Professional Documents
Culture Documents
IMPROVEMENT PROPOSALS
Consultancy Services for Project Management Phase-I including preparation Draft Feasibility Report
of Detailed Project Report for up gradation of Junction with NH-27 near
Doraji- Jamkandorna, Kalavad Jamnagar section of NH-927D in the state of
Gujarat to two/ four lane with paved shoulder configuration (Package no -
NH/IAHE/18)
TABLE OF CONTENTS
CHAPTER - 7........................................................................................................................7-1
IMPROVEMENT PROPOSALS........................................................................................7-1
7.1 GENERAL............................................................................................................................7-1
7.2 STUDY OF EXISTING ALIGNMENTS..............................................................................7-1
7.2.1 Right of Way............................................................................................................7-1
7.2.5.1 Terrain..............................................................................................7-4
7.2.5.2 Land Use...........................................................................................7-4
7.2.6 Existing Kilometer, Design Chainage and Coordinate..............................................7-4
7.2.9 Utilities...................................................................................................................7-11
LIST OF TABLE
LIST OF FIGURE
Figure 7.1: Existing Pavement Codition.................................................................................7-4
Figure 7.2: HT Pylon and HT Line at Km 26+000..........................................................7-11
Figure 7.3: IOCL Crude Oil Pipe Line Near Km 10+000...............................................7-12
Figure 7.4: Cairn’s Crude Oil and Gas Pipe Line Near Km 12+800.............................7-12
Figure 7.5: TCS-1 for Concentric Widening at Rural Area with 2 Lane Paved Shoulder
..............................................................................................................................................7-16
Figure 7.6: TCS-1A for Eccentric Widening (Left/Right) at Rural Area with 2 Lane
Paved Shoulder...................................................................................................................7-17
Figure 7.7: TCS-2 for Re-construction/Raising at Rural Area with 2 Lane Paved
Shoulder...............................................................................................................................7-17
Figure 7.8: TCS-3 for New Construction at Rural Area with 2 Lane Paved Shoulder7-18
Figure 7.9: TCS-4 for New Construction Eccentrically for Bypasses/Realignment.....7-18
Figure 7.10: TCS-5 for Urban Area with 2 Lane with Paved Shoulder........................7-19
Figure 7.11: TCS-6 for Widening at Urban Area with 4 Lane.......................................7-19
Figure 7.12: TCS-6A for Re-construction at Urban Area with 4 Lane.........................7-20
Figure 7.13: TCS-7 for New Construction at Urban Area with 4 Lane........................7-20
Figure 7.14: TCS-8 for Approach with Both Side Slip Road..........................................7-21
Figure 7.15: TCS-8A for Approach without Slip Road...................................................7-21
Figure 7.16: TCS-9 for Elevated Structure Part of Kalavad Town...............................7-22
Figure 7.17: TCS-10 for Structure Part of Flyover/VUP/CUP.......................................7-22
Figure 7.18: Jamkandorna Bypass Options.....................................................................7-28
Figure 7.19: Kalavad Bypass options................................................................................7-30
Figure 7.20: Haripar Realignment Options.....................................................................7-32
Figure 7.21: Khandera Bypass options.............................................................................7-34
Figure 7.22: Vijarkhi Bypass options................................................................................7-36
Figure 7.23: Town Plan Map of Kalavad.........................................................................7-66
7.1 GENERAL
This chapter deals with brief description of the project highlighting the salient features of the
project road. The concept of widening of the road and proposed bypasses/ realignment is
discussed. The project proposals like Bus Bays, Truck Lay Byes, Toll Plaza, VUP, PUP/
CUP, Flyover etc. with their locations will also be discussed.
7.2 STUDY OF EXISTING ALIGNMENTS
The project road starts from km 107+500 of SH-26 (old) at the Junction of NH-27 where
grade separation by VUP is exist with SH-26 and NH-27. The project end point exists at km
4+700 of SH-26 and Junction with SH-25. The existing length as per km stone difference is
102+800 km.
The existing road alignment passes through 2 district of the Gujarat state namely; Rajkot and
Jamnagar districts. Out of total length 72.200 km in Jamnagar district and remaining length
35/300 km is in the Rajkot district. The district boundaries of the both the district is at km
72/200.
The Project study corridor starts at junction of NH-27 (km 96/300) and NH-927D (SH-26)
Km 107/500 in Dhoraji and ends at Junction of SH-25 km 85/900 (Km 4+700 of SH-26) in
Jamnagar via Jamkandorna, Kalavad, Haripar, Vijarkhi villages etc.
The existing Carriageway width varying from intermediate lanes to four lanes with passing
through congested built-up area. The project corridor comprises four lane from Km 45/200 to
Km 48/800 and from Km 89/000 to Km 91/000 of total length 5.6 Km and remaining
intermediate to two lane of total length 96.7 Km. The existing alignment having deficient
curve radius including in approaches of bridges.
7.2.1 Right of Way
As per the details obtained from the State PWD, Rajkot and Site road inventory, the Right of
Way varies from 24m to 30m. The summary of existing ROW along the Project stretch is
given in Table 7.1.
Table 7.1: Detail of Existing ROW
S. Number of
Deficiencies
No. Location
1 16 Reverse curve with insufficient curve length
2 67 Radius less than Absolute minimum required
3 17 Radius less than Desirable minimum required
The existing pavement surface is flexible type of length 102.500 Km with earthen shoulders
except 300m length on CC pavement at Four lane stretch of Jamkandorna. Paved shoulders
are absent in the complete stretches.
Pavement condition is generally good in the stretch between Jamnagar and Kalavad where as
the pavement condition is fair to poor in the section between Kalavad and Dhoraji which is
only due to inadequate maintenance. During the site visit following defects were generally
noted:
2. Patching
3. Raveling
4. Potholes
5. Edge breaking
6. Depressed shoulders
The surface is poor especially in those stretches where periodic maintenance by the way of
renewal has not been done for quite some time.
The pavement, in about 60 km of length, is with fair to poor condition. The side drainage is
generally available along the project stretch.
The road surface is black topped with SDBC in some portion and with Premix carpet in rest
of section. At most of the locations the last overlay was done with SDBC while in some
stretches BM was laid under PMC.
The Following graph indicating the pavement condition in percentage with respective of
distresses were noted.
Type Width of
S. Existin Type of of Cross
Side Cross Road Leading To
No. g Km Junction Surfac Road
e (m)
107+25
1 RHS T WBM 5 To Power House
5
103+01
2 RHS T BT 3.9 Village
3
101+92
3 RHS Y BT 3 Amar Kot
0
100+18
4 LHS T BT 3 Taravada
0
5 98+160 RHS T BT 3.6 Issuriya
6 98+070 LHS T BT 3.7 Raaide
7 94+555 RHS T BT 4 Dudhiyavadar
8 91+580 LHS Y BT 3.7 Anchavad
Pipardi (LHS)
9 89+316 Both X BT 13
Kandorna (RHS)
10 87+785 RHS T CC 5.2 Vidya Nagar
11 87+720 RHS T CC 3.5 Bai Mukund
7.2.9 Utilities
Utilities like electric line, OFC, Gas/oil Pipe line, High Tension Line etc are running along/
across the project road. The High tension line has been crossing at 12 location along project
highway listed in Table 7.8. The crude oil/gas pipe line has been crossing at existing Km
10+000 and Km 12+800.
Table 7.8: High Tension Line Crossing
S.
Existing Km S. No. Existing Km
No.
1 5+400 2 7+500
3 10+800 4 26+000
Figure 7.3: IOCL Crude Oil Pipe Line Near Figure 7.4: Cairn’s Crude Oil and Gas Pipe
Km 10+000 Line Near Km 12+800
The Kilometer stones and 200m has been found almost all along the project highway. The
Kilometer stone at Km 48.000 and Km 89.000 are missing. The few boundary stones are
missing along the project highway. The Kilometers stones are marked as SH-26 (State
Highways) and updating of Kilometers stone has not been done as per NH-927D.
The existing earthen drainage has been found at following location listed in Table 7.9 along
project road. There is no line drain along project highway.
33 13+885 RHS -
As far as possible the existing centre line have been followed for the design of horizontal alignment. Existing carriageway is about 5.50m to
7.0m in width is widened as per provisions of 2-lane manual i.e. IRC:SP:73-2015. The typical arrangements of highway component in rural area,
built-up area and in approaches of grade separators are given below:
Figure 7.5: TCS-1 for Concentric Widening at Rural Area with 2 Lane Paved Shoulder
Figure 7.6: TCS-1A for Eccentric Widening (Left/Right) at Rural Area with 2 Lane Paved Shoulder
Figure 7.7: TCS-2 for Re-construction/Raising at Rural Area with 2 Lane Paved Shoulder
Figure 7.8: TCS-3 for New Construction at Rural Area with 2 Lane Paved Shoulder
Figure 7.10: TCS-5 for Urban Area with 2 Lane with Paved Shoulder
Figure 7.13: TCS-7 for New Construction at Urban Area with 4 Lane
Figure 7.14: TCS-8 for Approach with Both Side Slip Road
TSC Schedule
The indicative TCS schedule are given in table below:
Table 7.11: Typical Cross Section Schedule
Lengt Lengt
S. Existing Km Design Chainage TCS
h h
No.
From To (m) From To (m)
107+02
1 107+470 450 0 450 450 TCS-1
0
105+97
2 107+020 1050 450 1500 1050 TCS-2
0
105+35
3 105+970 620 1500 2100 600 TCS-1
0
105+25
4 105+350 100 2100 2200 100 TCS-1 A
0
105+02
5 105+250 230 2200 2450 250 TCS-1
0
104+91
6 105+020 110 2450 2550 100 TCS-1 A
0
102+04
7 104+910 2870 2550 5400 2850 TCS-1
0
100+73
8 102+040 1310 5400 6700 1300 TCS-3
0
100+03
9 100+730 700 6700 7400 700 TCS-1
0
10 100+030 97+900 2130 7400 9525 2125 TCS-2
11 97+900 91+790 6110 9525 15642 6117 TCS-1
TCS-1 to TCS-
12 91+790 91+670 120 15642 15762 120
8
13 91+670 91+276 394 15762 16156 394 TCS-8
14 91+276 91+264 12 16156 16168 12 TCS-10
15 91+264 90+825 439 16168 16562 394 TCS-8
TCS-8 to TCS-
16 90+825 90+705 120 16562 16682 120
6
17 90+705 90+310 395 16682 17100 418 TCS-6
18 90+310 90+040 270 17100 17350 250 TCS-7
19 90+040 89+800 240 17350 17590 240 TCS-6
20 89+800 89+200 600 17590 18190 600 TCS-6A
21 89+200 88+535 665 18190 18850 660 TCS-6
TCS-6 to TCS-
22 88+535 88+415 120 18850 18970 120
1
23 88+415 87+525 890 18970 19850 880 TCS-1
24 87+525 87+370 155 19850 20000 150 TCS-1 A
Lengt Lengt
S. Existing Km Design Chainage TCS
h h
No.
From To (m) From To (m)
25 87+370 87+200 170 20000 20150 150 TCS-1
26 87+200 87+050 150 20150 20300 150 TCS-3
27 87+050 86+800 250 20300 20550 250 TCS-1
28 86+800 86+700 100 20550 20650 100 TCS-1 A
29 86+700 86+450 250 20650 20900 250 TCS-3
30 86+450 85+525 925 20900 21825 925 TCS-1
31 85+525 85+075 450 21825 22275 450 TCS-2
32 85+075 84+160 915 22275 23200 925 TCS-1
33 84+160 83+960 200 23200 23400 200 TCS-1 A
34 83+960 82+810 1150 23400 24550 1150 TCS-1
35 82+810 82+350 460 24550 25010 460 TCS-2
36 82+350 82+040 310 25010 25600 590 TCS-1
37 82+040 81+140 900 25600 26170 570 TCS-3
38 81+140 80+885 255 26170 26425 255 TCS-2
39 80+885 80+520 365 26425 26780 355 TCS-3
40 80+520 79+800 720 26780 27500 720 TCS-2
41 79+800 78+700 1100 27500 28600 1100 TCS-1
42 78+700 78+000 700 28600 29100 500 TCS-1
43 78+000 77+325 675 29100 29760 660 TCS-5
44 77+325 76+655 670 29760 30430 670 TCS-1
45 76+655 76+345 310 30430 30740 310 TCS-8A
46 76+345 76+338 7 30740 30747 7 TCS-10
47 76+338 75+985 353 30747 31100 353 TCS-8A
48 75+980 75+780 200 31100 31300 200 TCS-3
49 75+780 75+250 530 31300 31920 620 TCS-1
50 75+250 75+150 100 31920 32020 100 TCS-1 A
51 75+150 74+775 375 32020 32500 480 TCS-1
52 74+775 74+675 100 32500 32600 100 TCS-1 A
53 74+675 74+485 190 32600 32770 170 TCS-1
54 74+485 74+215 270 32770 33035 265 Toll Plaza
55 74+215 73+390 825 33035 33850 815 TCS-1
56 73+390 73+235 155 33850 34000 150 TCS-3
57 73+235 71+085 2150 34000 36000 2000 TCS-1
58 71+085 70+865 220 36000 36220 220 TCS-1 A
59 70+865 70+450 415 36220 36625 405 TCS-1
60 70+450 70+240 210 36625 36825 200 TCS-1 A
Lengt Lengt
S. Existing Km Design Chainage TCS
h h
No.
From To (m) From To (m)
61 70+240 70+125 115 36825 36940 115 TCS-1
62 70+125 69+935 190 36940 37125 185 TCS-3
63 69+935 68+720 1215 37125 38350 1225 TCS-1
64 68+720 68+265 455 38350 38800 450 TCS-3
65 68+265 67+125 1140 38800 39950 1150 TCS-1
66 67+125 66+900 225 39950 40170 220 TCS-3
67 66+900 65+980 920 40170 41100 930 TCS-1
68 65+980 65+730 250 41100 41350 250 TCS-3
69 65+730 65+260 470 41350 41820 470 TCS-1
70 65+260 64+810 450 41820 42270 450 TCS-2
71 64+810 64+450 360 42270 42640 370 TCS-1
72 64+450 63+900 550 42640 43160 520 TCS-3
73 63+900 63+710 190 43160 43350 190 TCS-2
74 63+710 63+275 435 43350 43800 450 TCS-3
75 63+275 62+975 300 43800 44100 300 TCS-2
76 62+975 62+540 435 44100 44540 440 TCS-1
77 62+540 62+380 160 44540 44700 160 TCS-1 A
78 62+380 57+030 5350 44700 50050 5350 TCS-1
79 57+030 56+330 700 50050 50750 700 TCS-2
80 56+330 56+150 180 50750 51000 250 TCS-1
81 56+150 55+980 170 51000 51150 150 TCS-3
82 55+980 52+930 3050 51150 54200 3050 TCS-2
83 52+930 52+190 740 54200 54950 750 TCS-1
84 52+190 51+960 230 54950 55170 220 TCS-3
85 51+960 51+630 330 55170 55500 330 TCS-1
86 51+630 51+405 225 55500 55720 220 TCS-3
87 51+405 50+930 475 55720 56200 480 TCS-1
88 50+930 50+780 150 56200 56350 150 TCS-1 A
89 50+780 48+875 1905 56350 58280 1930 TCS-1
TCS-1 to TCS-
90 48+875 48+755 120 58280 58400 120
6
91 48+755 46+790 1965 58400 60320 1920 TCS-6
92 60320 60403 83 TCS-7
93 46+790 46+170 620 60403 60596 193 TCS-9
94 60596 60700 104 TCS-7
95 46+170 45+300 870 60700 61550 850 TCS-6
96 45+300 45+180 120 61550 61670 120 TCS-6 to TCS-
Lengt Lengt
S. Existing Km Design Chainage TCS
h h
No.
From To (m) From To (m)
1
97 45+180 44+840 340 61670 62020 350 TCS-1
98 44+840 44+715 125 62020 62140 120 TCS-1 A
99 44+715 44+285 430 62140 62570 430 TCS-1
100 44+285 44+155 130 62570 62700 130 TCS-1 A
101 44+155 42+855 1300 62700 64000 1300 TCS-2
102 42+855 41+205 1650 64000 65640 1640 TCS-1
103 41+205 41+085 120 65640 65760 120 TCS-1 A
104 41+085 40+725 360 65760 66120 360 TCS-1
105 40+725 40+540 185 66120 66300 180 TCS-3
106 40+540 39+095 1445 66300 67770 1470 TCS-1
107 39+095 38+530 565 67770 68365 595 TCS-3
108 38+530 37+960 570 68365 68900 535 TCS-4
109 37+960 37+180 780 68900 69680 780 TCS-1
110 37+180 36+570 610 69680 70290 610 TCS-2
111 36+570 36+470 100 70290 70400 110 TCS-1
112 36+470 34+470 2000 70400 71850 1450 TCS-4
113 34+470 32+780 1690 71850 73550 1700 TCS-1
114 32+780 32+570 210 73550 73750 200 TCS-3
115 32+570 31+760 810 73750 74570 820 TCS-1
116 31+760 31+520 240 74570 74800 230 TCS-3
117 31+520 31+275 245 74800 75050 250 TCS-1
118 31+275 31+100 175 75050 75225 175 TCS-3
119 31+100 29+425 1675 75225 76900 1675 TCS-1
120 29+425 29+210 215 76900 77100 200 TCS-3
121 29+210 29+060 150 77100 77250 150 TCS-1
122 29+060 28+560 500 77250 77710 460 TCS-3
123 28+560 28+420 140 77710 77850 140 TCS-1
124 28+420 28+290 130 77850 77980 130 TCS-1 A
125 28+290 27+575 715 77980 78700 720 TCS-1
126 27+575 27+410 165 78700 78860 160 TCS-1 A
127 27+410 26+500 910 78860 79800 940 TCS-1
128 26+500 26+280 220 79800 80000 200 TCS-3
129 26+280 22+835 3445 80000 83350 3350 TCS-1
130 22+835 22+650 185 83350 83530 180 TCS-3
131 22+650 21+960 690 83530 84220 690 TCS-1
132 21+960 21+450 510 84220 84730 510 TCS-2
Lengt Lengt
S. Existing Km Design Chainage TCS
h h
No.
From To (m) From To (m)
133 21+450 21+000 450 84730 85200 470 TCS-1
134 21+000 20+845 155 85200 85350 150 TCS-3
135 20+845 20+595 250 85350 85600 250 TCS-1
136 20+595 19+985 610 85600 86210 610 TCS-2
137 19+985 18+395 1590 86210 87800 1590 TCS-1
138 18+395 18+050 345 87800 88100 300 TCS-2
139 18+050 17+775 275 88100 88360 260 TCS-3
140 17+775 17+335 440 88360 88800 440 TCS-2
141 17+335 16+645 690 88800 89500 700 TCS-1
142 16+645 16+120 525 89500 90000 500 TCS-3
143 16+120 15+725 395 90000 90400 400 TCS-1
144 15+725 15+415 310 90400 90700 300 TCS-3
145 15+415 15+215 200 90700 90900 200 TCS-1
146 15+215 14+870 345 90900 91250 350 TCS-1 A
147 14+870 14+500 370 91250 91620 370 TCS-1 A
148 14+500 13+150 1350 91620 92875 1255 TCS-4
149 13+150 13+000 150 92875 93030 155 TCS-1
150 13+000 12+250 750 93030 93700 670 TCS-4
151 12+250 11+550 700 93700 94400 700 TCS-3
152 11+550 11+150 400 94400 94800 400 TCS-1
153 11+150 11+000 150 94800 94950 150 TCS-1 A
154 11+000 9+560 1440 94950 96345 1395 TCS-1
155 9+560 9+305 255 96345 96610 265 Toll Plaza
156 9+305 8+840 465 96610 97110 500 TCS-2
157 8+840 6+990 1850 97110 98950 1840 TCS-1
158 6+990 6+790 200 98950 99140 190 TCS-1 A
159 6+790 6+440 350 99140 99480 340 TCS-2
160 6+440 6+165 275 99480 99755 275 TCS-5
10020
161 6+165 5+760 405 99755 445 TCS-5
0
10052
162 5+760 5+440 320 100200 320 TCS-1
0
10065
163 5+440 5+310 130 100520 130 TCS-1 A
0
10068
164 5+310 5+280 185 100650 30 TCS-1
0
10080 TCS-1 to TCS-
165 5+280 5+160 120 100680 120
0 8
Lengt Lengt
S. Existing Km Design Chainage TCS
h h
No.
From To (m) From To (m)
10128
166 5+160 4+677 483 100800 483 TCS-8
3
10134
167 4+677 4+617 60 101283 60 TCS-10
3
10180
168 4+617 4+160 457 101343 457 TCS-8
0
After detail study some of the locations require realignments/ bypasses. Jamkandorna &
Kalavad, Haripar, Khandhera, Vijarkhi towns where realignments/ bypasses options were
explored. The detail comparison of these alternatives are described as below.
The following locations where bypasses and realignments may be required are as below:
7.4.1 Jamkandorna Bypass
The existing highway section from Km 88+550 to Km 90+640 passing through Jamkandorna
town of Rajkot district. This town is a taluka head quarter. Four lane section having deficient
geometry exist for 1930m length in the town. Three alternative including two bypass options
has been explored to improve the geometry and safety consideration in built-up area. Based
on the detail techno-economic comparison of various alternatives option-2 with using
existing road by improving one deficient curve radius in 285m length will be best suitable
option. This option requires minimum land acquisition and construction cost. However due to
urban area, bypass option with option-1, may be suitable but considering traffic study and
substantial land acquisition in agriculture land option-1 is not recommonded.
Alternative option-3 i.e. bypass from RHS, is also having a merit that it also connects SH-23
(Rajkot) & Shriji Nagar road, but it has substantial land acquisition & more length (5.950
km) with high cost will not be recommended considering low traffic demand.
The highway section between existing Km 39+200 to 37+700 of project road having deficient
geometry & sharp curve in approaches of submersible minor bridge. Three alternatives has
been explored for the section. As per the comparative statements, all three options are more
or less all are similar in features but option-1 with improved geometry, less R&R problem to
avoid habitations/building structures, safety consideration due to more distance from
habitation, is recommended.
The land acquisition requirement for option-2 & option-3 are 8.37 Ha & 10.6 Ha
respectively. Option-1 with bypass having less length 1.750 km and less land acquisition area
has also been explored. The option-1 will avoid existing road section along Khandera
habitation and less land acquisition of 7.74 ha with 100km/hr speed & more standard
geometry will be best alternative.
comprises 1320m for widening and balance new construction will be most feasible option
with approximate 9.3 Ha land acquisition. However option-2 with less length will require less
land acquisition of approximate 8.76Ha but it will require cutting of adjoining hill which is
situated near to dam location. The option-2 will be economical considering cost criteria but
on techno-economical ground with minimal cost option-1 will be recommended. Option-3 is
based on standards design with 100 kmph design speed but not economical considering land
acquisition & R&R as well as more length.
7.5 GEOMETRIC IMPROVEMENT AND PROPOSALS
The horizontal curves which are deficient either in radius or in transition lengths and curve
length have been improved. The vertical curves which are deficient in curve length and
gradients have also been improved. The improvement of geometrics is necessary on National
Highways for safety and comfort of road users, even for low traffic volumes.
7.5.1 Alignment Improvement Alternatives
Improvement of existing alignment has been done in following ways which will have
significant beneficial impact in terms of
Minimizing Displacement
Avoid adverse impacts of the crowded areas along the project stretch
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
Existing Radius is less than
1 106+330 1.132 215 250 Improved for Design Speed of 80 kmph
absolute minimum required
The length of curve not as per The proper radius has been given to accommodate
2 105+600 1.850 requirement of deflection 475 700 sufficient length of curve and transition as per
curve requirement of deflection curve
The length of curve not as per The proper radius has been given to accommodate
3 105+300 2.157 requirement of deflection 270 500 sufficient length of curve and transition as per
curve requirement of deflection curve
Length of curve and transition The proper radius has been given to accommodate
4 104+970 2.492 330 500
are insufficient sufficient length of curve and transition
Existing Radius is less than
5 101+834 5.608 180 250 The realignment on right side has been proposed
absolute minimum required
due to new construction of major bridge with
Sharp reverse curve in the
6 101+490 5.942 278 250 reverse curve for the design speed of 80 kmph
approach of Major Bridge
7 100+825 6.603 Broken Back curve and 190 400 The realignment on right side has been proposed
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
due to new construction of major bridge with
Existing Radius is less than
improvement of curve radius for the design speed
absolute minimum required
of 100 kmph
Reverse curve and 300 and The reverse has been improved by providing single
8 99+215 8.214 1000
insufficient length of curve 3100 curve with sufficient length of curve and transition
Existing Radius is less than
9 97+944 9.467 230 250 Improved for Design Speed of 80 kmph
absolute minimum required
The Broken back curve has been eliminated by
Brocken Back curve and 1400 and
10 92+353 15.073 2000 providing single curve with sufficient length of
insufficient length of curve 235
curve for design speed of 100 kmph
The Broken back curve has been eliminated by
Brocken Back curve and 824 and
11 92+152 15.275 2000 providing single curve with sufficient length of
insufficient length of curve 310
curve for design speed of 100 kmph
The Broken back curve has been eliminated by
Brocken Back curve and 750 and
12 91+935 15.493 1200 providing single curve with sufficient length of
insufficient length of curve 710
curve for design speed of 100 kmph
The setting of curve with
The proper radius has been given to accommodate
13 92+760 15.672 transition is not proper and 378 500
sufficient length of curve
not sufficient in length
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
Brocken Back curve and
214 & The Broken back curve eliminated by providing
14 91+275 16.114 Existing Radius is less than 275
251 single curve with Design Speed of 80 kmph
absolute minimum required
Deficient Existing Curve Improved for Minimum Design Speed of 65 kmph
15 90+155 17.232 55 150
Radius in Jamkandorna Town in the buildup area of Jamkandorna
Existing Radius is less than
16 88+865 18.518 178 800 Improved for Design Speed of 100 kmph
absolute minimum required
555,100, The proper single radius of curve has been given to
Series of reverse curve and
17 87+970 19.594 555 and 400 eliminate reverse curve and Brocken back curve
Brocken back curve
810 with sufficient length of curve and transition
Existing Radius is less than Existing Design speed have been Improved to 100
18 87+425 19.936 215 400
absolute minimum required kmph speed
Existing Radius is less than
19 87+130 20.230 120 250 Improved for Design Speed of 80 kmph
absolute minimum required
Reverse curves and Existing
20.585 & 145m & 250m &
20 86+775 Radius is less than absolute Improved the for Design Speed of 80 kmph
20.818 190m 250m
minimum required
Length of curve and transition The curve has been improved with proper length of
21 85+630 21.736 400 500
are insufficient curve and transition
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
The Brocken back curve has been eliminated by
Brocken back curve and 122 and
22 84+775 22.786 700 providing single curve with sufficient length of
insufficient length of curve 650
curve and transition
The Brocken back curve has been eliminated by
Brocken back curve and 170 and
23 83+360 23.398 700 providing single curve with sufficient length of
insufficient length of curve 226
curve and transition
Existing Radius is less than
Existing Design speed is about 80 kmph have been
Desirable minimum required
24 83+430 23.930 355 600 Improved to 100 kmph speed with sufficient length
and insufficient length of
of curve
curve and transition
Reverse curves and length of 1150 and 2000 and The reverse curve has been improved with proper
25 82+960 24.400
curve is insufficient 13000 2000 length of curve
26 81+940 25.700 125
Re- Existing alignment contains
Improved with Single Curve and Realignment in
27 alignmen 25.800 sharp reverse curve and 70 550
500m length
t Brocken back curve
28 81+155 26.146 950
Existing Radius is less than
29 80+735 26.558 115 250 Improved for Design Speed of 80 kmph
absolute minimum required
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
Reverse curve with next
The sufficient length of curve and transition has
30 80+180 27.119 curve And length of curve is 589 400
been provided
insufficient
Reverse curve with previous
Existing Design speed is about 80 kmph has been
curve and existing Radius is
31 79+957 27.343 250 500 Improved to 100 kmph speed with proper curve
less than Desirable minimum
length
required
The Brocken back curve has been eliminated by
Brocken back curve and 380 and
32 79+660 27.622 2250 providing single curve with sufficient length of
insufficient length of curve 560
curve
The Brocken back curve has been eliminated by
Brocken back curve and 330 and
33 79+330 27.953 2450 providing single curve with sufficient length of
insufficient length of curve 400
curve
Length of curve is insufficient
The sufficient length of curve has been provided as
34 78+985 28.300 as per requirement of 1650 5300
per deflection angle
deflection angle
Existing Radius is less than Improved for Design Speed of 50 kmph in the
35 77+910 29.193 120 150
absolute minimum required buildup area of Satudad Village
36 77+565 29.524 Existing Radius is less than 75 150 Improved for Design Speed of 50 kmph in the
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
absolute minimum required buildup area of Satudad Village with some R&R
Length of curve is insufficient
The sufficient length of curve has been provided as
37 77+422 29.665 as per requirement of 500 800
per deflection angle
deflection angle
Broken back curve and
175 and The Broken back curve eliminated by providing
38 77+005 30.079 Existing Radius is less than 360
197 single curve with Design Speed of 80 kmph
minimum requires
Broken back curve and 960 and The Broken back curve eliminated by providing
39 76+610 30.462 500
insufficient curve length 1485 single curve with sufficient curve length
Existing Radius is less than
40 76+316 30.766 213 250 Improved for Design Speed of 80 kmph
absolute minimum required
Existing Radius is less than
41 75+860 31.222 145 250 Improved for Design Speed of 80 kmph
absolute minimum required
Existing Radius is less than
42 75+280 31.986 200 500 Improved for Design Speed of 100 kmph
absolute minimum required
Broken back curve and 400 and The Broken back curve eliminated by providing
43 74+714 32.552 600
insufficient curve length 930 single curve with sufficient curve length
Broken back curve and 140 and The Broken back curve eliminated by providing
44 73+985 33.267 700
insufficient curve length 720 single curve with sufficient curve length
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
Length of curve and transition The curve has been improved with proper length of
45 73+640 33.611 340 700
are insufficient. curve and transition
Existing Radius is less than
46 73+310 33.933 155 250 Improved for Design Speed of 80 kmph
absolute minimum required
Existing Radius is less than
47 72+444 34.810 240 360 Improved for Design Speed of 100 kmph
absolute minimum required
Length of curve and transition The curve has been improved with proper length of
48 72+170 35.086 690 700
are insufficient. curve and transition
Existing Radius is less than
49 70+960 36.122 230 250 Improved for Design Speed of 80 kmph
absolute minimum required
Existing Radius is less than
50 70+345 36.720 220 250 Improved for Design Speed of 80 kmph
absolute minimum required
Broken back curves and in The Broken back curve eliminated by providing
150 and
51 69+980 37.081 sufficient length of curve and 300 single curve with proper length of curve and
365
transition transition
Broken back curves and
345 and The Broken back curve eliminated by providing
52 68+475 38.591 Existing Radius is less than 400
280 single curve with Design Speed of 100 kmph
Desirable minimum required
53 67+000 40.068 Insufficient length of curve 260 400 The proper radius has been given to accommodate
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
and transition because of
sufficient length of curve and transition
reverse curve with next curve
Existing Radius is less than Existing Design speed is about 80 kmph has been
54 65+840 41.240 225 400
Desirable minimum required Improved to 100 kmph speed
Existing Radius is less than
55 65+162 41.926 100 250 Improved for Design Speed of 80 kmph
absolute minimum required
Existing Radius is less than Existing Design speed is about 80 kmph has been
56 64+300 42.771 150 400
Desirable minimum required Improved to 100 kmph speed
Existing Radius is less than
57 64+015 43.059 140 400 Improved for Design Speed of 100 kmph
absolute minimum required
Existing Radius is less than
58 63+450 43.630 150 400 Improved for Design Speed of 100 kmph
absolute minimum required
Existing Radius is less than
59 56+524 50.597 230 250 Improved for Design Speed of 80 kmph
absolute minimum required
Existing Radius is less than
60 56+050 51.071 160 250 Improved for Design Speed of 80 kmph
absolute minimum required
Length of curve and transition The curve has been improved with proper length of
61 55+813 51.315 585 600
are insufficient. curve and transition
62 54+510 52.622 Existing Radius is less than 178 250 Improved for Design Speed of 80 kmph
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
absolute minimum required
Existing Radius is less than
Existing Design speed is about 80 kmph have been
Desirable minimum required
63 53+569 53.557 316 500 Improved to 100 kmph speed with sufficient length
and Length of curve and
of curve and transition
transition are insufficient.
Existing Radius is less than
64 52+062 55.070 145 250 Improved for Design Speed of 80 kmph
absolute minimum required
Existing Radius is less than
65 51+526 55.611 177 250 Improved for Design Speed of 80 kmph
absolute minimum required
Length of curve and transition The curve has been improved with proper length of
66 50+900 56.242 485 500
are insufficient. curve and transition
Existing Radius is less than
67 49+978 57.167 240 300 Improved for Design Speed of 80 kmph
absolute minimum required
There is no requirement of
There is no requirement of curve because deflection
68 49+308 57.842 curve because deflection 3400 2000
angle is less than 10
angle is less than 10
Existing Radius is less than
69 49+061 58.089 225 300 Improved for Design Speed of 80 kmph
absolute minimum required
70 46+533 60.330 Existing alignment contains 165 - Improved for design speed of 65 kmph with
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
71 46+513 60.350 20 -
series of sharp curve, reverse
72 46+463 60.400 50 -
curve and Brocken back provision of small realignment
Re-
curve
73 alignmen 60.500 32 -
t
Proposed curve on The curve with Design Speed of 80 kmph has been
74 46+282 60.581 - 250
realignment provided
Existing Radius is less than
Existing Design speed is about 80 kmph have been
Desirable minimum required
75 44+771 62.084 340 500 Improved to 100 kmph speed with sufficient length
and Length of curve and
of curve and transition
transition are insufficient.
Existing Radius is less than
76 44+230 62.625 220 500 Improved for Design Speed of 100 kmph
absolute minimum required
Length of curve and transition The sufficient length of curve and transition has
77 43+747 63.108 495 800
are insufficient. been provided
Length of curve and transition The curve has been improved with proper length of
78 43+188 63.678 385 500
are insufficient. curve and transition
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
Length of curve and transition The sufficient length of curve and transition has
79 42+825 64.042 450 800
are insufficient. been provided
Length of curve and transition The curve has been improved with proper length of
80 42+562 64.305 430 500
are insufficient. curve and transition
Reverse curve with 870 and The reverse curve eliminated by providing single
81 41+629 65.219 2000
insufficient length of curve. 6450 curve with sufficient length of curve
Existing Radius is less than
Existing Design speed is about 80 kmph have been
Desirable minimum required
82 41+153 65.695 297 450 Improved to 100 kmph speed with sufficient length
and Length of curve and
of curve and transition
transition are insufficient.
Existing Radius is less than
83 40+644 66.217 179 400 Improved for Design Speed of 100 kmph
absolute minimum required
Length of curve and transition The sufficient length of curve and transition has
84 40+258 66.603 485 600
are insufficient. been provided
85 39+065 67.800 Existing alignment having 400 - Realignment have been proposed for minimum
86 38+965 67.900 series of sharp reverse curve 385 - design speed of 80 kmph
87 38+768 68.100 and Brocken back curve in 201 -
88 38+668 68.200 habitation of Haripar village 161 -
89 38+518 68.350 and in approaches of Major 116 -
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
Existing Radius is less than
101 32+710 73.623 168 250 Improved for Design Speed of 80 kmph
absolute minimum required
Existing Radius is less than
102 31+634 74.689 118 250 Improved for Design Speed of 80 kmph
absolute minimum required
Existing Radius is less than
103 31+185 75.139 175 400 Improved for Design Speed of 100 kmph
absolute minimum required
Length of curve and transition The curve has been improved with proper length of
104 30+424 75.901 390 600
are insufficient curve and transition
Existing Radius is less than
105 29+326 76.988 117 250 Improved for Design Speed of 80 kmph
absolute minimum required
106 29+015 77.300 217 -
Existing alignment contains
107 28+872 77.400 360 -
series of sharp curve, reverse Improved with Single Curve for design speed of
190 &
108 28+672 77.600 curve and Brocken back - 100 kmph
360
curve
109 28+570 77.700 360 -
Existing Radius is less than Existing Design speed have been Improved to 80
110 26+415 79.901 111 400
absolute minimum required kmph speed
111 25+990 80.382 Length of curve and transition 540 360 The sufficient length of curve and transition has
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
are insufficient. been provided
Existing Radius is less than
Desirable minimum required Existing radius have been improved to
112 25+265 80.992 330 360
and inadequate transition accommodate transition curve for 80 Kmph
length
Length of curve is
The curve has been improved as per requirement of
113 24+293 81.898 insufficient for a existing 1000 3000
deflection angle
deflection angle
Existing Radius is less than
114 22+743 83.443 230 300 Improved for Design Speed of 80 kmph
absolute minimum required
The curve has been improved with proper length of
Length of curve and transition
115 22+485 83.925 260 300 curve and transition as required for absolute
are insufficient
minimum speed of 80 kmph.
The Broken back curve eliminated by providing
Broken back curve and length 560 and
116 21+375 84.812 250 single curve and sufficient transition curve has
of transition is insufficient 320
provided with Design Speed of 80 kmph
Broken back curve and
182 and The Broken back curve eliminated by providing
117 20+950 85.240 Existing Radius is less than 250
155 single curve with Design Speed of 80 kmph
absolute minimum required
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
Broken Back curve in 450 and Broken Back curve has been improved with single
118 19+980 86.200 1000
existing alignment 6500 curve radius
Existing Radius is less than Existing Design speed have been Improved to 80
119 18+625 87.525 225 250
absolute minimum required kmph speed
Existing Radius is less than
120 17+925 88.224 110 250 Improved for Design Speed of 80 kmph
absolute minimum required
The curve has been improved to avoid the broken
Length of curve and transition
121 17+410 88.737 325 275 back with previous curve by giving proper length of
are insufficient.
curve and transition
Broken back curve and
183 and The Broken back curve eliminated by providing
122 16+370 89.752 Existing Radius is less than 285
169 single curve with Design Speed of 80 kmph
absolute minimum required
123 14+320 91.800 Series of sharp curve 335 - Improved by proposing realignment
124 14+000 92.100 including broken back curve 95 -
125 13+895 92.200 and reverse curve near 40 -
Re- Vijarkhi Village and Vijarkhi
126 alignmen 92.650 dam 24 -
t
127 13+230 92.800 59 -
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
HIP
Existing
S. Existing Design Proposed
Deficiency Curve Remark
No. KM Chainag Radius
Radius
e
are insufficient as per existing curve and transition as per requirement of
deflection angle deflection angle
Length of curve is not
The curve has been improved with proper length of
136 10+032 95.899 sufficient as per existing 1050 2000
curve as per requirement of deflection angle
deflection angle
Length of curve and transition The curve has been improved with proper length of
137 7+600 98.339 455 550
is not sufficient curve and transition
Existing Radius is less than Existing Design speed is about 80 kmph have been
138 6+895 99.042 230 450
Desirable minimum required Improved to 100 kmph speed
Existing Radius is less than
139 6+525 99.412 159 250 Improved for Design Speed of 80 kmph
absolute minimum required
Small Reverse curve
(Undulating Alignment) with 250 and The sufficient length of curve has been provided by
140 5+265 100.671 5000
insufficient length of curve as 300 eliminating reverse curve by providing single curve
per deflection angle
Broken back curve and
270 & The Broken back curve eliminated by providing
141 5+025 100.906 Existing Radius is less than 500
270 single curve with Design Speed of 100 kmph
Desirable minimum required
The flyover with slip road on both sides has been proposed at the end of project highway at
intersection with Jamnagar bypass (SH-25). The details of the same are given in table below.
S. Existing Design
Proposed Span Remarks
No. Km Chainage
1 4+675 101.313 1x15m+1x30m+1x15m At Junction With SH-25
The VUP with slip road on both sides has been proposed at the intersection with SH-1
leading to Arani.
The CUP has been proposed for the camel/animal cross since the camel occurrences observed
at this location.
Design
S. No. Existing Km Proposed Span Remarks
Chainage
CUP has been Proposed to
1 76+330 30.743 1 x 7.0m x 4.50
Facilitate crossing for camel also
The RCC covered drain has been proposed in urban/ built-up area and in the rest of the
stretches earthen drain has been proposed. The details of drain along the project road are
listed in Table 7.21 below:
Total
S. Built-Up
Existing KM Design Chainage Length Type of Drain
No Area
(Km)
.
From To From To
RCC covered
1 4+125 5+125 101.800 100.800 1.000 Flyover
drain
2 5+125 5+760 100.800 100.200 0.600 Earthen drain -
RCC covered Theba
3 5+760 6+440 100.200 99.480 0.720
drain village
4 6+440 45+180 99.480 61.670 37.810 Earthen drain -
RCC covered Kalavad
5 45+180 48+875 61.670 58.280 3.390
drain village
6 48+875 77+325 58.280 29.760 28.520 Earthen drain -
RCC covered Satodad
7 77+325 78+000 29.760 29.100 0.660
drain village
8 78+000 88+415 29.100 18.970 10.130 Earthen drain -
RCC covered Jamkandorn
9 88+415 90+705 18.970 16.682 2.288
drain a Town
10 90+705 90+825 16.682 16.562 0.120 Earthen drain -
RCC covered
11 90+825 91+750 16.562 15.762 0.800 VUP
drain
107+00
12 91+750 15.762 0.000 15.762 Earthen drain -
0
Total Length of RCC Drain 8.858
Total Length of Earthen Drain 92.942
Proposal of Junction development has been made for 62 nos. Intersection along the project
highway. Out of which, 54 nos. are three arm junctions and 7 nos. are four arm junction and
one staggered junction. There are two intersections with National highway i.e. NH-27 and
SH-25 respectively at starting and end of the project highway. Out of 62 no. junctions, 10 no.
are major junctions with National highway and State highway and remaining 52 no. are
minor junctions with village/ other type of road. All the junctions except crossing of National
highway/ State highways are of minor in nature. The list of major and minor junctions is
given in Table 7.22.
7 36+345 70.530 3-Legged Existing NH-927D Khandhera Junctions at Start and End of Khandhera
8 34+500 71.830 3-Legged Existing NH-927D Khandhera Bypass
Width of Cross
S. Existing Design Type of Type of
Side Road Cross Road Leading To
No. Km Chainage Junction Surface
(m)
1 107+255 227 RHS T WBM 5.00 For Cross road to power house
2 103+013 4440 RHS T BT 3.90 -
3 101+920 5530 RHS Y BT 3.00 Amar Kot
4 100+180 6990 LHS T BT 3.00 Taravada
5 98+160 9260 RHS T BT 3.60 Issuriya
6 98+070 9355 LHS T BT 3.70 Raaide
7 94+555 12863 RHS T BT 4.00 Dudhiyavadar
8 91+580 15848 LHS Y BT 3.70 Anchavad
9 89+316 18072 BOTH X BT 13.00 Pipardi (LHS) Kandorna (RHS)
10 87+785 19595 RHS T CC 5.20 Vidya Nagar
11 87+720 19660 RHS T CC 3.50 Bai Mukund
12 87+145 20215 RHS T BT 5.60 Varudi Mata Temple
13 86+910 20445 RHS Y BT 3.70 Velda
14 83+245 24115 LHS T BT 3.40 Pipardi
15 83+230 24130 RHS T BT 2.80 Ram Para
16 80+870 26440 LHS Y BT 4.00 Vimal Nagar
17 80+825 26485 RHS T BT 2.80 Thordi
Width of Cross
S. Existing Design Type of Type of
Side Road Cross Road Leading To
No. Km Chainage Junction Surface
(m)
18 80+510 26785 RHS T BT 3.60 Pipaliya
21 80+335 26965 LHS Y BT 3.30 -
22 77+905 29200 LHS Y BT 3.70 Chitara Wad Pati
25 73+015 34220 RHS T CC 4.40 Kana Vadala
26 72+770 34460 LHS T BT 6.70 Gundasari
27 70+990 36100 RHS Y BT 5.20 Bhavabhi Khijadiya
28 68+470 38550 LHS T BT 3.60 Gundasari
29 68+420 38600 LHS Y BT 4.20 Jamdadar
30 60+945 46255 RHS T BT 3.70 Danidhar Temple
31 60+660 46440 LHS T BT 3.50 Fagas
32 58+210 49900 LHS T BT 4.10 Rinari
33 55+980 51145 RHS T BT 5.30 Murila
34 54+540 52585 LHS T BT 3.70 Jalaakanam
35 51+680 55462 LHS Y BT 2.90 Karavaniya
36 47+500 59605 RHS T BT 5.40 Mota Bhadukiya
37 47+300 59805 BOTH X CC 4.00 Pipaliya (LHS) Sardarbag (RHS)
38 45+515 61330 LHS Y BT 3.50 Wavadi
39 44+615 62215 LHS T BT 3.70 Wavadi
40 38+710 68145 RHS Y CC 3.10 Ranuja
Width of Cross
S. Existing Design Type of Type of
Side Road Cross Road Leading To
No. Km Chainage Junction Surface
(m)
41 31+030 75290 RHS T BT 6.30 Varudi Temple
42 28+600 77685 LHS Y BT 5.60 Khankotda
43 22+235 83990 RHS Y BT 4.20 Nani Matli
44 19+850 86305 RHS T BT 3.60 Pasaya
45 18+000 88155 RHS T BT 4.00 Beraja
46 17+465 88680 RHS Y BT 3.80 Aliya
47 12+200 93750 LHS Y BT 3.00 Miyathara
48 11+980 94005 RHS T CC 3.30 Vijrakhi
49 10+345 95585 BOTH X BT 5.30 Suwarada (LHS) (RHS)
50 08+700 97835 RHS T CC 5.80 I.O.C. Ltd.
51 06+245 99690 BOTH X CC & BT 3.90 Theba (LHS) (RHS)
52 04+630 101310 BOTH X BT 20.5 Khambhaliya (LHS) Dhrol (RHS)
As per the site requirement and locations of major town like Dhoraji, Jamkandorna, Kalavad
and Jamnagar, 6 no. Truck Lay Bye has been proposed along the project highway. The
locations of Truck Lay Bye are as given in table below
Design
S. No. Existing Km Side Remarks
Chainage
1 107+064 0.400 Right At Start of Project
2 93+315 14.100 Left Before Jamkandorna Town
3 86+064 21.300 Right After Jamkandorna Town
4 50+450 56.700 Left Before Kalawad Town
5 43+560 63.300 Right After Kalawad Town
6 5+530 100.400 Left At End of Project Before Flyover
The Q-shelter type bus stop has been proposed as per existing bus stop location near to the
intersection or built-up area or as per requirement of site. The detailed drawing of the Q-
shelter bus stop is given with the drawing volume. The standard bus bay will not be
proposing to avoid additional land acquisition, cost reduction and having low traffic demand.
There are total 58 bus stops proposed on both side of the road .The detailed bus stops location
with respective village or cross road are listed in table below.
S. Existing
Design Chainage Side Remarks
No. Km
1 107+164 0.300 Left Ganesh Nagar
2 107+295 0.170 Right Ganesh Nagar
3 102+090 5.350 Left Amarkot Road
4 101+486 5.950 Right Amarkot Road
S. Existing
Design Chainage Side Remarks
No. Km
5 100+276 7.150 Left Travada Road
6 100+015 7.411 Right Travada Road
7 98+320 9.100 Left Issuria, Raaide Road
8 97+820 9.600 Right Issuria, Raaide Road
9 90+405 17.000 Left Jamkandorna Town
10 89+680 17.700 Right Jamkandorna Town
11 87+060 20.300 Left Boria Village
12 86+960 20.400 Right Boria Village
13 80+810 26.500 Left Thordi Road
14 80+200 27.100 Right Thordi Road
15 77+710 29.400 Left Satodad Village
16 77+435 29.651 Right Satodad Village
17 73+135 34.100 Left Village Kana Vadala
18 72+835 34.400 Right Village Kana Vadala
19 71+240 35.850 Left Bhavabhi Khijadia Road
20 70+738 36.350 Right Bhavabhi Khijadia Road
21 68+570 38.500 Left Minor Junction
22 68+410 38.650 Right Minor Junction
23 64+220 42.850 Left Toda Village
24 63+175 43.900 Right Toda Village
25 61+040 46.050 Left Minor Junction
26 60+890 46.200 Right Minor Junction
27 58+260 48.850 Left Minor Junction
28 57+170 48.950 Right Minor Junction
29 54+576 52.550 Left Jalaakanam Road
30 54+526 52.600 Right Jalaakanam Road
31 51+735 55.400 Left karavania Road
32 51+630 55.500 Right karavania Road
33 48+515 58.640 Left Kalawad Urban Area
S. Existing
Design Chainage Side Remarks
No. Km
34 48+495 58.660 Right Kalawad Urban Area
35 46+800 60.300 Left Kalawad Urban Area
36 46+245 60.620 Right Kalawad Urban Area
37 41+500 65.350 Left Cross Road to Temple
38 41+400 65.450 Right Cross Road to Temple
39 40+850 66.000 Left Cross Road to Nana Badanpar
40 40+750 66.100 Right Cross Road to Nana Badanpar
41 38+745 68.130 Left Haripar Village
42 38+715 68.160 Right Haripar Village
43 28+760 77.550 Left Motimatli Village
44 28+710 77.600 Right Motimatli Village
45 22+260 83.950 Left Matwa Village
46 22+190 84.020 Right Matwa Village
47 19+910 86.270 Left Cross Road to Pasaya
48 19+830 86.350 Right Cross Road to Pasaya
49 18+027 88.120 Left Sapda Village
50 17+930 88.230 Right Sapda Village
51 12+108 93.850 Left Vijarkhi Village
52 12+162 93.900 Right Vijarkhi Village
53 10+435 95.500 Left Mota Thavaria Village
54 10+300 95.635 Right Mota Thavaria Village
55 6+320 99.620 Left For Cross road to Theba Road
56 6+210 99.730 Right For Cross road to Theba Road
SH-25 major intersection/
57 4+733 101.200 Left
Lumbininagar
58 4+588 101.350 Right SH-25 major intersection
Vehicle counting cum classifier unit, lighting etc will be provided as per section 10 of 2-lane
Manual.
Table 7.26: List of Proposed Toll Plaza