Professional Documents
Culture Documents
DEEDOKE
HYDROPOWER PROJECT
DECEMBER 2012
AF-Colenco Ltd.
Hydropower Plants
DEEDOKE HPP
Preliminary Feasibility Study
2/57
Table of Contents
Page
1 INTRODUCTION .............................................................................................................7
1.1 General ..............................................................................................................................7
1.2 Objectives of the Study .....................................................................................................8
1.3 Available information........................................................................................................8
2 TOPOGRAPHY ..............................................................................................................10
2.1 Topographical map ..........................................................................................................10
2.2 SRTM Digital Elevation Model ......................................................................................10
2.3 Topographic survey .........................................................................................................10
3 HYDROLOGY ................................................................................................................12
3.1 Deedoke HPP Catchment Area .......................................................................................12
3.2 Water availability ............................................................................................................13
3.3 Floods ..............................................................................................................................13
4 GEOLOGY ......................................................................................................................16
4.1 General ............................................................................................................................16
4.2 Expected Conditions at Dam Site ....................................................................................17
4.3 Construction Materials ....................................................................................................17
4.4 Seismicity ........................................................................................................................18
5 LAYOUT AND CIVIL DESIGN ....................................................................................19
5.1 Introduction .....................................................................................................................19
5.2 Dam Site Locations .........................................................................................................19
5.2.1 Cross Section 44 ..............................................................................................................21
5.2.2 Cross Section 44c ............................................................................................................21
5.2.3 Cross Section 46 ..............................................................................................................22
5.2.4 Selected dam site location ...............................................................................................24
5.3 River hydraulics ..............................................................................................................24
5.4 General Layout ................................................................................................................27
5.4.1 Alternative 1 at XS 46: Construction of plant outside of river bed .................................27
5.4.2 Alternative 2 at XS 46: Construction of spillway outside of river bed ...........................28
5.4.3 Alternative 3 at XS 44c: Plant constructed in river bed ..................................................29
5.5 Power house ....................................................................................................................30
5.6 Spillway ...........................................................................................................................32
5.6.1 General Arrangement ......................................................................................................32
5.6.2 Characteristics .................................................................................................................32
5.6.3 Discharge Capacity..........................................................................................................32
Tables:
Table 3-1: Inflows to Deedoke HPP, daily and monthly values ........................................................13
Table 3-2: Yeywa Reservoir Inflow Peaks ........................................................................................14
Table 3-3: Deedoke HPP Design Flood Peaks ...................................................................................15
Table 4-1: Summary of peak ground accelerations (Yeywa) .............................................................18
Table 5-1: Tailwater level results for Cross-section 44c....................................................................26
Table 5-2: Discharge Capacity Deedoke Spillway ............................................................................33
Table 5-3: Required height of coffer dams vs. spillway gate opening for 1:50 year flood................34
Table 9-1: Assumptions for excavation material ...............................................................................49
Table 9-2: Assumed Unit Rates Deedoke Pre-Feasibility..................................................................50
Table 9-3: Total Investment Cost Alternative 1 .................................................................................51
Table 9-4: Total Investment Cost Alternative 2 .................................................................................51
Table 9-5: Total Investment Cost Alternative 3 .................................................................................52
Table 10-1: Energy Simulation Parameters .......................................................................................53
Table 10-2: Energy Simulation Results .............................................................................................54
Figures:
Figure 1-1: Locality map for Deedoke HPP (1 square = 1 km) ...........................................................8
Figure 2-1: Location of surveyed cross-sections................................................................................11
Figure 3-1: Derivation of Deedoke HPP catchment area using ArcGIS 10.0 (ESRI, 2010) .............12
Figure 3-2: Design flood hydrographs used for flood routing ...........................................................14
Figure 4-1: Location of the foreseen dam site (red) and existing quarries for HPP Yeywa ..............16
Figure 5-1: Locality map showing considered locations for the proposed Deedoke HP scheme ......20
Figure 5-2: Cross Section 44 (based on DHPI 11/2012 geodetic survey) .........................................21
Figure 5-3: Photo of cross section 44 .................................................................................................21
Figure 5-4: Cross Section 44c (based on DHPI 11/2012 geodetic survey) ........................................22
Figure 5-5: Photo of cross section 44C ..............................................................................................22
Figure 5-6: Cross Section 46 (based on DHPI 11/2012 geodetic survey) .........................................23
Figure 5-7: Photo of cross section 46 .................................................................................................23
Figure 5-8: Longitudinal Profile before construction of Deedoke Dam ............................................25
Figure 5-8: Longitudinal Profile after construction of Deedoke Dam ...............................................25
Figure 5-9: Tailwater curve for Cross-section 44c and XS 46 ...........................................................26
Figure 5-10: Layout Alternative 1 at cross section 46 .......................................................................28
Figure 5-11: Layout Alternative 2 at cross section 46 .......................................................................29
Figure 5-12: Layout Alternative 3 at cross section 44c .....................................................................30
Figure 5-13: Typical arrangement bulb turbine (source Rheinfelden) ...............................................30
Figure 5-14: Cross Section Spillway..................................................................................................32
Figure 5-15: Stilling Basin Type IV (USBR).....................................................................................33
Figure 5-16: Sketch diversion concept Alternative 1 at XS 46 (not to scale) ....................................35
Figure 5-17: Sketch diversion concept Alternative 2 at XS 46 (not to scale) ....................................35
Figure 5-18: Sketch diversion concept Alternative 3 at XS 44c (not to scale) ..................................36
Figure 10-1: Average Inflow used for the Energy Simulation ...........................................................53
Figure 10-2: Tailwater Levels at Cross Section 44c ..........................................................................54
Figure 10-3: Water Losses .................................................................................................................55
Figure 10-4: Energy Production .........................................................................................................55
Annexes:
Annex 1: Alternative dam sites
Annex 2: Layout at u/s Dam site
Annex 3: Construction Program – Alternative 3
1 INTRODUCTION
1.1 General
In October 2012, AF-Colenco Ltd. (AFC) was retained by DHPI to carry out a pre-
feasibility study for the construction of Deedoke low-head hydropower plant (HPP)
downstream of the existing Yeywa Hydropower Plant (commissioned in 2009).
Yeywa HPP is located on the Myitnge River (lower reach of Nam Tu River),
approximately 50 km southeast of Mandalay in central Myanmar. The main
components of the 790 MW Yeywa Hydro Power Plant (HPP) include the Yeywa 134 m
high RCC Dam with a Reservoir of 2630 million m3 and a 790 MW capacity Power
Station (4 No. Bulb Turbines, each with design discharge 210 m3/s). The Yeywa
Reservoir is operated to reach optimal energy production during the wet and dry
seasons. During the wet season, the reservoir often spills and the target energy
production is easily reached. During the dry season, however, the target energy
production is constrained by the available inflows to the reservoir and subsequent lower
reservoir levels. The purpose of the Deedoke low-head HPP is to supplement energy
production from Yeywa HPP, particularly during the dry season.
In May 2012, a site visit was undertaken by AF-Colenco Ltd. together with DHPI to
identify possible locations of the proposed Deedoke HPP. During the site visit, the
general hydraulics and geomorphology of the river reach were inspected. Based on the
site visit, a preliminary site located approximately 16 km downstream of Yeywa Dam on
the Myitnge River was identified as a possible location for Deedoke HPP (refer to
Figure 1-1). The site is located downstream of the Deedoke Rapids, to take advantage
of the additional head.
In October 2012, DHPI performed a survey of river cross-sections from Yeywa
Reservoir to Deedoke area (approximate distance of 18.5km). The additional
topographical information indicated that Deedoke scheme should be located further
downstream, where the valley widens into the left bank. After investigation as part of
this prefeasibility study, cross-section 46 (XS 46) and cross-section 44c (XS 44c) were
identified as preferred locations of Deedoke HPP.
In November 2012, a second site visit was realized by AFC geologists jointly with
DHPI team. During this Site Visit, the surveyed profile 44C was identified as the
preferred candidate location for the dam axis. The following surveys and investigations
were agreed: detailed topo survey of the area including pagoda and village, one
borehole on the right bank and two boreholes along the axis on the left bank; 3 seismic
refraction profiles (along dam axis and 2x from upstream to downstream on left bank).
At the time of preparation of this report, these surveys were still ongoing.
As part of the Yeywa Feasibility Study, a detailed hydrological analysis was undertaken
for the estimation of a range of design flood events (1:2 to 1:10 000 years Recurrence
Interval) based on high-quality flow data measured at Shwesaye gauging station. These
findings were also used in this Study for the estimation of the design flood peaks at
Deedoke HPP.
The Yeywa Water Management Model (developed by AF-Colenco Ltd for the operation
of Yeywa Reservoir) was updated in October 2012 with an additional 11 years of flow
data (total of 37 years). The Model was also re-calibrated based on actual measured
outflows and power output from Yeywa Power plant since its commissioning in 2009.
The updated model was used to determine the estimated releases from Yeywa Dam
during the dry and wet season. The releases from Yeywa Reservoir equal the inflows to
Deedoke HPP as the inflow of the intermediate catchment area is negligible.
2 TOPOGRAPHY
2.1 Topographical map
A topographical map (20m contour interval) was sourced from the Yeywa Feasibility
Study. The map covers the area from approximately 5km upstream of the existing
Yeywa Reservoir to approximately 4km downstream of Shwesaye gauging station
(Refer to Figure 1-1, only partly shown).
2.2 SRTM Digital Elevation Model
A 90m x 90m NASA Shuttle Radar Topographic Mission (SRTM) DEM for Myanmar
was sourced from the internet. The SRTM DEM was used in ArcGIS 10.1 to determine
the intermediate catchment area from Yeywa Reservoir to Deedoke HPP.
2.3 Topographic survey
Following from the initial Site Visit in May 2012, a geodetic survey was carried out on
the river reach between Yeywa Reservoir and Deedoke area. DHPI conducted a geodetic
survey and results were provided to AFC in September 2012. Details of the survey are
as follows:
Cross-sections were measured at 500 m intervals from Yeywa Reservoir to
14.5 km downstream of the reservoir (approximate start of Deedoke Rapids)
Cross-sections were measured at 100 m intervals from 14.5 km to 17 km
downstream of the Yeywa Reservoir
Cross-sections were measured at 500 m interval from 17km to 18.5 km
downstream of Yeywa Reservoir.
For the above survey, only the stretch above the water level was surveyed. As the
knowledge of the full channel to the bottom elevation is essential for the hydraulic
analysis of the river reach AFC further requested that all cross-sections were to be
resurveyed to include the full river section. In October 2012, a re-survey to include the
full river section was undertaken for cross-sections from 15km to 16.5km downstream
of Yeywa Reservoir only (Cross-sections 33 to 44
Figure 2-1 shows the location of the surveyed cross-sections.
3 HYDROLOGY
3.1 Deedoke HPP Catchment Area
The incremental catchment area between Yeywa Reservoir and the proposed
Deedoke HPP (based on Cross-section 44) was estimated using ArcGIS 10.1 (ESRI,
2010) based on the 90 m SRTM DEM (refer to Figure 3-1). The incremental catchment
area was estimated at 290 km2, which is about 1% of Yeywa Reservoir catchment area.
The total catchment area of Deedoke HPP is therefore at 28,496 km2.
From the above findings, it can be assumed that any contribution with respect to runoff
from the incremental area between Yeywa Reservoir and Deedoke HPP is negligible in
comparison to the runoff at Yeywa Reservoir and thus can be ignored for the purpose of
this Study.
Thus, outflows from Yeywa Reservoir can be considered as inflows to Deedoke HPP.
Also, the outflow design flood peaks from Yeywa Reservoir can be considered as the
inflow design flood peaks to Deedoke HPP.
Figure 3-1: Derivation of Deedoke HPP catchment area using ArcGIS 10.0 (ESRI,
2010)
3.3 Floods
As mentioned in chapter 3.1 the additional runoff generated from the incremental
catchment between Yeywa Reservoir and Deedoke HPP can be considered negligible in
comparison to the catchment area of Yeywa Reservoir. Thus it can be assumed that the
outflow peaks from Yeywa Reservoir are representative of the inflow peaks to Deedoke
HPP. The inflow peaks to Yeywa Reservoir are shown in Table 3-2. The peaks were
derived based on a probabilistic analysis of the annual maximum flow record at Yeywa
HPP (scaled from Shwesaye gauging station) for period 1972-2008.
Q10000,w
6'600
Q1000,w
6000 Q100,w
Q50,w
Q50,d
5000
4'200
4000
3'900
Flow (m3/s)
3000
2000 1'815
1'145
1000
0
0 200 400 600 800 1000 1200 1400 1600
Hours
4 GEOLOGY
4.1 General
The candidate dam sites are located at the upstream end (Section 44C) or downstream
end respectively (Section 46) of a large flat terrace carrying the Tha yet pin village and
downstream of the river rapids. The project site is in the vicinity of the High Tech
Quarry for Yeywa HPP on the right bank of the river. Therefore the general bedrock
conditions at the site can be well characterized by analogy to the existing quarry. The
Deedoke river rapids are located at the upstream toe of the quarry hill, along the cross
section passing through the former army quarry on the slope of the right bank. The MSP
and Asia World quarries are located further downstream on the left bank. Therefore the
general geological conditions of the project site are well known and can be
characterized by Permo-Triassic dolomitic limestone, covered by river deposits. The
only Unknown related to the geology of the project site is the depth of rock surface
beneath the alluvial cover.
Rapids
Figure 4-1: Location of the foreseen dam site (red) and existing quarries for HPP
Yeywa
quarry.
Construction materials for the embankments (coffer dam, wing dams etc.) can be
obtained from the terrace deposits, i.e. at least partly from foundation excavations for
the dam, spillway and powerhouse. Low-permeable core material has to be confirmed
by test pits or trenching in topsoil covering the alluvial terraces. High-quality rockfill
and rip-rap material shall be obtained from quarried rock in the vicinity.
4.4 Seismicity
The project is located in the same seismic region as Yeywa HPP, therefore the same
seismic design parameters shall be used as for Yeywa calculations in 2005.
The peak ground accelerations (PGA) are summarized in Table 4-1.
XS 46
XS 44c
XS 44
Figure 5-1: Locality map showing considered locations for the proposed Deedoke HP scheme
Figure 5-4: Cross Section 44c (based on DHPI 11/2012 geodetic survey)
section, the river would be artificially widened and the control removed. The
geomorphology of the river at XS 46 is also favorable for the reshaping of the river to
the extents of the permanent structure, seeing that this section is located at a wide bend
of the river.
Boundary conditions at XS 46 are as follows:
High flow velocities are expected within the original river reach at XS 46 due to
the presence of the gorge. At the gorge, the flow regime enters critical, and is
associated with high velocities (expected to be in the range of 6 m/s). Thus,
should coffer dams be built along the banks or within the river as part of the
river diversion works during construction, it may be necessary that the toe of the
dams be protected with riprap.
A Pagoda is located on the left bank about 400m upstream of XS 46. The
Pagoda must be protected from being flooded during the construction and final
commissioning of the Deedoke Scheme.
Geological conditions of the left bank might be unfavorable.
The HEC-RAS model for Deedoke was configured utilizing 20 river cross-section
profiles, obtained from recent surveys undertaken in September and October 2012. The
location of the cross-sections (refer to Figure 2-1) were informed based on specification
provided by the Engineer following the Site Visit in May 2012. In the case of XS 44c,
dummy cross-sections were also inserted from XS 45 to XS 47 to artificially widen the
river at the existing gorge (located at Cross-section 46). The model was used to
interpolate additional cross-sections between the surveyed sections.
The Manning roughness coefficients were determined based on observations made
during the May 2012 Site Visit. In general, a Manning roughness coefficient of 0.03
was used for the river bed and 0.035 for the river banks. The downstream boundary
condition type was selected as normal depth, with an approximate energy slope of
0.0005 m/m (based on the slope of the channel calculated over the full longitudinal
section).
A steady-state analysis was performed for the river reach. The following figure shows
the longitudinal profile downstream of Yeywa .
The water levels for the following discharges are presented:
The tailwater level results for Cross-section 44c and 46 can be viewed in Table 5-1 and
Figure 5-10.
Q (m3/s) XS 44c XS 46
73.0
72.5
Water Level (masl)
72.0
71.5
71.0
70.5
70.0
0 100 200 300 400 500 600 700 800 900 1000
Discharge (m 3 /s)
XS 44c XS 46
The arrangement in Figure 5-14 shows a bulb turbine with direct driven generator
without gear box. Especially the vertical dimension of the PH is reduced considerably
compared with Kaplan units; therefore the costs for the civil structure are smaller.
5.6 Spillway
5.6.1 General Arrangement
The spillway of Deedoke is a broad crested weir with seven openings equipped with
radial gates and a stilling basin. A section of the spillway is shown below in Figure
5-15.
5.6.2 Characteristics
The key characteristics of the spillway are as follows:
Crest: Number of openings 7
Type of gates radial
Sill elevation 72.5 m a.s.l.
Width of openings 20 m
With of intermediate piers approx. 5 m
Length of piers approx. 30 m
Number of intermediate piers 6
Stilling Basin: Type Type IV (USBR)
Blocks at beginning
Total Length 45 m (40 m from end of piers)
Width 170 m
Floor Elevation 67.0 masl
5.6.3 Discharge Capacity
The weir is calculated as broad crested weir. The effect of submergence has been
considered. Upstream flow velocity has been neglected (conservative assumption).
With a design flood of 4200 m3/s (Q100) and a check flood of 6600 m3/s (Q10000) the
minimum crest elevation is 83.8 masl. The deck elevation of all structures is set at
84.0 masl.
5.6.4 Stilling Basin
The Froude Number at the Beginning of the Stilling Basin together with the tail water
conditions is governing the type of hydraulic jump to be contained inside of the stilling
basin.
For Deedoke the Froude Numbers at the beginning of the stilling basin are about 3.4 for
the 100 year flood and 2.5 for the 10’000 year flood. For the conditions at Deedoke an
oscillating hydraulic jump is expected and a Type IV stilling basin is recommended by
USBR – Design of Small Dams (see Figure 5-16).
Due to the big reservoir Yeywa upstream of Deedoke no major sedimentation problems
are expected allowing the installation of baffle blocks in the stilling basin. Type IV
stilling basin is selected.
The shape of the stilling basin and the dimension of the stilling basin shall be optimised
in a hydraulic model test.
Table 5-3: Required height of coffer dams vs. spillway gate opening for 1:50 year flood
No. gates for diversion
3 gates 4 gates 5 gates 6 gates 7 gates
3
Discharge (m /s) 3900 3900 3900 3900 3900
Upstream reservoir level (masl) 83.83 81.78 80.53 79.68 78.93
Freeboard (m) 1.0 1.0 1.0 1.0 1.0
Required cofferdam level
84.83 82.78 81.53 80.68 79.93
(masl)
Crest width 4m
Height above ground 14 m
Crest length approx. 500 m
Foundation Width 46 m
Embankment volume approx. 170’000 m3
Construction of the power house will in this case only start in the second diversion
phase.
Foundation Width 40 m
Embankment volume approx. 80’000 m3
The river is diverted in the remaining right part of the river. According to HEC-RAS
analysis the maximum water level for the Q50 flood will be below 80 masl
After completion of the spillway bays a new coffer dam will be constructed to enable
powerhouse construction and the river will be diverted through spillway bays 1-4. The
cofferdam will have the following characteristics:
Max water level Q50 < 82 masl (during wet season)
Crest elevation 83 masl
Crest width 4m
Height above ground 14 m
Crest length approx. 600 m
Foundation Width 46 m
Embankment volume approx. 200’000 m3
6 ELECTRO-MECHANICAL WORKS
6.1 Turbine and Generator
It was decided to arrange a power house capable of running with only one turbine
during the dry period, when the release from Yeywa is about 300 m3/s. During wet
season, the maximum outflow from Yeywa is close to 900 m3/s and three units are
required at Deedoke to handle the flow.
6.1.1 Main Hydraulic Data
Rated discharge per unit: 300 m3/sec
Gross Head at rated Discharge: 9.07 m
Frequency: 50 Hz
Rated Speed: 85.71 rpm
Suction Head - 6.5 m
Runner Diameter: 6.1 m
Output (at rated discharge and head) 22.7 MW
Number of units 3
Assumed total efficiency (For energy simulation) 0.88
8 CONSTRUCTION PROGRAM
8.1 Introduction
The construction program is outlined for the 3 different alternatives presented in this
study. Only the main activities are shown. In reality construction phases can overlap
depending on the detailed construction program to be identified in a later stage. The
following notation is used in graphical presentation:
PHASE 1
A platform will be cut into the left bank at elevation 79 masl. This elevation
corresponds to the 1:50 year flood level (about 76.7 masl) plus 1 m freeboard. The
platform will serve as access route to the construction site.
From the left edge of the platform, the ground will be excavated at a slope of about
1:1.5 to form a coffer dam protecting the construction works in the left bank.
The slopes of the excavation of the powerhouse area depend on the material
properties (rock or loose material). If rock is not present, or the rock is fractured
(poor quality), then a 1:1.5 to 1:1 slope will need to be excavated on the left side of
the powerhouse.
PHASE 2
The powerhouse is to be constructed with first priority since it is on the critical path
regarding the overall time schedule
In parallel construction of the spillway and stilling basins can start.
PHASE 3
The excavated area to the left of the completed structure is to be back-filled to an
elevation of 84.0 masl and in line with the powerhouse / weir bridge to allow access
to the structure.
The gantry cranes shall be installed
Start of spillway gate installation
PHASE 4
The approach channel and tailwater channel, upstream and downstream of the
powerhouse, respectively, are to be finalized.
Closing of river, diversion of river through Spillway Bays 1-7
Construction of river closure dam
PHASE 5
The upstream and downstream coffer dams located along the river bank are to be
disassembled.
Installation of EM equipment, test and start of operation
8.2.2 Alternative 2
The construction phases of Alternative 2 are basically the same as for Alternative 3
(refer to chapter 8.2.3) and therefore not presented in particular. The difference to
Alternative 3 is as follows:
Phase 1 requires no coffer dams. The river bed will remain untouched and
spillway bays 1-6 will be fully constructed on the left river bank.
8.2.3 Alternative 3
PHASE 1:
During dry season build cofferdams on the left river bank with excavation
material from the spillway area.
Remaining river section is about 50-60 m at level 69 masl and 100 m at 80 masl.
Water level is lower than 80 masl for the 50 year flood.
After completion of the left bank cofferdam, excavation for 6 spillway bays is
possible also in wet season.
PHASE 2:
Construction the 6 spillway bays with stilling basin and connection dam to left
bank. This work could already start while excavation (Phase 1) is still ongoing
Installation of gantry crane
Start of spillway gate installation
PHASE 3:
Closing of bays 5 and 6 to be connected to the power house cofferdam
Removal of left bank coffer dams
Diversion of river through bays 1-4
Construction of power house cofferdams.
Excavation works in powerhouse area
PHASE 4:
Construction of power house structure
PHASE 5:
Construction of spillway bay 7
Connection power house to spillway
Filling works, connect powerhouse with right river bank with connection dam
Remove fill in bays 5 and 6
Remove cofferdams
Start installation of power house equipment
PHASE 6:
Complete installation of power house equipment
Take all spillway gates in operation
Dissembling of power house coffer dams
Commissioning of units
9 PROJECT COST
9.1 General
For the prefeasibility study a preliminary cost estimate has been carried out. The cost of
the tree alternatives have been calculated: Alternative 1 and 2, both at cross section 46
and Alternative 3 at cross section 44-c.
No details about the underground conditions have been available at the time of this
report such the calculated costs are only indicative.
The following break-down has been made in order to determine the total plant cost:
Direct Cost
o Civil Works
o Hydraulic Steel Structures
o Electromechanical Equipment
o Transmission Lines
Site Installation/ Preparatory Works
Contingency
Land Acquisition and Compensation
Administration and Engineering Services
Interest Costs are considered in the Economic Evaluation in Chapter 10.
9.2 Quantities
The basis of the quantities of the civil works is the corresponding sketches being part of
this report and the cross section 46 from the topographical survey in October 2012.
The expected type of excavation material can only be estimated at this time as no
drillings have been carried out yet. As a first approximation the following assumptions
where made:
similar, the costs for Alternative 1 are higher due to significant excavation volumes and
due to a bigger closing dam (it must be mentioned, that construction time could be
reduced for this solution as powerhouse construction can start earlier). Nevertheless the
difference in cost of the Alternatives is sensitive to underground conditions which shall
be investigated for the Feasibility Study.
A Total Construction and Equipment Costs 54'612.4 13'866.7 29'947.5 28'047.8 126'474.4
Rate with respect to total cost A 43.2% 11.0% 23.7% 22.2% 100.0%
B Reimbursement for Land Acquisition --- -
C Reimbursement for Resettlement --- 200.0
D Reimbursement for Relocation of State Road --- -
E Various Expenses 0.8% 1'011.8
F Investigations 1.0% 1'264.7
G Feasibility Study, Final Design and Tendering 2.0% 2'529.5
H Design, Supervision and Administration 7.0% 8'853.2
A Total Construction and Equipment Costs 47'276.8 13'866.7 29'947.5 27'085.3 118'176.3
Rate with respect to total cost A 40.0% 11.7% 25.3% 22.9% 100.0%
B Reimbursement for Land Acquisition --- -
C Reimbursement for Resettlement --- 200.0
D Reimbursement for Relocation of State Road --- -
E Various Expenses 0.8% 945.4
F Investigations 1.0% 1'181.8
G Feasibility Study, Final Design and Tendering 2.0% 2'363.5
H Design, Supervision and Administration 7.0% 8'272.3
A Total Construction and Equipment Costs 46'952.8 13'866.7 29'947.5 28'047.8 118'814.8
Rate with respect to total cost A 39.5% 11.7% 25.2% 23.6% 100.0%
B Reimbursement for Land Acquisition --- -
C Reimbursement for Resettlement --- 200.0
D Reimbursement for Relocation of State Road --- -
E Various Expenses 0.8% 950.5
F Investigations 1.0% 1'188.1
G Feasibility Study, Final Design and Tendering 2.0% 2'376.3
H Design, Supervision and Administration 7.0% 8'317.0
10 ENERGY EVALUATION
An energy evaluation was performed based on the hydrology presented in chapter 3.2.
The inflow used in the simulation corresponds to the average monthly inflow from 1972
to 2008 with a total inflow volume of 15200 Mio m3.
The following table presents the main results of the energy simulation:
11.2 Conclusion
The key data of the proposed scheme are:
- Reservoir FSL: 80.0 m a.s.l.
- Powerhouse with 3 bulb turbines, 22 MW each
- Average power production per year 279.6 GWh
- Discharge 3 x 300 m3/s
- Hydraulic head 8.5 m
- Spillway with 7 tainter gates H = 8 m, W = 20 m
The scheme will be located near the small Tha Yet Pin village close to the former MSP-
Quarry. Final location will depend on the optimization of the construction phases and
river diversion. A possible location some 3 km downstream should also be considered as
additional head could be gained resulting in higher installed capacity and energy
production.
The construction of the scheme will last about 6 years if the power house civil works
can only be started after diversion of the river through the spillway. Shorter construction
period could be reached by placing all structures on the left bank of the river bed. After
completion of the spillway and the civil works of the power house the river section
would then be closed by a closure dam.
The estimated cost of the scheme is between 130 and 140 mio. USD. The electro-
mechanical part is more than 50% and hydraulic steel structures represent about 10%.
The remaining 40% for civil works are relatively moderate as usual for this type of
schemes.
Energy production during the dry season (December to May) can be handled with only
one of the three units. With one unit, the produced power is 188.5 GWh per year. The
other two units will only be used during wet season and will produce additional
91 GWh per year.
7 Construction 80 dys
8 Removal 30 dys
10 Construction 50 dys
11 Removal 30 dys
82 Switchyard 85 dys
108 Base Slab & Pier & Weir (7) 150 dys
Project: Deedoke - Alternative 3 Split External Tasks Inaktiver Meilenstein Manueller Sammelrollup Progress
Date: Tue 18.12.12 Milestone External Milestone Inaktiver Sammelvorgang Manueller Sammelvorgang Deadline
Summary Inaktiver Vorgang Manueller Vorgang Nur Anfang
Page 1