Professional Documents
Culture Documents
IDCPL, F 1/ D 6, Shanti Appartment Owners Association, Plot No-3, Beside Bus Depot, Sector –
11, Nerul (East), NAVIMUMBAI,MAHARASHTRA – 400706
Tel – 9967350828, 9833599544
website: www.idcpl.org
OWNER CLIENT
PUBLIC WORKS DEPARTMENT
GOVERTMENT OF MAHARASHTRA
CONTRACTOR
PROJECT
Consultancy Services for Feasibility Study cum DPR, Survey and Preparation of and
plan by adopting LiDAR or similar technology for widening to two lanes with paved
shoulders to various roads as per Package mentioned in the state of Maharashtra for
an approximate length 60.00kms under Under Hybrid Annuity/EPC in Wardha District
FIRST SUBMISSION
76
TABLE OF CONTENTS
GLOSSARY ........................................................................................................................... 5
1 INTRODUCTION ........................................................................................................ 7
1.1 Back Ground ............................................................................................................................... 7
1.2 Project Road ............................................................................................................................... 8
1.3 Objective of Consultancy Services ............................................................................................. 8
1.4 Scope of Services ....................................................................................................................... 9
1.5 Interaction with Client ................................................................................................................. 9
5 WORK PROGRAM................................................................................................... 31
P a g e 2 | 71
7.3.3 Camber/Cross Fall ..................................................................................................... 35
7.3.4 Super elevation .......................................................................................................... 35
7.3.5 Transition Curves ....................................................................................................... 35
7.3.6 Vertical Profile ............................................................................................................ 37
7.3.7 Drainage System ....................................................................................................... 37
7.4 Design Standards - Structures ................................................................................................. 37
7.4.1 Special Design Requirements ................................................................................... 37
7.4.2 Design Loads and Stresses ....................................................................................... 38
7.4.3 Pipe Culverts ............................................................................................................. 38
P a g e 3 | 71
13.2 Socio-Economic Study ....................................................................................................... 59
13.2.1 Socio-Economic Profile.............................................................................................. 60
13.2.2 Socio-Economic Survey of PAP ................................................................................ 60
14 DELIVERABLES ...................................................................................................... 61
14.1 Inception Report ................................................................................................................. 61
14.2 Strip Plans .......................................................................................................................... 61
14.3 Draft Feasibility Report ...................................................................................................... 61
14.4 Final Feasibility Report ...................................................................................................... 62
14.5 Technical Schedules .......................................................................................................... 62
14.6 Draft Detailed Project Report ............................................................................................. 62
14.7 Final Detailed Project Report ............................................................................................. 62
14.8 Monthly Progress Report ................................................................................................... 62
P a g e 4 | 71
Glossary
ADB - Asian Development Bank
ADT - Average Daily Traffic
AADT - Annual Average Daily Traffic
BBD - Benkelman Beam Deflection
BIS - Bureau of Indian Standards
BOQ - Bill of Quantities
BOT - Build Operate Transfer
CGRA - California Good Roads Association
Ch. - Chainage
DBFO - Design Build Finance Operate
DGR - Director General of Resettlement
DPR - Detailed Project Report
GAD - General Arrangement Drawing
GPS - Global Positioning System
HTMS - Highway Traffic Management System
IRC - Indian Road Congress
LCW - Left Carriageway
LHS - Left Hand Side
LOS - Level of Service
MCW - Main Carriageway
MoRT&H - Ministry of Road Transport & Highways
MOSRTH - Ministry of Shipping, Road Transport & Highways
NH - National Highway
NHAI - National Highways Authority of India
NHDP - National Highway Development Program
O&D - Origin and Destination
P a g e 5 | 71
PAP - Project Affected Persons
PWD - Public Works Department
QAP - Quality Assurance Plans
RCW - Right Carriageway
RHS - Right Hand Side
ROB - Railway Over Bridge
ROW - Right of Way
R&R - Resettlement & Rehabilitation
SSR - Standard Schedule of Rates
TBM - Temporary Bench Mark
TOR - Terms of Reference
VDF - Vehicle Damage Factor
°C - Degree Centigrade
°F - Degree Fahrenheit
P a g e 6 | 71
1 INTRODUCTION
1.1 Back Ground
The Government of the State of Maharashtra, represented by the ‘Executive engineer, Public
Works Division, ARVI. (the “Authority” or “Engineer – in – charge”) is engaged in the
development of state highways under HYBRID ANNUTY MODE (HAM) and as part of this
endeavour, the Authority has decided to carry out up-gradation and expansion of the stretches
of the Major District Roads (MDR’s) & State Highways (SH’s) in the State of Maharashtra.
Accordingly, PWD has issued a work order vide their Letter ref. No 1863/TC/2023 dt. 03-07-
2023.
The stretches included in the project are given in Table 1.1 below:
Table 1.1: List of Roads under Package
P a g e 7 | 71
Fig-1: Project Layout
P a g e 8 | 71
1.4 Scope of Services
Scope of Consultancy services has been outlined in Clause 4 of TOR. However, the major
tasks under the Consultancy assignments are reproduced as follows:
I. Widening/Improvement proposal for the Project Road shall be accommodated within
the available RoW of the project road. However, land acquisition (details) wherever
required shall be prepared based on revenue records/ maps and necessary draft
notifications (3a, 3A, 3D) for Land Acquisition shall be prepared.
II. Suitable proposal for widening/ strengthening/ improvement shall be prepared based
on design and necessary bid documents for EPC/PPP shall be prepared.
III. Preliminary designs & drawings specifying the project requirements shall be prepared.
IV. Environmental Impact Assessment (EIA), Environmental Management Plan (EMP) and
Rehabilitation & Resettlement studies shall be carried out.
A team of engineers visited the site and carried out detailed reconnaissance survey, Inventory
and Condition of Roads & Pavements.
P a g e 9 | 71
2 PROJECT APPRECIATION
2.1 Project Site
After detailed discussion with PWD authorities, the Final length of the stretch of the Project
are as follows:
Actual
Pkg. and No. Roads Length(km)
Length (km)
Anji Virul SH 325 to Arvi in Km..0/00 to 27/00
27.00 23.5
SH 325 Length 27.00Km
Rasulabad Sorta MDR-10to.Arvi in Km. 0/00 to
10.00
MDR 10 10/00 Length 10.00Km 10.00
Nandora Pachegaon Pim
MDR 43 Palkhuta MDR 26 to Arvi in Km. 0/00 to 13/00, 13.00
13.10
Length 13.00Km
Virul Rasulabad MDR 43 to Arvi in Km. 0/00 to
4.00
MDR 37 4/00, Length 4.00Km 4.20
Ekalara Takarkheda MDR 37 to Arvi in Km. 0/00
6.00 7.10
MDR 26 to 6/00, Length 6.00Km
Total Length 60.00 57.90
The team of engineers visited the site and carried out reconnaissance survey, Inventory and
Condition survey of Roads & Pavements. The following findings were noted down during the
survey:
2.1.1 Terrain
The terrain is mostly Plain. Out of total 60.00 Kms, terrain is as follows:
2.1.2 Climate
The climate of this area is typical of that on the Centre part of India, with plentiful and regular
seasonal rainfall, oppressive weather in the hot months. The summer season from March to
June is followed by the south-west monsoon season from June to September. October and
November form the post-monsoon or the retreating monsoon season. The period from
December to February is the cold season.
Rainfall:
Located near centre of Indian peninsula far from the Bay of Bengal and Arabian Sea.
Chandrapur (Chimur) has a tropical wet and dry climate with dry condition prevailing for most
P a g e 10 | 71
of the year. It receives an annual rainfall of about 1000 mm, almost entirely from monsoon
rains between June to September.
Temperature:
Summers are extremely hot lasting from March to June, with maximum temperature occurring
in May.
P a g e 11 | 71
Length of
Chainage Village/
Sr.No. Habitation(m) Road Width(m) Remark
Habitation
(Km) LHS RHS
1 0+000 Rasulabad 200 200 3.75
2 2+900 Virul 200 200 3.75
3 3+100 Virul 650 650 3.75/5.0
MDR 37: Km xx to Km yy
Length of
Chainage Village/
Sr.No. Habitation(m) Road Width(m) Remark
Habitation
(Km) LHS RHS
1 6+200 Nandpur 900 3.75
2.1.5 Junctions
Details of Major Junctions have been collected during the reconnaissance survey are listed in
Table-2.2: Major Junctions.
Width
Type of
Sr.No. Chainage LHS RHS of Proposed as
Junction
Road(m)
SH 325: Km xx to Km yy
1 0+000 5.5 T Major Junction
2 1+200 VR 5.5 T Minor Junction
3 1+850 VR 5.5 T Minor Junction
4 6+470 VR 3.75 T Minor Junction
5 7+860 VR 3.75 T Minor Junction
6 8+250 VR 3.75 Y Minor Junction
7 9+280 VR 3.75 T Minor Junction
8 10+200 VR 3.75 T Minor Junction
9 14+150 VR 3.75 T Minor Junction
10 19+150 VR 3.75 Y Minor Junction
11 21+860 VR 3.75 T Minor Junction
12 23+500 Arvi Wardha 5 T Major Junction
MDR 10: Km xx to Km yy
1 0+150 VR 3.75 Y Minor Junction
2 0+350 VR 3.75 T Minor Junction
3 2+280 VR 5 T Major Junction
4 4+600 VR 5 T Minor Junction
5 7+200 VR 3.75 Y Minor Junction
P a g e 12 | 71
MDR 43: Km xx to Km yy
1 0+200 VR 3.75 T Minor Junction
2 3+520 VR 3 T Minor Junction
3 3+920 VR 5 T Minor Junction
MDR-26: Km xx to Km yy
1 0+000 Arvi 3.75 T Major Junction
2 0+300 VR 3.75 Y Minor Junction
3 1+890 VR 3.75 T Minor Junction
4 4+580 VR 5.5 T Minor Junction
5 13+000 Arvi Wardha 3.75 T Major Junction
MDR 37: Km xx to Km yy
1 0+000 Takarkheda 3.75 + Major Junction
2 6+050 VR 5 T Minor Junction
3 6+170 VR 5 T Minor Junction
4 6+800 VR 5 T Minor Junction
5 7+170 Arvi 5 Y Major Junction
P a g e 13 | 71
2.1.6 Geometrics
It was observed that the project road passes through Plain/Rolling/Hilly terrain for the
complete project. The project road passes through substandard curves at many locations.
These locations need geometric improvement.
Photograph showing 5.5m C/W with good condition (SH 325 - Virul Anji Stretch)
Photograph showing 3.75m C/W with bad condition (MDR 10, Rasulabad Sorta)
P a g e 14 | 71
2.1.8 Carriageway Configuration
The existing Carriageway configuration is generally 3.5m to 5.5m wide. Road wise distribution
is as follows:
MDR 10
6.40 3.60 - 10.00
2.1.10 Bypasses
P a g e 15 | 71
The park is open for visitors from 15th October to 30th June every season and remains
full-day closed on every Tuesday.
The vegetation of Tadoba forest is of Southern tropical dry deciduous type and is spread
on around 626 sq.km.
Teak is the prominent tree species in the forest and there are a few lakes, which makes
sure the park has rich water resources.
Major part of this forest lies in the hilly area; thus, many hillocks and terrains provide
shelter to the wild animals here.
It has a dense forest area, smooth meadows, deep valleys, and a great atmosphere to
stabilize more numbers of tigers.
The main attraction of the Tadoba National Park is Jungle or Tiger Safari in an open top
gypsy.
There is good chance to spot the shy Sloth Bear and Wild Dogs.
One can find some of the Central India’s best native woodland bird species in this forest.
Accommodation facilities are available and are mainly concentrated among two of its
popular entrance gates i.e., Kolara Gate and Mohurli Gate.
The Tadoba National Park is divided into three separate forest ranges, i.e. Tadoba
north range, Kolsa south range, and Morhurli range, which is sandwiched in between
the first two. There are two lakes and one river in the park, which gets filled every
monsoon, the ‘Tadoba Lake,’ ‘Kolsa Lake,’ and ‘Tadoba River.’ These lakes and rivers
provide vital ingredients needed to sustain the park’s life.
The Tadoba Tiger Reserve is rich in flora and fauna. Some of the famous and wildly
seen flora of this park include, Teak, Ain, Bija, Dhauda, Hald, Salai, Semal, Tendu,
Beheda, Hirda, Karaya gum, Mahua Madhuca, Arjun, Bamboo, Bheria, Black Plum,
and many others. Apart from this the list of animals noted in this part include, Tigers,
P a g e 16 | 71
Indian leopards, Sloth bears, Gaur, Nilgai, Dhole, Striped Hyena, Small Indian Civet,
Jungle Cats, Sambar, Spotted Deer, Barking Deer, Chital, Marsh Crocodile, Indian
Python, Indian Cobra, Grey-headed Fish Eagle, Crested Serpent Eagle, Peacock,
Jewel Beetles, Wolf Spiders, etc.
P a g e 17 | 71
3 DETAILED METHODOLOGY FOR SERVICES
3.1 Work Methodology
The preparation of the feasibility report will be carried out in a systematic procedure giving due
consideration to time and quality of work. The draft methodology planned for the project is
presented in Fig. -3.1 and described briefly.
1. Reconnaissance survey shall be carried out to get familiar with the site and site
features.
2. Inception report shall be prepared and submitted to the client and shall include the
following:
a. Introduction
b. Project Appreciation
c. Work Methodology
d. Design Standards
3. All available information regarding the existing project road will be collected from PWD/
other concerned authorities. Information thus obtained will be reviewed and planning
will be made for collecting further necessary information.
4. The Various Field surveys and investigations to be carried out as per TOR are listed
below:
a. Topographic Survey
e. Geotechnical Investigation.
f. Material Investigation.
P a g e 18 | 71
g. Traffic Survey
5. Intermediate/ Two lane cross sections will be prepared based on the existing cross
sections and fitted on the existing cross-section. The following aspects will be taken
into primary consideration during the preparation of improvement proposal.
a. The improvement will be fitted into the existing ROW to the maximum extent
possible.
b. The existing utilities will be planned for relocation, wherever required, within the
ROW to the maximum extent possible.
d. The alignment and grade of the existing highway will be maintained. The
alignment will be changed in locations where geometrics can be improved.
e. Proposal will be planned to see that the traffic will be least disruptive during
construction stage.
6. A field visit will be made to carry out public consultation in assistance with local
representative of the client and the local administration. Public consultation report will
be prepared subsequent to the field visit and the same will be included in the feasibility
report.
P a g e 19 | 71
Consultancy Services for Feasibility Study cum DPR, Survey and Preparation of and plan by adopting LiDAR or similar
technology for widening to two lanes with paved shoulders to various roads as per Package mentioned in the state of
Maharashtra for an approximate length 60.00kms under Under Hybrid Annuity/EPC in Wardha District
Collection of Available
Documents
Reconnaissance Survey
Inception Report
Technical Schedules
P a g e 20 | 71
7. Draft feasibility report containing design alternative along with the preliminary designs
and results of various surveys and investigations, will be submitted to the client.
8. Final Feasibility Report shall be submitted after incorporating the corrections and
suggestions provided by the client.
9. Draft Technical schedule will be prepared and submitted to the client on approval of
Feasibility Report.
10. Necessary assistance will be provided for preparing bid documents for the tendering
process for the construction of the project.
11. Technical assistance will be provided during the bidding process and also the post
award queries by the concessionaire will be answered.
P a g e 21 | 71
4 TASK ASSIGNMENT AND MANNING SCHEDULE
4.1 Task Assignment
The task assignment for various key personal are as follows:
Designation of
S.
Name Key Task Assignment
No.
Personnel
• TECHNICAL/MANAGERIAL STAFF
1 Dr. Dulal Chandra Senior Highway • Liaison with PWD Maharashtra and
Saha Engineer – cum - other related Organizations.
Team Leader
• Co-ordinate in the formulation and
development of QAP for all
activities.
• Evolve and finalize design
standards in consultation with other
Key Personnel of the team.
• Finalize data formats and
requirements for field investigations
and adopt system for computer-
based data processing and storage.
• Prepare schedule and organize all
field, design and documentation
activities.
• Organize data collection,
compilation and development of
data bank.
• Responsibility for finalizing
geometric design standards for
road, pavement design, drainage
design and BOQ.
• Evaluate improvement options and
finalize project components.
• Packaging of contract.
• Prepare reports, documents and
appraisal notes.
• Monitor time schedule, manage and
evaluate team’s resources for timely
project completion.
• Organize public consultation with
the help of Client.
P a g e 22 | 71
Designation of
S.
Name Key Task Assignment
No.
Personnel
• Guide the team members in working
out the Project cost.
• Provide leadership and direction to
multi-disciplinary team to achieve
project objectives.
Any Other relevant tasks as
identified from time to time.
P a g e 23 | 71
Designation of
S.
Name Key Task Assignment
No.
Personnel
3 A Krishna Priya Traffic – cum Safety • Develop QAP and implementation
Expert procedure.
• Evolve, finalise and adopt highway
capacity standards
• Finalise data formats and
requirement of traffic surveys.
• Schedule all relevant activities.
• Collect, compile and develop traffic
data bank.
• Supervise all traffic surveys and
analyze traffic data and prepare
traffic projections.
• Identify bypass and location for
traffic control
• Prepare traffic management
scheme for construction and post
construction stages.
• Carryout design of intersection and
interchanges.
• Identify and design road furniture
and traffic safety measures
Any Other relevant tasks as
identified and assigned by Team
Leader
P a g e 24 | 71
Designation of
S.
Name Key Task Assignment
No.
Personnel
and make recommendation for type
of pavement to be adopted.
• Prepare a detailed pavement design
and rehabilitation report.
• Make recommendations on
appropriate methods and practices
related to pavement construction
Any Other relevant tasks as
identified and assigned by Team
Leader
P a g e 25 | 71
Designation of
S.
Name Key Task Assignment
No.
Personnel
6 B Sandeep Purna Quantity Surveyor/ • Review & Finalization of data
Documentation formats and requirements for field
Expert Surveyor studies for exploration and
selection of construction materials.
• Review of Collection, compilation
and development of data bank for
materials and pavements.
• Scheduling of all field and
laboratory testing activities and
finalisation of formats.
• Specifications for pavement
materials.
• Time schedule and management of
Material and Pavement
Engineering Team's resources.
• Identification of Quarry sites for
aggregates, quarry spall, sand,
borrow material.
• Verify manufacturers’ certificates;
7 M Nageswara Rao Surveyor • Develop QAP and implementation
procedure for topographic survey
• Prepare data format and
methodology
• Organize and supervise fixation of
reference points with GPS & Total
Stations.
• Organize and supervise fixation of
TBMs
• Organize and supervise topographic
survey
• Download survey data into
computer and rectify accuracy of all
survey operations
• Co-ordinate with Highway Engineer
for the development of alignment
plans and road profiles
Any Other relevant tasks as
P a g e 26 | 71
Designation of
S.
Name Key Task Assignment
No.
Personnel
identified and assigned by Team
Leader
P a g e 27 | 71
Designation of
S.
Name Key Task Assignment
No.
Personnel
environmental impact studies;
• Collection, Compilation and
development of environment and
social related data bank;
• Inventory of existing environmental
feature ;
• Data analysis and selection of
parameters for the environmental
impact mitigation measures;
• Propose Environmental
Management Plan for the
construction phase.
• Time schedule and management of
environmental Team’s resources.
Any Other relevant tasks as
identified and assigned by Team
Leader
P a g e 28 | 71
Designation of
S.
Name Key Task Assignment
No.
Personnel
Leader
• SUPPORT STAFF
S. Designation of Key
Name Task Assignment
No. Personnel
To assist the key professionals in
1 To be named later Survey Engineers carrying out relevant tasks as identified
from time to time.
P a g e 29 | 71
Quantity Surveyor /
5 B.Purna Sandeep
Documentation Expert 16.67 16.67
Resettlement &
6 Ajay Kumar Alugolu
Rehabilitation Specialist 10.00 10.00
Total Man-Days
144.35 142.35
P a g e 30 | 71
5 WORK PROGRAM
The work programme for the above-mentioned project is prepared and presented in Appendix
1. The various activities are listed down and scheduled to be completed in the stipulated time
of 3 months.
P a g e 31 | 71
6 PROFORMA FOR DATA COLLECTION
All required Proforma for data collection required for the Project preparation has been given in
QAP, attached as a separate report.
P a g e 32 | 71
7 DESIGN STANDARDS AND PROPOSED CROSS SECTIONS
7.1 General
Highway designing is the process wherein the layout of the road in specific terrain is designed
to meet the needs of the road users. Designing is carried out keeping in view the following
aspects:
1. Road function
4. Capital cost,
5. Maintenance costs,
7. Environment impacts,
8. Aesthetics, and
The principal geometric features for fulfilment of these objectives are road classification, the
horizontal alignment, vertical profile, road cross-section, road furniture’s etc.
Manual for Specifications and Standards for Two Lanning of National Highways through
Public Private Partnership.
P a g e 33 | 71
3. Indian Roads Congress (IRC) Codes and Standards
Where the above standards are not adequate, international standards and specifications will
be followed. The various codes that will be referred during the various stages of the project
are listed in Appendix 2.
Proposed Typical cross sections for the Project Road are as follows:
P a g e 34 | 71
7.3.2 Horizontal Geometry
In road alignment, changes in direction are often necessary due to many restrictions.
Restrictions may be imposed by topography, environment, roadway width, ecological qualities
of areas, monuments, places of worship, sites of structures and other considerations. For
convenient, safe and pleasant travel on road, changes in directions have to be accomplished
by introducing horizontal curves and transition curves in the alignment.
Design speed, super elevation and coefficient of lateral friction affect the design of circular
curves. Length of transition curve is determined on the basis of rate of change of centrifugal
acceleration or the rate of change of super elevation.
The cross fall for earthen shoulder in straight sections shall be 0.5% steeper than that of the
carriageway subject to a minimum of 3.0%. On curves, the shoulder on the high side of
superelevated portion shall be provided with reverse slope from the superelevated
carriageway portion. As per clause 4.2.5 of the manual, the rate of change between
pavement cross slope and outside shoulder shall not exceed 5%.
P a g e 35 | 71
Spiral curve is used for transitions. These are necessary for smooth entry of vehicles from a
straight section into a circular curve. The transition curves also improve aesthetic appearance
of the road, besides permitting gradual application of the super elevation to counteract
centrifugal force and extra widening at curves. Minimum length of transition curves specified
in IRC: 73-1980 for various design speeds and various radius of horizontal curves is
presented in Table - 7.1.
P a g e 36 | 71
7.3.6 Vertical Profile
The vertical profile is provided for a smooth longitudinal profile consistent with category of the
road and lay of the terrain. Too frequent grade changes shall be avoided to reduce kinks and
visual discontinuities in the profile. The vertical profile of the existing road shall be improved
as per the recommendations in IRC:SP:23-1983 “Vertical Curves for Highways”.
Carriageway configuration of all Structures shall be incompliance with IRC Standards for 2-
lane.
2. Carriageway configuration for all Structures shall be incompliance with IRC Standards
for 2 Lane.
4. Bearing of new bridges shall be easily accessible for inspection and maintenance.
P a g e 37 | 71
5. Reinforced Earth/R.C.C Retaining wall type shall be provided for high fill/embankment
with aesthetically pleasing appearance. Design life of reinforcing elements for earth
retaining structures shall be 100 years minimum. Structure with viaduct shall be
provided for ensuring unhindered local cross movement of pedestrians and local
vehicular traffic.
P a g e 38 | 71
8 KEY PLAN AND LINEAR PLAN
The layout map of the Project roads is as under:
The layout map of the Project roads is as under:
P a g e 39 | 71
9 DEVELOPMENT PLANS IN AND AROUND THE PROJECT
ROAD
Development plans being implemented and / or proposed for implementation in the near
future by the local bodies are being collected and the possible impact of such development
plans on the overall scheme for field work and design for the study shall be taken care during
investigations. Details of the same shall be incorporated in subsequent reports, if any.
P a g e 40 | 71
10 QUALITY ASSURANCE PLANS
10.1 General
The purpose of quality assurance plan is to define various activities to be performed in a
planned, systematic way within the quality management system of the consultants. The
procedure adopted in planning, implementation and demonstration of an activity in a
systematic manner to fulfil the requirements is presented in the Quality Assurance Plan. The
assignment will be carried out with regulated procedures such that reports and product of
studies & investigations fully satisfy the needs of the project specified in terms of reference. In
order to achieve the standards and results, steps for quality control will be introduced and
implemented throughout the tenure of the assignment. QAP will indicate details of tasks
conceived and would identify personnel with specific responsibilities regarding preparation,
checking and verifying various activities of the project.
• Quality procedure for Field studies and investigations and review of survey data
• Details of personals responsible for collection of data, carrying out designs & drawings
• Details of personals responsible for carrying out checks, verification and approval
P a g e 41 | 71
4. Material Cum Geotechnical Engineer Cum Geologist
7. Environmental Specialist
• Evolve and finalize design standards in consultation with other Key Personnel of
the team
• Finalize data formats and requirements for field investigations and adopt system
for computer-based data processing and storage
• Prepare schedule and organize all field, design and documentation activities
• Responsibility for finalizing geometric design standards for road, pavement design,
drainage design and BOQ
• Monitor time schedule, manage and evaluate team’s resources for timely
completion of project
P a g e 42 | 71
Any Other relevant tasks as identified from time to time.
• Finalize data formats and requirement of relevant studies on bridges and other
structures
• Propose rehabilitation scheme for the existing bridges and widening schemes for
existing structures and construction alternatives based on techno-economic
considerations
• Design bridges, cross-drainage structures, retaining walls etc for DBFO Model
• Finalisation of data formats and requirements for field studies for exploration and
selection of construction materials & topographic survey
• Finalisation of data formats and requirements for field studies for pavement
investigations condition, roughness, strength, subgrade characterisation and
subgrade strength
• Evaluate Reports, documents and drawings and other design related features
P a g e 43 | 71
d. Material Geo-Technical Expert Cum Geologist
• Prepare formats for recording field and laboratory investigation data with regard to
soils, materials and geotechnical investigations
• Organize and supervise sampling and testing of soils and materials and
geotechnical investigations
• Recommend ways and means for maximum utilization of locally available materials
and the manner of improving local weaker materials
• Organize and supervise fixation of reference points with GPS & Total Stations
• Download survey data into computer and rectify accuracy of all survey operations
• Co-ordinate with Highway Engineer for the development of alignment plans and
road profiles
P a g e 44 | 71
• Finalise data formats and requirement of traffic surveys
• Supervise all traffic surveys and analyse traffic data and prepare traffic projections
• Prepare traffic management scheme for construction and post construction stages
g. Environmental Specialist
• Quality Assurance Plan (QAP) and implementation of the same for all field, design
and documentation activities regarding environmental aspects
• Evolution, finalisation and adoption of the scheme for field work and
instrumentation for environmental impact assessment
• Finalisation of data formats and requirements for field studies for environmental
impact studies
• Data analysis and selection of parameters for the environmental impact mitigation
measures
P a g e 45 | 71
• Resettlement Action Plan including cost of resettlement and rehabilitation
h. Design Engineer
• Design of road alignment – plan & profile, based on the topographic survey and
propose improvements, where necessary
• Pavement design for main carriageway and Service Roads, as per the findings of
the traffic projections
• Producing work quantities and cost estimates that are accurate and reliable
• Get the drawing checked with respect to quality from the CAD Engineer in neatly
laid out and easily comprehensible format
• Ensuring that dimensions and details arrived at by calculations are translated into
drawings
• Check the “CHECK PRINT” using Yellow and Red marks. (Items marked with
Yellow are deemed correct, items that need correction are scored with Red and
remarks are written. Revisions / additions are also marked in Red
• Giving the corrections to the CAD engineer and recheck using Yellow and Red.
P a g e 46 | 71
• Get the fully corrected drawing verified by Highway Engineer / Key Discipline
Engineer
i. Field Engineer
• Collected the data formats prepared by the Design engineer and verified by
Highway engineer
• Get the surveys done as per standards and also as per TOR
• Get all the necessary site information as when needed by the design engineer for
designs and verifications
j. Draftsman
Draftsman is responsible for ensuring that dimensions and other precise information is
incorporated in neatly laid out and easily comprehensible drawings.
10.3 Documentation
Quality in work, is something which the Consultant lays prime importance to. The consultant has a well -
defined Quality assurance Plan, which shall guide the project implementation.
The main approach for the same will be:
• Continuous improvement of process based on the objective measurement and analysis
• Need to consider process as value added
P a g e 47 | 71
• Obtaining the results of process performance and effectiveness
• Understanding, meeting and integrating clients, statutory and regulatory requirements.
The focus of QA system is on the processing, handling, documenting, archiving and reporting
procedures.
P a g e 48 | 71
11 SURVEYS & INVESTIGATIONS
11.1 General
Surveys and investigations required for design of the project road is listed below. A brief
description is also presented in the sections to follow. The preliminary data collection format
sheets used for the collection of various survey and investigations data are presented in
annexure at the end of the document.
1. Topographic survey
5. Pavement roughness
7. Geotechnical survey
8. Material survey
9. Traffic surveys
P a g e 49 | 71
levelling for the near by established Bench mark (BM) by Auto level. In addition to TBM, levels
will be established/ transferred to all existing permanent structures along the project road.
Complete features & Cross-sectional levels will be taken by total station for the complete
corridor along the project road.
a. Cracking
b. Raveling
c. Pot Holes
d. Patch Works
e. Rutting
The road length will be divided into 50m sections and data will be recorded for each section.
P a g e 50 | 71
that performance of a flexible pavement is related to the elastic deflection under wheel loads.
To determine the strengthening requirement the following data will be collected:
• The characteristics deflection of the pavement under a standard wheel load (8160
kg.) fitted with dual tyre inflated to a pressure of 5.60 kg/cm2
• Information regarding the type and moisture content of the sub grade soil
The tests shall be conducted in a staggered way along the rear outer wheel path. Rebound
deflections will be measured using CGRA method. The measured deflection readings will be
corrected for seasonal variations depending on the type of sub grade soil and field moisture
content. Temperature corrections will be made to get the characteristic deflection of the
existing pavement.
P a g e 51 | 71
with adequate yields of materials for this project along with prevailing market rates will be
collected. Approximated lead for transport of materials will also be determined during material
survey.
• The materials like sand, gravel, moorum, stone etc., should be available at
minimum possible lead.
Keeping the above points in view the material survey will be conducted considering the
feasibility of the material availability, ease of transportation, quality and cost of the material
The initial task of identifying the homogeneous traffic links shall be undertaken on the
identified road sections. The scope of traffic studies in this project will be established based
on the results of the review of available traffic data. Homogeneous traffic links will be
established through identification of the major intersections and urban centres. On the basis
of these and the characteristics of the road sections, the locations for conducting traffic
surveys under this project will be established. The fixation of locations will be made for traffic
volume surveys, both at mid sections and intersections. However, the locations will be
finalized with due consultation with PWD officials
P a g e 52 | 71
counts. One supervisor will be employed at each count locations. Traffic Engineer will
carryout random check counts to ensure the quality of data collection. The data collected will
be summarized and analysed to arrive at the ADT, hourly variation and directional variation.
The various class of vehicles counted will be as per relevant IRC code and the same is
specified in Table - 11.1.
Two-Wheeler Bi-Cycle
Three-Wheeler Cycle-Rickshaw
Bus/Truck/Road Roller
The location of origin and destination zones will be determined in relation to each individual
station and the possibility of traffic diversion to the Project Road from/to other road routes
including bypasses. The trip matrices will be worked out for each vehicle type information
giving due weightage for trucks. Trucks will be summed up by commodity type and the results
will be tabulated to give total weight and average weight per truck for the various commodity
P a g e 53 | 71
types. The sample size for each vehicle type will be indicated in a table format and the same
shall be represented graphically.
The data derived from surveys will also be analysed to bring out the lead and load
characteristics and desire line diagrams. The distribution of lead and load obtained from the
surveys will be compared with those derived from the axle load studies. The commodity
movement data will be duly taken into consideration while making the traffic demand
estimates.
P a g e 54 | 71
to determine VDF. This survey will be carried out at two locations in both directions for one
day (16 hours).
P a g e 55 | 71
12 Analysis & Preliminary Design
Based on the data obtained from various surveys and investigations, analysis is to be done to
carry out preliminary designs. Some of the preliminary designs will consist of the following:
1. Horizontal alignment
2. Vertical Profile
3. Cross-sections
P a g e 56 | 71
in Capacity Utilisation of the Road Sections will be studied and an estimation of the time-
based users versus non-time based users and the local traffic versus the through traffic is
proposed. All these findings will collectively contribute to the understanding of the existing
problems on the project corridor at a micro level and pave the way for suggesting
development measures related to geometric improvements and development of other road
infrastructures like ROB, Interchanges etc. However, in order to establish the base year link
traffic volume in terms of ADT, the seasonal correction factor needs to be applied to the traffic
volume data in order to arrive at the AADT (Annual Average Daily Traffic) of base line traffic
figures.
It further proposes to review the impact of plans, programmes and schemes with focus being
primarily on appreciation of implications of envisaged development scenario on proposed
project facility and on operation of activities proposed in the region along the corridor. The
review will have prime focus on their impact on travel demand levels on corridor. In addition,
we also propose to appreciate the phasing, expected level and time of operation of these
projects and consequent traffic generation levels.
P a g e 57 | 71
To design, the thickness of overlay required for strengthening the existing pavement,
structural evaluation of the existing pavement will be carried out. The structural evaluation of
the pavement will be conducted using Benkelman beam deflection technique. For the design
of new pavement and pavement for widening portion, strength of subgrade is determined
along with the traffic loading characteristics.
P a g e 58 | 71
13 ENVIRONMENTAL & SOCIAL IMPACT
13.1 Environmental Analysis
The Consultants are of the opinion that the environmental evaluation of any project cannot be
reduced to the completion of a Leopold Matrix. One reason is that fundamental weakness of
matrices to accommodate secondary effects or the relative importance of different effects
which may be short or long term, local or regional, reversible or permanent in character.
The Consultants would evaluate the performance of the proposed highway against a series of
objectives or standards. The early part of the assessment program would seek to determine
an agreed set of performance standards for various environmental attributes. It is likely,
however, that it will not be until the characteristics of the environmental consequence of the
highway have been determined that evaluation techniques can be applied. It is expected that
trade-off analysis will be necessary.
• As noted earlier, mitigation measures are only necessary when unavoidable and
unacceptable residual environmental effects keep following the close coordination
or environmental and engineering factors in the highway design process which is a
hallmark of our approach. Various solutions to the residual environmental effects
may be available. The solutions may also differ in their expected degree of
success and financial implications.
P a g e 59 | 71
13.2.1 Socio-Economic Profile
The widening of road/construction of new road for changes in existing alignment or for
bypasses require acquisition of land and removal of encroachments etc., which may in turn
involve losing agricultural land, getting displaced and losing access to present income earning
activities. The data on demography, economic activity, social infrastructure, transportation
system, accident statistics etc., would be ascertained and supplemented by primary surveys.
A descriptive and quantified socio-economic profile for the road influence area will be
prepared.
• Socio-demographic characteristics
Analysis of data gathered during the baseline survey will lead to identifying the magnitude of
impacts both in social and economic terms for the different types of PAPs. It will also indicate
the type of entitlements that need to be given to PAPs – resettlement, monetary compensation
or livelihood restoration.
P a g e 60 | 71
14 DELIVERABLES
14.1 Inception Report
This inception report shall contain the following:
b. Work methodology,
f. Analysis and preliminary designs proposed to be carried out for the project, and
c. Traffic forecast
d. Improvement proposals
e. Preliminary designs
f. Pavement design
g. Drainage Design
h. Design of structures
i. Land acquisition
P a g e 61 | 71
14.4 Final Feasibility Report
The Consultant shall prepare and submit to the client the final feasibility report along
with environmental and social reports, utilities relocation plans, land plan schedules,
and preliminary costing after incorporating the clients’ observations in the draft.
P a g e 62 | 71
Appendix - 2: List of Codes
1 IRC: 2 -1968 Route Marker Signs for National Highways (First Revision)
Dimensions and weight of Road Design vehicles. (First
2 IRC: 3 -1983
Revision)
Standard Specification & Code of Practice for Road Bridges,
3 IRC: 5 -1998
Section I – General Features of Design (7th Revision)
Standard Specifications & Code of Practice for Road Bridges,
4 IRC: 6 -2000
Section II – Loads and Stresses (Fourth Revision)
Recommended Practice for Numbering Bridges and Culverts
5 IRC: 7 -1971
(First Revision)
6 IRC: 8 -1980 Type Designs for Highway Kilometre Stones (Second Revision)
P a g e 63 | 71
Sl. IRC Code Number
IRC Code Description
No. and Year
Standard Specifications and Code of Practice for Road Bridges.
15 IRC: 24 -2001
Section-V Steel Road Bridges (First Revision)
16 IRC: 26 -1967 Type Design for 200-Metre Stones
Standard Letters and Numerals of Different Heights for Use on
17 IRC: 30 -1968
Highway Signs
Standard for Vertical and Horizontal Clearances of Overhead
18 IRC: 32 -1969 Electric Power and Telecommunication Lines as Related to
Roads
Standard procedure for evaluation and condition surveys of
19 IRC: 33 -1969
stabilised soil roads.
20 IRC: 34 -1970 Recommendations for road construction in waterlogged area.
21 IRC: 35 -1997 Code of Practice for Road Markings (with Paints) (First Revision)
Recommended Practice for Construction of Earth Embankments
22 IRC: 36 -1970
for Road Works
Guidelines for the Design of Flexible Pavements (Second
23 IRC: 37 -2001
Revision)
Guidelines for Design of Horizontal Curves for Highways and
24 IRC: 38 -1988
Design Tables (First Revision)
Standard Specifications and Code of Practice for Road Bridges,
25 IRC: 40 -2002
Section IV -Brick, Stone and Block Masonry (Second Revision)
26 IRC: 41 -1997 Type designs for check barriers (First Revision)
Proforma for record of test values of locally available pavement
27 IRC: 42 -1972
construction materials.
Recommendations for Estimating the Resistance of Soil Below
28 IRC: 45 -1972 the Maximum Scour Level in the Design of Well Foundations of
Bridges
Recommendation about the alignment survey and geometric
29 IRC: 52 -2001
design of hill roads. (Second Revision)
30 IRC: 54 -1974 Vertical Clearances at Underpasses for Vehicular Traffic.
Recommended Practice for Treatment of Embankment Slopes
31 IRC: 56 -1974
for Erosion Control
P a g e 64 | 71
Sl. IRC Code Number
IRC Code Description
No. and Year
Recommended Practice for Sealing of Joints in Concrete
32 IRC: 57 -1974
Pavements
Guidelines for the design of plain jointed Rigid pavements for
33 IRC: 58 -2002
highways (Second Revision)
Tentative Guidelines for the design of gap graded cement
34 IRC: 59 -1976
concrete mixes for road pavements.
Tentative Guidelines for the construction of Cement Concrete
35 IRC: 61 -1976
Pavements in Hot Weather
36 IRC: 65 -1976 Recommended practice for traffic rotaries.
37 IRC: 67 -2001 Code of Practice for Road Signs (First Revision)
38 IRC: 69 -1977 Space Standards for Roads in Urban Areas
Guidelines on regulations and control of mixed traffic in urban
39 IRC: 70 -1977
areas.
40 IRC: 71 -1977 Recommended practice for preparation of notations.
41 IRC: 73 -1980 Geometric Design Standards for Rural (Non-Urban) Highways
42 IRC: 75 -1979 Guidelines for the Design of High Embankments
Standard Specifications and Code of Practice for Road Bridges.
43 IRC: 78 -2000
Section-VII Foundations & Sub-structure (Second Revision).
44 IRC: 79 -1981 Recommended Practice for Road Delineators
Type Designs for Pick-up Bus Stops on Rural (i.e., Non-Urban)
45 IRC: 80 -1981
Highways
Tentative Guidelines for Strengthening of Flexible Road
46 IRC: 81 -1997 Pavement Using Benkelman Beam Deflection Technique (First
Revision)
Standard Specifications and Code of Practice for Road Bridges.
47 IRC: 83 -1999
Section-IX Bearings, Part-I: Metallic Bearings.
Standard Specifications and Code of Practice for Road Bridges,
48 IRC: 83 -1987
(Part-II) Section-IX Bearings, Part-II: Electrometric Bearings
Standard Specifications and Code of Practice for Road Bridges,
49 IRC: 83 -2002 (Part-II) Section-IX Bearings, Part-III : POT POT-CUM-PTFE,
PIN AND METALLIC GUIDE BEARINGS
P a g e 65 | 71
Sl. IRC Code Number
IRC Code Description
No. and Year
50 IRC: 84 -1983 Code of Practice for Curing of Cement Concrete Pavement
Recommended practice for accelerated strength testing and
51 IRC: 85 -1983
evaluation of concrete for Road and Airfield Constructions.
52 IRC: 86 -1983 Geometric Design Standards for Urban Roads in Plains
Guidelines for the design and erection of false work for road
53 IRC: 87 -1984
bridges.
Recommended practice for lime fly ash stabilised soil base/ sub
54 IRC: 88 -1984
base in pavement construction.
Guidelines for Design & Construction of River Training & Control
55 IRC: 89 -1997
Works for Road Bridges (First Revision)
Tentative guidelines for construction of cement concrete
56 IRC: 91 -1985
pavement in cold weather.
57 IRC: 92 -1985 Guidelines for the Design of Interchanges in Urban Areas
58 IRC: 93 -1985 Guidelines on Design and Installation of Road Traffic Signals
Guidelines on Accommodation of Underground Utility Services
59 IRC: 98 -1997
Along and Across Roads in Urban Area (First Revision)
Guidelines for design of continuously reinforced concrete
60 IRC: 101 -1988
pavement with elastic joints.
61 IRC: 102 -1988 Traffic studies for planning bypasses around towns.
P a g e 66 | 71
Sl. IRC Code Number
IRC Code Description
No. and Year
Recommendations About Overlays on Cement Concrete
69 IRC: SP: 17 -1977
Pavements
70 IRC: SP: 18 -1978 Manual for Highway Bridge Maintenance Inspection.
Manual for Survey, Investigation and Preparation of Road
71 IRC: SP: 19 -2001
Projects (First Revision)
72 IRC: SP: 21 -1979 Landscaping of Road
Recommendations for the Sizes for each Type of Road Making
73 IRC: SP: 22 -1980
Machinery to Cater to the General Demand of Road Works
74 IRC: SP: 23 -1983 Vertical Curves for Highways
Gopi and his Road Roller-Guidelines on Maintenance of Road
75 IRC: SP: 25 -1984
Roller
Report Containing Recommendations of IRC Regional
76 IRC: SP: 27 -1984
Workshops on Highway Safety
77 IRC: SP: 32 -1988 Road Safety for Children (5-12 Years Old)
Guidelines on Supplemental Measures for Design, Detailing &
78 IRC: SP: 33 -1989
Durability of Important Bridge Structures.
General Guidelines About the Equipment for Bituminous
79 IRC: SP: 34 -1989
Surfacing Dressing
80 IRC: SP: 35 -1990 Inspection and Maintenance of Bridge.
81 IRC: SP: 37 -1991 Guidelines for Evaluation of Load Carrying Capacity of Bridges
Guidelines on Bulk Bitumen Transportation & Storage
82 IRC: SP: 39 -1992
Equipment
Guidelines on techniques for strengthening and rehabilitation of
83 IRC: SP: 40 -1993
bridges.
Guidelines on Design of At-Grade Intersections in Rural & Urban
84 IRC: SP: 41 -1994
Areas
85 IRC: SP: 42 -1994 Guidelines on Road Drainage
86 IRC: SP: 44 -1994 Highway Safety Code
87 IRC: SP: 46 -1997 Steel Fibre Reinforced Concrete For Pavements
Guidelines on Quality System for Road Bridges (Plain,
88 IRC: SP: 47 -1998
Reinforced, Prestressed and Composite Concrete).
P a g e 67 | 71
Sl. IRC Code Number
IRC Code Description
No. and Year
89 IRC: SP: 48 -1998 Hill Road Manual
90 IRC: SP: 50 -1999 Guidelines on Urban Drainage
91 IRC: SP: 51 -1999 Guidelines for Load Testing of Bridges
92 IRC: SP: 52 -1999 Bridge Inspector's Reference Manual
Guidelines on Use of Polymer and rubber Modified Bitumen in
93 IRC: SP: 53 -2002
Road Construction (First Revision)
94 IRC: SP: 54 -1999 Project Preparation Manual for Bridges
95 IRC: SP: 55 -2001 Guidelines for Safety in Construction Zones
96 IRC: SP: 56 -2000 Guidelines for Steel Pedestrian Bridges
97 IRC: SP: 57 -2001 Guidelines for Quality Systems for Road Construction
98 IRC: SP: 58 -2001 Guidelines for Use of Fly ash in Road Embankments
Guidelines for Use of Geotextiles in Road Pavements and
99 IRC: SP: 59 -2002
Associated Works
An Approach Document for Assessment of Remaining Life of
100 IRC: SP: 60 -2002
Concrete Bridges
Sl.
Name of the Publication
No.
3 MORT&H Specifications for Road and Bridge Works, 2001 (Fourth Revision)
MOST Standard Plans for 3.0 m Span Reinforced Cement Concrete Solid Slab
4
Superstructure with and without Footpaths for Highways, 1991
MOST Standard Plans for Highways Bridges R.C.C. T-Beam & Slab Superstructure -
5
Span from 10 m to 24 m with 12 m width, 1991
MOST Standard Plans for Highway Bridges PSC Girder and RC Slab Composite
6 Superstructure for 30 m Span with and without Footpaths, 35 m Span with Footpaths
and 40 m Span without Footpaths, 1991
P a g e 68 | 71
Sl.
Name of the Publication
No.
MOST Standard Drawings for Road Bridges - R.C.C. Solid Slab Superstructure (15* &
7
30* SKEW Span 4.0 m to 10.0 m (with and without Footpaths), 1992
9 MOST Computer Aided Design System for High Embankment Problems, 1993
MOST Standard Drawing for Road Bridges R.C.C. Solid Slab Superstructure (22.5*
11
SKEW) R.E. Span 4M to 10M (with and without Footpath), 1996
Standard Plan for Highway Bridges - Prestressed Concrete Beam & RCC Slab Type
13
Superstructure - Volume –II
MOST Standard Plans for Single, Double and Triple Cell Box Culverts with and
15
without Earth Cushion
BIS Publications
Sl.
Name of the Publication
No.
IS: 1944 (Part-I & II) 1970 Code of Practice for lighting of Public thoroughfare: Parts
1 Land 2 For Main and secondary roads (Group-A and B) (First revision) (Amendments
No. 1 and 2) Parts – I and 2 in one volume) (Amendments-2).
IS: 1944 (Part-V) 1981 Code of Practice for Lighting of Public Thoroughfares: Parts 5
2
Lighting for Grade separated junctions, Bridges and Elevated roads (Group – D).
P a g e 69 | 71
Sl.
Name of the Publication
No.
IS: 1944 (Part-VI) 1981 Code of Practice for lighting of Public thoroughfare: Part-6
3
Lighting for Towns and city centres and areas of civic Importance (Group-E).
5 IS: 10748 – 1995 Hot rolled steel for welded tubes and pipes (First Revision)
P a g e 70 | 71
Appendix - 3: Survey Forms
P a g e 71 | 71