DOCUMENT TITLE:
DOCUMENT NUMBER:
KAK-ANA-CFS-CMS-0004 rev.A01
Doc. No:
METHOD STATEMENT FOR Sub Doc No: KAK-ANA-CFS-CMS-0004
LIFTING AND INSTALLATION WORKS Page Date: 21.07.2018
1 of 6 Rev: A01
TABLE OF CONTENTS:
1.0 SCOPE
The work covered by this method statement covers delivery, lifting, unloading and installation of
pre-casted foundations and equipments required on site.
3.1 Crane
3.2 Boom Truck
3.3 Delivery Trucks
3.4 Trailers
7.6 Cranes and boom truck third party certifications shall be available with the equipments
7.7 Riggers, flagman and safety officers shall be vigilant to ensure that all lifting activity is
performed in safe manner not to damage any other facilities and plant equipments.
7.8 Crane and boom truck outrigger positions should be provided with wooden or steel pads to
avoid punching through ground, pavements or road.
7.9 Barricades shall be provided within the lifting radius and no personnel will walk or stay below
lifted load or crane booms.
7.10 All lifting accessories such as shackles, slings, chains and lifting beams when used are in good
working condition.
7.11 Ensure all lifting and rigging activities postponed during presence of heavy winds and
unfavorable weather conditions.