Document Title:
METHOD STATEMENT FOR
CAST IN PLACE CONCRETE
Document No.:
HAC-10143-MS-CIV-001
If, despite best endeavors, a conflict should arise between this method statement and the project specification
the requirements of the latter shall be observed and this document revised, accordingly.
Prepared Checked Approved
Rev. Issue Date
Constr. Manager HSE Quality Project Manager
00 March 2022
Al Arish Simple Cycle Power Plant
Project No. 10143
HAC-10143-MS-CIV-001
Table of Contents
1.0 Scope: ............................................................................................................................................... 3
2.0 Purpose:............................................................................................................................................ 3
3.0 References: ...................................................................................................................................... 3
4.0 Responsibilities: ............................................................................................................................... 3
4.1. Project Manager:.......................................................................................................................... 3
4.2. Construction manager: ................................................................................................................ 3
4.3. Technical office Manager: ........................................................................................................... 3
4.4. Site Engineer: ............................................................................................................................... 3
4.5. QC Engineer:................................................................................................................................. 3
4.6. Laboratory Technician: ................................................................................................................ 4
4.7. Safety Officer: ............................................................................................................................... 4
4.8. Lifting Team:................................................................................................................................. 4
4.9. Supervisors, Foremen and Subcontractor(s): ............................................................................ 4
4.10. Fitters and welders: ................................................................................................................. 4
5.0 Methodology: .................................................................................................................................... 5
5.1. Pre-works: ..................................................................................................................................... 5
5.2. Blinding Concrete:........................................................................................................................ 5
5.3. “Foundation” Formwork, steel reinforcement and concrete placing activities ....................... 5
5.4. “Vertical Elements” Formwork, steel reinforcement and concrete pouring: ........................... 7
5.5. “Roof Slab” Formwork, steel reinforcement and concrete pouring. ........................................ 8
6.0 Materials matrix ............................................................................................................................... 9
7.0 Tools / Equipment ........................................................................................................................... 9
8.0 Health, Safety and Environmental Requirements ...................................................................... 10
Al Arish Simple Cycle Power Plant
Project No. 10143
HAC-10143-MS-CIV-001
1.0 Scope:
This method statement details the method and sequence for execution of all aspects of Formwork,
steel reinforcement, concrete placing and curing for all concrete works.
2.0 Purpose:
Execution of all concrete elements Concrete methodology.
3.0 References:
• Project Specification–Cast in place concrete.
• Approved shop drawings.
• All related Documents.
4.0 Responsibilities:
4.1. Project Manager:
• Monitoring all project activities regarding to project schedule.
4.5. QC Engineer:
• Shall report to the QA/QC Manager.
• Ensuring that the project inspection test plan(s) (ITP) has been briefed to and is then
followed by the construction team.
• Hold point Inspection for cast-in-place concrete.
• Inspect all the material delivered to the site with approval inspection.
• Coordinate with the third-party laboratory for all test for fresh and hard concrete
samples.
Al Arish Simple Cycle Power Plant
Project No. 10143
HAC-10143-MS-CIV-001
5.0 Methodology:
5.1. Pre-works:
• Excavation till reach the bottom level of the replacement soil under foundation as
required in project specification, drawings and geotechnical Report Recommendation.
• All surrounding facilities shall be protected before excavation activity starts.
• Submerge bottom level of excavated area for 24 hours as geotechnical report
recommendation.
• Conduct Plate Bearing Test as required in the project specification.
• Place the replacement soil layer by layer with approved compaction tests by the
engineer.
• After reach the foundation level submit surface preparation for the soil deformation
according to the approved shop drawing.
• Deliver concrete at site as indicated in project specs grade: C350 with cement type II in
proper rate. And it will be placed in layers. Vibrators will be used to avoid any concrete
defects*.
• Top of Concrete (TOC) will be monitored by surveying team.
• Surface shall be fair face finish by using helicopter troweling.
• Construct formwork so concrete members and structures are of size, shape and
alignment.
• Curing shall be applied by the approved curing compound after finishing concrete
pouring as per manufacturer’s requirements
• In case of defect occurred, Repair team will be standby to repair and concrete defects
using the approved materials.
• Quality team to establish the concrete loads check points, and all QC activities shall be
carried out according to the approved ITP.
• Standard Cylinders shall be sampled for hardened concrete testing as standards
requirements.
• Vertical water stop will be allocated and installed as the project specification in the
construction joint and will be welded with the horizontal water stop, ensure that the
overlap between the vertical and horizontal water stop about 100 mm by using welding
machine.
*Castingoperation for all the raft with one pump L 42m or any available suitable length in charge of casting
and second pump as standby if required.
Al Arish Simple Cycle Power Plant
Project No. 10143
HAC-10143-MS-CIV-001
▪ Safety boots.
▪ Safety helmets.
▪ High visibility Vest.
• Utilities shall be clearly marked and identified. Signboards identifying the type
of utilities shall be displayed at the relevant locations indicating limits of their
limits.
• Only allowed persons are permitted into the work zone. The barricades shall
be kept interlocked and continues at all the times. Any accident shall be promptly
reported to the safety department for further investigations and action.
• Barrier shall be added for the excavated borders.
• Caution tape shall be provided to all excavated area.
• Housekeeping and removing any unrequired materials to be ensured all the
time.