NDT (if
required) prior to fit-up .
5.8.6 Trimming tubular braces in-situ for closed root openings is not acceptable
without specific approval by PPC/LSP.
5.8.7 Tack weld shall only be done by qualified welders and be performed with the
same qualified welding procedure, as that will be used for fabrication welds.
Consumables used for tacking shall be the same as per the qualified WPS.
Preheat for tack welds shall be followed on approved WPS.
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 13 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.8.8 Tack weld for structural joints shall minimum of 50mm (2 in.) length where
practical, and tack weld for piping joints shall be ≤25mm (1in.) length.
Subcontractor/ vendor shall propose and demonstrate an acceptable
alternate to PPC. Tack weld shall be sufficient and equally space to prevent
the tack weld from cracking. These tack welds shall be cleaned by grinding
before actual welding commences.
5.8.9 For fit-up of piping, steel structure, tank, the internal and external transition
shall be in accordance to the AFC drawing and project specifications, code
and standard applied and verified by PPC QC Inspector.
ii) The root gap in fillet welds shall not exceed 1.0mm and shall only
exceed 0.5mm intermittently.
iv) Weld reinforcement shall blend smoothly with the parent metal with no
signs of overlap.
ii) Internal misalignment of pipe-work shall not exceed 15% of the pipe wall
thickness up to a maximum of 1.5 mm and 3.0 mm for external surface.
iii) The individual weld layer thickness for all processes shall not exceed 3/8
inch (9.5 mm) for materials less than 1-1/4 inch (32 mm) thick, or 1/2 inch
(13 mm) for greater material thickness.
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 14 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.8.13 Surface to be welded shall be cleaned to bright metal for a distance of not
less than 25.4 mm from the edges of weld groove and all surface shall be
free from oil, grease, water, loose scale, paint or any foreign material.
5.8.14 Temporary welds for fabrication aids shall not be made in high-stress areas.
If unavoidable, these welds shall be subject to the same welding and
material requirements as other structural welds. These welds shall minimum
of 50mm (2 in.) length. Preheat for temporary welds shall be followed on the
applicable WPS. These fabrication aids/temporary attachments shall be
produced from material of the same type as being welded. Temporary
attachments/fabrication aids for piping is not permitted.
5.8.15 All temporary attachments shall be cut from a good condition plate and shall
match the adjoining members in term of weld ability. All temporary
attachment shall be removed by grinder or thermal cutting to minimum of
03mm from the surface of the material and subsequently ground flush with
the surface. After grinding, the area shall be checked by MT/PT.
5.8.17 Run-on and run-off tabs shall be used for all welds at the plates end
locations, and at beam splices and terminations. These tabs shall be
produced from material of the same type as being welded.
5.9.1 Where shrinkage and distortion is likely to affect the adequacy of the
member of piping, tank, steel structure, welding sequences shall be
developed to control distortion, warping, creeping and the build-up of
excessive internal stresses in the piping, tank, steel structure and shall be
submitted to PPC for approval before the weld activity commence.
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 15 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.9.2 The approved welding sequence shall be briefed to the welders and displayed
prominently at the working area.
5.9.3 Welding Engineer or supervisor shall supervise the welding of the assembly to
ensure the planed sequences are followed.
i) WPS to be applied
iv) Tack weld, temporary attachments and spacers used in the assembly of
components
5.9.5 Whenever practical, two welders are required to weld a joint from both sides
simultaneously for welding of pipes or tubular with diameter greater than 12
inches. For welding of pipes or tubular with diameter greater than 20 inches,
two or more welders are required to weld simultaneously.
5.9.6 Avoid welding at both ends of the component because this shall cause high
stress in the component due to weld metal shrinkage when cooling. The high
stress can cause distortion of component or crack in the weld joint.
5.9.7 Special attention is required when welding a large panel of tubular, beam, or
plates to minimize distortion. Welding of the panel shall start from the centre
and out to the perimeter.
5.10.1 All approved WPS and list of welder/ operator shall be posted at site/ shop
for welding supervisor and welder’s reference. Welders shall adhere to the
parameters as specified in the related WPS. The welding supervisor shall
ensure that the welders follow the parameters in the WPS.
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 16 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.10.2 Welding consumables to be used for welding shall be checked for the
correct classification, type and size as per approved WPS. It must be dry
and free from foreign material such as grease, oil, water and paint.
Consumables must be stored in heated quivers at all times.
5.10.4 Welders/ operators shall be checked and his identification number shall be
written with permanent marker adjacent to the joints. The welding
supervisor must select good welders for welding critical joints.
5.10.5 The welders/ operators shall be briefed on the applicable WPS requirements
i.e. amperage, voltage, travel speed, type and size of consumables,
preheating, etc.
5.10.6 Welding sequences shall be available at work area for reference (if any).
5.10.8 Shelter shall be provided at all times to give protection to the weld areas
from wind, rain and moisture.
5.10.9 Before welding the weld joint shall be cleaned free from rust, dusty, scale,
oil, paint, etc.
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 17 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.11.2 All arcing or re-arcing of electrodes must be done in the weld groove and
not on the area adjacent to the weld. Arc strikes outside the weld groove
area are not allowed. Arc strikes outside the weld groove area shall be
removed by grinding or removal and replacement of the section affected by
the arc strike. All arc strike areas outside the weld area shall be subject to
MT/PT inspection. All indications of cracking shall be subject to grinding and
re-inspection to insure complete removal.
5.11.3 The maximum weave width for SMAW, GTAW, SAW etc. shall comply with
approved WPS.
5.11.4 Welding start and stop should be staggered within 50mm of each weld pass
for each weld layer. This is essential in order to avoid unnecessary defects
and poor weld profiles, which may require dressing and re-welding.
5.11.6 All gouged areas after surface dressing shall be tested by MT/PT (if
required) to check for surface cracks, porosity etc.
5.11.7 Care must be taken when laying down welding tongs to ensure that the
electrode end does not come in contact with the plate surface. All arc strikes
shall be subjected to repair or rejection at the discretion of PPC/LSP.
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 18 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.12.1 Visual inspection acceptance criteria shall follow ASME VIII Div.1 or Div.2,
ASME B31.3/ B31.1, API 650, AWS D1.1 which is applicable.
5.12.3 The following inspection shall be carried out after a welded component is
completed:
x) NDT Inspection
For effective inspection, it is essential that the weld and adjacent surface is
cleaned from slag, spatters, mill scales and oxides.
5.13.2 Repair to correct the weld defect shall be made using the approved WPS
and be carried out by a qualified welder.
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 19 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
5.13.3 The repair areas shall be re-examined by the same NDT method with which
the defect was originally detected. The number of repair attempts shall be
limited to no more than two (02) times.
6. SPECIAL REQUIREMENT
6.1 All weld joints to be subsequently covered by an abutting member weld shall
be accepted by NDT in accordance with Project specification prior to fit-up
or welding of the covering member. All plate butt welds that will be
subsequently covered by an abutting weld shall be ground smooth and
subject to MT on the attachment surface for a minimum distance of 50mm
(2 in.) either side of the intended attachment.
6.2 Method statement may require for welding some critical items as ring plate,
lifting padeyes, and repair for crack/fracture defects….
7. RECORD
a. Welding summary report, inc. welder ID, date welded, WPS, visual acceptance of
fit up and weld.
All reports shall be verified by PPC/LSP, Third Party representative and must be
kept by subcontractor/ vendor for Final Documentation.
8. APPENDIX
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 20 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 21 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 22 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 23 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
Confidential: This document is confidential and must not be copied or reproduced except with the express permission of Long Son Petrochemicals Co., Ltd.
PETROCHEMICAL COMPLEX IN SOUTH OF VIETNAM
Tổ hợp hóa dầu Miền Nam Việt Nam
PACKAGE A2
Long Son Petrochemicals Co., Ltd TANK FARM AND INTERCONNECTING PIPELINES
Contract No. : LSP-CA-147 EPC Project No. LSA22018
Welding Control Procedure Page 24 / 24
Doc.No. : TF1-2Q92-100021 Rev.A EPC Doc No. : - Rev.A
Tank/piping/steel structure:
Confidential: This document is confidential and must not be copied or reproduced except with the express
permission of Long Son Petrochemicals Co., Ltd.