Project Name:

Document Title
Document No.

Method Statement
For the Installation of FAN COIL UNITS

Project :

Employer :

Project Design & Construction


Supervision Service Consultant:

Main Contractor :

Revision History

Issued for
LPS-01-HTI-MST-ME-024 0 Review and
Approval
Review by Approved by
Purpose of Prepared by QA QC Manager Project Manager
Doc. no. Rev. no. Date
submission

CONTENTS

1|27
1. PURPOSE…………………………………………………….………………………………………………………………………………………..3
2. SCOPE of Works………………………………………………………………………………………………………………………………………..3
3. REFERENCES………………………………………………………………………………………………………………………………………………3
4. ABBREVIATIONS………………………………………………………………………………………………………………………………………..3
5. RESOURCES……………………………………………………………………………………………………………………………………………….3
5.1 Equipment………………………………………………………………………………………………………………………………………….3
5.2 Manpower………………………………………………………………………………………………………………………………………….4
5.3 Material……………………………………………………………………………………………………………………………………………..4
6. RESPONSIBILITIES……..……………………………………………………………………………………………………………………………..4
6.1 Project Manager ………………………………………………………………………………....................................................4
6.2 Site Engineer/Supervisor………………..….……………………………………………………………………………………………….4
6.3 QA/QC Engineer …………………………………………………………………………………………………………………………………4
6.4 Safety Engineer/Officer ………………………………………………………………………................................................4
7. SEQUENCE OF ACTIVITIES……………………………………………………………….……………………………………………………5-7
8. QUALITY ASSURANCE/QUALITY CONTROL…………………………..…………………………………………………………………8
9. HSE ISSUES, RISK ASSESSMENT AND HAZARD ANALYSIS………………………….................................................8
9.1 Safety Lightings………………………………………………………………………………………………………………………………….8
9.2 Task Lightings…………………………………………………………………………………………………………………………………….8
9.3 Emergency Arrangement……………………………………………………………………………………………………………………8
10. ATTACHMENTS ……………………………………………………………………………………………………………………………………8
10.1 Risk Assessment……………………………………………………………………………………………………………………………9-20
10.2 Inspection Test Plan………………………………………………………………………………………………………………………21
10.3 Checklist for Fan Coil Unit…… …………………….………………………………………………………………………………-27

2|27
1. PURPOSE
The purpose of this method statement is to describe the sequential approach for Installation of Fan Coil
Unit in accordance with the contract requirements. This method statement shall ensure that the
installation of Fan Coil Units executed safely. This method statement aims to ensure that quality assurance
and quality control activities area adopted by Contractor M/s in systematic manner accordance with
project requirements, works are inspected by the Project Consultant and conformance is verified and
documented.

2. SCOPE of WORKS
This method of statement describe:
Installation shall be carried out in accordance to the relevant Qatar Design Consortium,
Neo-Spectrum and HBK Judgments. The system shall be applied in accordance to manufacturer's
recommendation. Installation shall be carried out by qualified applicator trained and approved
by the manufacturer.

This method statement is subject to the requirements as stated in the following regulatory & statutory
documents, applicable standards / specifications / building codes:
 Project Approved Shop Drawing
 Approved Project Specification
 Qatar Construction Specification 2014

3. REFERENCES
 Project Specifications / Qatar Construction Specification 2014
 Project HSE Plan
 Project Quality Plan
 Approved Material Submittal
 Shop Drawing / IFC Drawing
 QCDD Regulation

4. ABBREVIATIONS
QCS Qatar Construction Specifications
HSE Health, Safety and Environment
QA/ QC Quality Assurance and Quality Control
ITP Inspection and Test Plan
ERP Emergency Response Plan
WIR Work Inspection Request
MIR Material Inspection Request
QCDD Qatar Civil Defense Department

5. RESOURCES
5.1 Tools and Equipment
 Concrete Drilling Machine
 Drilling Machine
 Measuring Tape & Marker
 Grinding Machine
 Chain Bloc
 Standard Tool Box
 Aluminum Ladder
 Scaffolding

3|27
5.2 Manpower
 Engineers
 Supervisors
 Foreman/Lead man
 Assistant
 Scaffolding Erector
 Helpers

5.3 Materials
 Anchors
 Identification label
 Threaded rod and steel support
 Anchor bolt, Bolt, and Nuts
 Fan Coil Unit Set/Assembly
 Fan Coil Unit Accessories
6 RESPONSIBILITIES
6.1. Project Manager: The Manager Leads and Directs the Projects team for overall development of the
project. Also, he provides single point of contact in dealing with the Employer resolving Contractual,
Commercial and Technical issues during the progress of the project for Mechanical works.
6.2. Site Engineer/ Supervisor: It is the Site Engineer / Site Supervisor’s duty to organize the work force in a
safe manner and to ensure that safety and protective equipment are being properly utilized. He also
ensures that the method statement procedure is strictly followed and observes any hold-points noted
on the ITP and notify the Engineer for inspection. They shall be responsible for safe execution of the
complete activity including, but not limited to.
a) Confirming the installation locations from schedule of approved construction drawings.
b) Organizing tools and equipment required to the work site
c) Assigning work crew.
d) Toolbox talks
6.3. QA/QC Engineer: It is the QA/QC Engineer & Inspector having the responsibility to ensure that all
Inspections and Tests are carried out as per Project Requirements, Shop drawings, Approved Method
statement and Inspection Test Plan and that all are properly recorded. They shall be responsible for.
Ensuring that approved work methods and materials are being used and in conformance with project
specifications.
Carryout periodic work inspection & testing along with client representative.
Stage inspections and surveillance in accordance with ITP.
6.4. Safety Engineer/ Officer:
Enforce the implementation of the HSE Management System in the project and support the relevant
construction Supervisors on all HSE matters;
Ensure that relevant HSE information and training is provided to all personnel working in the assigned
area;
Collaborate with Supervisors in assessing training needs for personnel in the assigned area;
Reports HSE findings to the relevant construction personnel as well as the HSE MANAGER, and follow up
the status of implementation of the identified preventive and corrective actions; Carry out any other
assigned HSE activity.

4|27
7. SEQUENCE OF ACTIVITIES
7.1 METHOD OF WORK
 Coordinated drawings and the required material is arranged by the Project engineer as per
 Project specifications. T h e F a n C o i l U n i t will be installed by experienced foremen/installers.
 Before the start of the work make sure that all the HSE measures have been taken and obtain all
the necessary PPEs. If required, get a safe work permit from the HSE department.
 Preparation & Pre-Installation Work
 Works shall not proceed until an approved shop drawing or detail is issued.
 After the approval of shop drawings, the site will be checked by the Project engineer.
 Safe Access to work areas shall be provided and shall be approved by the competent person
before the commencement of works.
 Materials shall be safely moved to the work area and shall not block access/egress from the site
 Where high-risk works are involved, a safety clearance must be obtained from the safety
department.
 Secure all the necessary permits before commencing work as well as for any connected works to
others.
Storage and Handling
 To ensure that deterioration of the Fan Coil Unit does not occur during storage, the following
recommendations must be adhered to:
 Stacks should be protected from weather elements using placing tarpaulins or similar sheets over
them securely fixed to the support posts, to provide protected and shaded conditions and at the
same time allow a free passage of air around the pipes.
 Fan Coil Unit should be stored in sheltered conditions that are protected from weather elements
and accidental damage.
 The modules of FCU are packed in plastic sheeting at the factory and strapped on wooden pallets
for transport, storage, and handling at the site.
 Protect the FCU modules against dust, rain, and sunshine at the site. It should be protected from
weather elements using placing tarpaulins or similar sheets over them securely fixed to the
support posts, to provide protected and shaded conditions and at the same time allow a free
passage of air around the units.
 If modules are stacked for storage, make sure the weight of the upper module is evenly
distributed over the frame of the lower module.
 Heavy modules must not be placed on lighter ones. The modules shall be lifted or hauled one by
one.
Installation of the Fan Coil Unit FCU)
 If the site is ready for installation, the setting-out activity based on the approved shop
 If the site is ready for installation, the setting-out activity based on the approved shop drawing
will be carried out.
 Shift the FCUs to the place of installation in a safe manner using a forklift/crane as applicable.
 Mark out the location of hangers & supports needed to hang/place FCU as per approved
construction drawings.
 Drill the marked position for supports by using the drill of appropriate size in the wall/ slab/
structure.
 Insert threaded rod of appropriate diameter and length in the hole after fixing anchor bolt of
fixed size and approved brand. Care should be exercised to avoid any damage to the threads.
 Place the vibration isolators in all rods of approved quality and brand for correct deflection as
per the manufacturer’s recommendations.
5|27
 Installation of FCU Unit shall be as per the Standard Procedures and Guidelines of the
Manufacturer and Supplier.
 For ceiling mounted FCU lift the FCU to the installation height stepwise using a scaffold i.e. first
at 2 meters and then above that height. Custom-made scaffolding to be prepared for lifting the
FCU and safety officer to conduct a toolbox talk on manual handling before the start of work.
 Firmly tighten the bolts, level the equipment by using spirit/ water level, and maintain a slope
towards the condensate pipe.
 Proper support near the valve package to be provided
 Manage the slope by 1% towards condensing pan, verify the slope one more time, and finally
tighten the bolts by using proper tools.
 Connect the water inlet and outlet pipes, observing the indications given on the side of the unit.
 Correctly insulate the water supply pipes to prevent dripping during the cooling mode operation.
 Insulation of valve package shall have a provision opening during the testing and commissioning
stage.
 Connect the chilled water pipe to FCU after applying expansion joints of approved brand and
adequate expansion capacity as per construction drawing. Provide additional adequate supports
near the valves.
 Make a “U” trap near the FCU for the condensate drain pipe, and finalize the condensate drain
pipe connection with a minimum 1% slope up to the nearest condensate drain riser.
 After the complete installation of the units, inspect the exposed finish, and cleanliness of
external as good interiors, and remove foreign materials, construction debris, and dust.
 Attach and fix the identification labels, safety and warning signs of approved materials, and
correct lettering at their locations as per approved drawings and specifications.
 Make sure the proper safe covering of FCU until to proceed with final system commissioning and
final handing over to the client.
FCU Connections – Air, Chilled Water, Electrical and Condensate Drain
 Ducting connection shall be done as per approved shop drawings.
 Provide flexible duct connections as applicable/ as approved drawing.
 Provide proper duct supports as per approved drawings.
 Chilled water connection shall be made as per approved drawings.
 Ensure supply and return connections are marked properly
 Provided pipe flexible connection and other piping accessories as per approved drawings and
submittals.
 The piping shall be free of any strain and shall not exert any load on FCUs.
 Install the control valves, strainer, and isolating valves correctly as per direction of flow as per
approved drawings.
 Ensure proper operation of valve handles and sufficient space for valve installation.
 Electrical power connections shall be done as per approved drawings.
 Individual submittal for Electrical details like control panel and its controls connection shall be
submitted as separate Method Statements.
 Condensate drain piping shall be terminated at the nearest floor drain.
 Provide the “U” traps in the condensate drain piping.
 Ensure provision for cleaning of “U” traps.
 Ensure proper slope to enable easy draining.
 The piping connections to FCUs shall be pressure tested to 1.5 times the working pressures. Coils
are not included in the testing.
 Flow test of the FCUs drain tray, and condensate drain pipe and ensure water is drained out
completely.
 Ensure that the FCU drain tray flow test is drained out completely. Stagnant water is not
6|27
acceptable.
 The installation is to be offered for the Consultant’s approval.

8. QUALITY ASSURANCE/QUALITY CONTROL

8.1. Quality Assurance and Quality Control


Project Team members are responsible for the implementing quality management system throughout the
project in accordance with the Project Quality Plan and contract requirements. The Inspection and Test
Plan (ITP) applicable to this work is attached in Appendix 1, 10.2.
8.2. Inspection and Test Plan (ITP)
Inspection will be performed internally with assigned Engineer, if necessary. All concern equipment must
be calibrated and valid. Latest list of calibration report shall be forwarded to Engineer for records
8.3. Process of Dealing Defect, Deficiency and Non-conformance
Project Team has established a system to demonstrate its commitment and method through Quality
Management System Procedure for Control of Non-Conformance and Corrective & Preventive in line with
ISO 9001:2008 requirements. These Procedure demonstrate the commitment
 Identifying the Non-conforming product/process.
 Control to prevent the intended use by doing appropriate analysis on effects of non-conformity.
 Ways to deal the Non-Conformance
 Maintaining relevant records for evidence of conformance with the acceptance criteria.
 Authorizing product delivery and project hand over to Client.
8.4. Measuring and Equipment Control
Testing and Measuring Equipment shall be calibrated and certified by approved third party facilities having
a standard traceable to “Qatar National Standard” Where no National Standards is available the basis
employed for calibration shall be in accordance to the international measuring standard.
Records shall be evaluated periodically to ascertain adequacy of inspection intervals presently in use. The
system designated to ensure all measurement resources have the capability of making measurements
within limit designated as appreciate to these requirements. It shall provide in the prevention of accuracy
by prompt detection of deficiencies and timely action for their correction.
All measuring test equipment and devices having an effect having an effect on quality shall be tag, sticker
or other suitable marking, indicating calibration status. Equipment and devices used for measuring, testing
and inspection shall require an initial inspection for accuracy, or shall be proven prior to release for use on
production.
All testing equipment shall maintain control log number and recorded in calibrations status report
electronically to monitor and reschedule for future calibration immediate the expiration date.
Project Team shall maintain Calibration Status logbook which provide pre-planned calibration frequency
for all applicable test and inspection equipment.
Project Team shall to ensure that each item of inspection, measuring and test equipment is calibrated as
per manufacturer’s recommendation. Valid calibration certificate for measuring and testing equipment
shall be present and available for inspection during inspection and test.

9. HSE ISSUES, RISK ASSESSMENT AND HAZARD ANALYSIS


Implementation of Health & Safety mechanisms and checks shall be done as per contract agreement and
the approved project safety manual. The safety officer shall carryout the necessary routine inspections.

7|27
9.1. Safety Lightings: Safety lights will be used in case of power failure ensuring good illumination for the
personnel.
9.2. Task Lightings: Adequate lightings will be provided ensuring the good illumination of the working area.
Task lighting will be connected to the nearest site distribution board which is RCD protected.
9.3. Emergency Arrangements: Site general safety procedure will be followed. In case of emergency the
safety officer will stop the works. He will put in to action the emergency arrangements as described in
the safety manual.

10. ATTACHMENTS
10.1. Attachment 1 - Risk Assessment.
10.2. Inspection Test Plan (ITP) (Appendix1)
10.3. Checklist for Fan Coil Unit. (Appendix2)

8|27
Attachment1

10.1. Risk Assessment

9|27
Risk Rating Residual Rating
Item Activity Hazard & Risks Existing Control Additional Controls
S L RR S L RR
01 Project Name: Unplanned movement of vehicles. Provide a secure area for 2 3 6 1 2 2
Delivery and unloading
Document Titleof the Overturning Fan Coil Unit Equipment.
Fan Coil Unit Collision with pedestrians/  Unload the Fan Coil Unit
Document No.
operatives strictly as per the
Collision with structures
manufacturers'
Collision with other vehicles
RA Description: Risk Assessment for Installation of Fan recommendations.
Overloading andCoil Unit
falling objects MST Ref. No.: LPS-01-HTI-MST-ME-024 Rev. No.: 0 Date: 04/10/2022
Falling of people  Use mechanical aids where
Project Name: LPS-01 - 2B+G+6 RESIDENTIAL BUILDINGS possible.
Contractor: HBK Contracting Company
 Maintain
Employer:
control of loads Sheik Ali Bin Hamad Bin Khalid Al-Thani
when lifting & moving.
Note: Where the Hazard Rating remains High after control measures have been identified
Visitingthedrivers
work must not be
should be RISK / IMPACT ASSESSMENT
started and the HSE department contacted for further advice. made aware of their Health
and Safety responsibilities; MATRIX
i.e., attend Zenon induction Where the Hazard Rating remains High after any additional control
HAZARD RATING measures have been identified the work must not be started and the
and obtain a visitor pass
HSE department must be contacted for further advice.
before entry.
Likelihood
 Qualified, Competent, and
Hazard Rating Likelihood Severity authorized Environment mobile 1 2 3 4 5
equipment operator(s).
Rating 1 – 6 Low -L 1 -Unlikely 1 - First aid  Qualified, 1 - NoCompetent,
impact and 1 1 2 3 4 5
Authorized Rigger
Rating 7 – 14 Medium - M 2 –May Happen 2 –Hosp. Treatment 2 – Local impact 2 2 4 6 8 10
 Trained, Competent, and

Severity
Rating 15 – 25 High -H 3 – Likely 3 - > 3 days 3 – Minor
Authorized impact
banksman 3 3 6 9 12 15
4 - Very likely 
4 –Major Injuries Valid 3rd party certificate
4 – Moderate impact 4 4 8 12 16 20
for lifting equipment
5 - Almost certain 5 – Fatal  Valid 5 – Major impact
driving/Operating 5 5 10 15 20 25
License for the Operator. Severity x Likelihood = Hazard Rating
(Operator/Driver must have
Contractor a valid Qatari Driving
Assessed by: Reviewed by: License. Approved by:
Name: Name:  Provide exclusion zone(s) Name:
Construction where the activity is
Project HSE Manager Project Manager
Signature: Signature: occurring. Signature:
 Wheel chocks should be
used in addition to the
Date: Date: Date:
brake, particularly if any
slope is present.
 Never be downhill of a
moving load.
 Workers on foot should
never be on the opposite
side of a truck from a 10 | 2 7
forklift while it is loading or
unloading material.
11 | 27
Appendix 1
10.2. Inspection Test Plan (ITP)

12 | 27